Levelset visitors can also get a free Procore account.

Oregon Retainage Guide and FAQs

Ready? Build Your Free Oregon
Retainage Now

Get Your Lien Waiver Now
Oregon Retainage FAQs

Oregon Retainage Overview

Oregon Retainage Requirements


  • Private Jobs
  • Public Jobs
  • Top Links
Retainage 5% Icon
Retainage Limit

Retainage from any party may not exceed 5% of the value of the work completed.


Payment Period Icon
Pay Period

Not specified in statute.


YES
PROCESS
There is a Process to Recover

Yes, written notice and timing provisions apply.


No Escrow Icon
Not Held In Escrow

In Oregon, contractors and owners do not need to hold retainage funds in a separate escrow account.

Exception: If the contract price is over $500,000, retainage must be held in an interest-bearing, escrow account.

Retainage 5% Icon
5 Percent

Retainage cannot exceed 5% unless the charter for the public entity provides for a higher rate.


Payment Period Icon
Pay Period

After 50% completion, if the work is satisfactory, the retainage rate may be reduced or eliminated upon written request by contractor and written approval of surety.


YES
PROCESS
There is a Process to Recover

Yes, written request with approval of surety.


No Escrow Icon
Not Held in Escrow

In Oregon, the contracting agency doesn't need to hold retainage funds in a separate escrow account.

Exception: If the contract price is over $500,000, retainage must be held in an interest-bearing, escrow account.

Retainage serves two general purposes: (1) To provide an incentive to the contractor or subcontractor to complete the project; and (2) To give the owner some protection against problems like liens, contractual defaults, delays, and more. In most states, laws exist to regulate how the parties use the retainage concept, mostly protecting some parties against abuse of the tool from others. The following are resources, legal information, and frequently asked questions about Oregon’s retainage requirements. The Oregon retainage statutes are reproduced below on this page.

Oregon Retainage Frequently Asked Questions

Oregon Retainage Private Projects FAQs

Does Oregon limit the amount of retainage that can be withheld from a contractor?

Retainage from any party may not exceed 5% of the value of the work completed.

How long can a party withhold retainage in Oregon?

This is not specified for private projects in the Oregon retainage statute.

Does Oregon require retained funds be deposited in a special account? Can securities be substituted for retainage?

Retained funds must be held in an interest-bearing, escrow account if the contract price exceeds $500,000.

*Applies to all contracts entered into after Jan. 1, 2020.

Securities may be substituted for retainage.

How can I make a claim to recover retainage in Oregon?

A contractor must notify the owner after fully paying a subcontractor in order to recover retained amounts.

Is there a specific notice required to recover retainage in Oregon?

The contractor shall notify the owner when the contractor pays a subcontractor in full and the owner shall, within 15 days after receiving the notice, pay the contractor the amount due the contractor in retainage.

Oregon Retainage Public Projects FAQs

Does Oregon limit the amount of retainage that can be withheld from a contractor?

Retainage may not exceed 5% of any progress payment unless charter of the public entity provides for a higher rate.

How long can a party withhold retainage in Oregon?

After 50% completion of the work, if the work is satisfactory, the retainage rate may be reduced or eliminated upon written request by contractor with written approval of surety. When work is 97.5% complete, the public entity may reduce the withheld amount to solely the total for the value of the work not yet completed (with no request).

The owner, contractor, or subcontractor has 30 days after contract is completed and work has been accepted by owner.

Does Oregon require retained funds be deposited in a special account? Can securities be substituted for retainage?

Retained funds must be held in an interest-bearing, escrow account if the contract price exceeds $500,000.

*Applies to all contracts entered into after Jan. 1, 2020.

Securities, bonds, or other similar instruments may be substituted for retainage. The funds may be deposited with the contracting agency or in a bank or trust company.

How can I make a claim to recover retainage in Oregon?

After substantial completion, the contractor must submit a written request with approval of surety. Once notice is given to owner, they have 15 days to accept or notify contractor or subcontractor of work yet to be performed under contract.

