Request for Copy of Miller Act Bond Form

Download your
Request for Copy of Miller Act Bond Form

About Request for Copy of Miller Act Bond Form

If you’re working on a federal construction project, you’re legally entitled to receive a copy of the Miller Act Bond. All you have to do is ask! Unfortunately, federal construction projects are not immune from payment issues. However, thanks to the Miller Act, many federal projects will have a payment bond in place to protect the subcontractors, material suppliers, and others from non-payment and other payment risks.

Download this form and send it to the prime contractor on the project. By law, they will have to respond to you.

Request for Copy of Miller Act Bond Form

Need to send a Request for Copy of Miller Act Bond Form?

We’re the Miller Act experts. With us it’s fast, easy, affordable, and done right!
mechanics lien county recorder e-filing.
Forms

Other National Forms

FAQs about Request for Copy of Miller Act Bond Form

Recent Questions & Answers About National Miller Act
Kansas Statute 16-1907

16-1907: Provisions Waiving Rights to Collect Damages for Delays, Void, Unenforceable -- Does this statute apply to a contractor working for the Federal Government (Dept...

What is the next step on a Bond Claim/ Construction Lien.

Yes we filed a lien on a project which went to the GC's bond. The claim was against the Subcontractor that hired us. The GC...

federal courthouse emergency water damage.$ 172,000.hired by gsa locally, told it was to big for them to pay me.. had to sign on with a gsa recommended 8a company. GSA paid 8a company but they never paid me. Miller act does not require a bond, according to gsa because it was not construction.I am a disabled veteran, from the 60s. I paid all my subs, 8a company has several judgements already against them. GSA still gives that company government work. So others can be taken advantage .

How do I get my money

Cost-Reimbursement Contracts

What remedies are available to a "materials supplier who supplies materials to a General Contractor who has entered into a Cost-Reimbursement Contract with the US...

How do you proceed with a Preliminary Notice if our customer will not provide the address to a Federal Public job.

We have a customer that I'm trying to enter in as a New Project but they will not provide the address to where the work...

Can a prime contractor hold retention on a federally funder project if thier contract is not subject to retention? What subpart is that located?

our customer is withholding retention on 2 federal projects because it was in a contract we doc u signed and did not catch, but we...

Ask an Expert for Free