Is there a specific notice required to recover retainage in Oregon?

See above.

Need More Help with Oregon Retainage? We're Here.

Oregon Retainage
Recent Questions & Answers

Colorado Retainage Law

We are a subcontractor in Colorado, we entered into a contract for $43K. The contract that was signed states that retainage will be 10%, however...

I have a question regarding the proper deduction of retainage at each billing.

We are holding a 5% Retainage on this current job. The question I have is this. We do our billings by AIA Forms g702 &...

Can a customer hold back retainage if not previously specified in the contract?

I am the prime contractor on a residential addition. We finished the project and the customer submitted payment, but held back 10% on the project...

How to file a lien in Oregon

Need to file a Oregon mechanics lien? File your mechanics lien with Levelset, the lien experts quickly and easily. Or you can follow the 3 steps below to file a lien yourself with Levelset's free information.

Want to Learn More about How Oregon Contractors Pay?
Truebeck Construction (formerly BNBT Builders)
Rating 5.0
Dallas Glass
Rating 5.0
Culver Glass
Rating 5.0
Tom Malot Construction
Rating 5.0
See other Lists of Contractors and How to Best Work With Them

Oregon Retainage Statutes

Getting informed about prompt payment laws is important. An examination of Oregon’s retainage laws, the rules and regulations related to the amount and timing of allowable retained payments, is important to know your rights and responsibilities as a party on a construction project. Oregon’s specific laws can be found in: OR. Rev. Stat. § 701.410 et seq. for private projects and §279C.550 et seq. for public projects; and are reproduced below. Updated as of 2021.

Retainage Statute on Private Projects

§ 701.410. Definitions

(1) As used in ORS 279C. 555, 279C. 570, 701.410, 701.420, 701.430, 701.435 and 701.440:

(a) “Construction” means:

(A) Excavating, landscaping, demolishing and detaching existing structures, leveling, filling in and otherwise preparing land for the making and placement of a building, structure or superstructure;

(B) Creating or making a building, structure or superstructure; and

(C) Altering, partially constructing and doing repairs in and upon a building, structure or superstructure.

(b) “Contractor” means a person that contracts with an owner on predetermined terms to be responsible for performing all or part of a job of construction in accordance with established specifications or plans, and that retains control of the means, method and manner of accomplishing the desired result.

(c) “Owner” means a person that is or claims to be the owner in fee or a lesser estate of the land, building, structure or superstructure on which construction is performed and that enters into an agreement with a contractor for the construction.

(d) “Subcontractor” means a person that contracts with a contractor or another subcontractor on predetermined terms to be responsible for performing all or part of a job of construction in accordance with established specifications or plans.

(2) As used in ORS 701.410, 701.420, 701.430, 701.435 and 701.440, “retainage” means the difference between the amount a contractor or subcontractor earns under a construction contract and the amount the owner pays on the contract to the contractor, the amount the contractor pays on the contract to the subcontractor or the amount the subcontractor pays on the contract to another subcontractor.

§ 701.420. Partial payment; retainage; effect; interest; notice of completion; payment by contractor and owner

(1) Partial payment is allowed and may be made on contracts for construction and home improvement. An owner, contractor or subcontractor may withhold as retainage an amount equal to not more than five percent of the contract price of the work completed. Partial payment allowed under this subsection is not acceptance or approval of some of the work or a waiver of defects in the work.

(2)

(a) The owner, contractor or subcontractor shall pay interest at the rate of one percent per month on the final payment due the contractor or subcontractor. The interest shall commence 30 days after the contractor or subcontractor has completed and the owner has accepted the work under the contract for construction for which the final payment is due. The interest shall run until the date when final payment is tendered to the contractor or subcontractor. When the contractor or subcontractor considers the work that the contractor or subcontractor is contracted to perform to be complete, the contractor or subcontractor shall notify the party to whom the contractor or subcontractor is responsible for performing the construction work under the contract. The party shall, within 15 days after receiving the notice, either accept the work or notify the contractor or subcontractor of work yet to be performed under the contract. If the party does not accept the work or does not notify the contractor or subcontractor of work yet to be performed within the time allowed, the interest required under this subsection shall commence 30 days after the end of the 15-day period.

(b) If the contract price exceeds $500,000, the owner, contractor or subcontractor shall place amounts withheld as retainage into an interest-bearing escrow account. Interest on the retainage amount accrues from the date the payment request is approved until the date the retainage is paid to the contractor or subcontractor to which it is due.

(3) When a contractor pays a subcontractor in full, including the amount the contractor withheld as retainage, the owner with whom the contractor has the contract shall pay the contractor, out of the amount that the owner withheld from the contractor as retainage, a sum equal to the amount of retainage that the contractor paid the subcontractor. The contractor shall notify the owner when the contractor pays a subcontractor in full under this section and the owner shall, within 15 days after receiving the notice, pay the contractor the amount due the contractor under this subsection. Interest on the amount due the contractor at the rate of one percent per month shall commence 30 days after the owner receives notice of full payment to the subcontractor.

§ 701.430. Performance bond; terms; effect of not obtaining bond

A contractor or subcontractor may execute and deliver to the owner, contractor or subcontractor before the commencement of construction for which the contractor or subcontractor will be responsible for performing a good and sufficient bond in a sum equal to the contract price for the faithful performance of the contract. The term of the bond obtained under this subsection must extend to include the period during which claims of lien or notices of other encumbrances based on the construction performed under the contract may be filed under applicable law. The bond must be approved by the owner, contractor or subcontractor entitled to withhold retainage. A faithful performance bond delivered under this section must include, but not be limited to, provisions to the effect that:

(1) The obligations of the contract must be faithfully performed;

(2) Payment must promptly be made to all persons supplying labor or materials to the contractor or subcontractor for prosecution of the work provided in the contract;

(3) All contributions due the Industrial Accident Fund and the Unemployment Compensation Trust Fund from the contractor or subcontractor in connection with the performance of the contract must be made promptly; and

(4) All sums required to be deducted and retained from the wages of employees of the contractor or subcontractor pursuant to the Personal Income Tax Act of 1969, must be paid over to the Department of Revenue.

§ 701.435. Deposits in lieu of cash retainage

(1) When a contractor on a public contract deposits bonds, securities or other instruments under ORS 279C. 560 (4), if the subcontract price exceeds $50,000 and constitutes more than 10 percent of the cost of the public contract, a subcontractor on the public contract may deposit bonds, securities or other instruments with the contractor or in a bank or trust company for the contractor to hold for the contractor’s benefit in lieu of moneys held as retainage. If the contractor accepts the bonds, securities or other instruments deposited as provided in this subsection, the contractor shall reduce the moneys held as retainage in an amount equal to the value of the bonds, securities and other instruments and pay the amount of the reduction to the subcontractor in accordance with ORS 701.420 and 701.430. Interest or earnings on the bonds, securities or other instruments shall accrue to the subcontractor.

(2) When a contractor on a public contract elects to have the public contracting agency deposit the accumulated retainage in an interest-bearing account under ORS 279C. 560 (5), the contractor, within 30 days following payment of the final amount due for construction of the public improvement, shall pay to each subcontractor who performed work on the construction the subcontractor’s proportional share of the interest earnings that accrued to the contractor as a result of the election. A subcontractor’s share of the total amount of interest earnings under this subsection shall be determined by the proportion that the amount of retainage withheld from the subcontractor bears to the amount of retainage withheld from the contractor and the length of time the retainage was withheld from the subcontractor. A share of the interest earnings shall be paid to a subcontractor under this subsection only when:

(a) Retainage is withheld from the subcontractor for more than 60 days after the day on which the first partial payment was due the subcontractor under the terms of the subcontract; and

(b) The amount of interest earnings due the subcontractor exceeds $100.

(3) If the contractor incurs additional costs as a result of the exercise of an option described in subsection (1) or (2) of this section, the contractor may recover the costs from the subcontractor by reducing the final payment. As work on the subcontract progresses, the contractor shall, upon demand, inform the subcontractor of all accrued additional costs.

(4) Bonds, securities and other instruments deposited or acquired in lieu of retainage, as permitted by this section, must be of a character approved by the Director of the Oregon Department of Administrative Services, including but not limited to:

(a) Bills, certificates, notes or bonds of the United States.

(b) Other obligations of the United States or agencies of the United States.

(c) Obligations of a corporation wholly owned by the federal government.

(d) Indebtedness of the Federal National Mortgage Association.

(e) General obligation bonds of the State of Oregon or a political subdivision of the State of Oregon.

(f) Irrevocable letters of credit issued by an insured institution, as defined in ORS 706.008.

§ 701.440. Applicability to federal projects

ORS 279C. 555, 701.410, 701.420 and 701.430 do not apply when the owner is the United States or any agency thereof or when the construction is paid for, in whole or in part, with federal moneys.

Retainage Statute on Public Projects

§ 279C.550. "Retainage" defined

As used in ORS 279C. 550 to 279C. 570, “retainage” means the difference between the amount earned by a contractor on a public improvement contract and the amount paid on the contract by the contracting agency.

§ 279C.555. Withholding of retainage

The withholding of retainage by a contractor or subcontractor on public improvement contracts shall be in accordance with ORS 701.420.

§ 279C.560. Form of retainage; procedures for holding and payment

(1) Unless a contracting agency that reserves an amount as retainage under ORS 279C. 570 (7) finds in writing that accepting a bond or instrument described in paragraph (a) or (b) of this subsection poses an extraordinary risk that is not typically associated with the bond or instrument, the contracting agency in lieu of withholding moneys from payment shall accept from a contractor:

(a) Bonds, securities or other instruments of a character described in subsection (6) of this section that are deposited as provided in subsection (4) of this section; or

(b) A surety bond deposited as provided in subsection (7) of this section.

(2) A contracting agency that holds moneys as retainage under ORS 279C. 570 (7) shall:

(a) Hold the moneys in a fund and pay the moneys to the contractor in accordance with ORS 279C. 570; or

(b) At the election of the contractor, pay the moneys to the contractor in accordance with subsection (4) or (5) of this section and in a manner authorized by the Director of the Oregon Department of Administrative Services.

(3) If the contracting agency incurs additional costs as a result of the exercise of an option described in subsection (1) or (5) of this section, the contracting agency may recover the costs from the contractor by reducing the final payment. As work on the contract progresses, the contracting agency shall, upon demand, inform the contractor of all accrued costs.

(4) The contractor may deposit bonds, securities or other instruments with the contracting agency or in a bank or trust company for the contracting agency to hold for the contracting agency’s benefit in lieu of moneys held as retainage. If the contracting agency accepts bonds, securities or other instruments deposited as provided in this subsection, the contracting agency shall reduce the moneys held as retainage in an amount equal to the value of the bonds, securities and other instruments and pay the amount of the reduction to the contractor in accordance with ORS 279C. 570. Interest or earnings on the bonds, securities or other instruments shall accrue to the contractor.

(5) If the contractor elects, the contracting agency shall deposit the retainage as accumulated in an interest-bearing account in a bank, savings bank, trust company or savings association for the benefit of the contracting agency. When the contracting agency is a state contracting agency, the account must be established through the State Treasurer. Earnings on the account accrue to the contractor.

(6) Bonds, securities and other instruments deposited or acquired in lieu of retainage, as permitted by this section, must be of a character approved by the Director of the Oregon Department of Administrative Services, including but not limited to:

(a) Bills, certificates, notes or bonds of the United States.

(b) Other obligations of the United States or agencies of the United States.

(c) Obligations of a corporation wholly owned by the federal government.

(d) Indebtedness of the Federal National Mortgage Association.

(e) General obligation bonds of the State of Oregon or a political subdivision of the State of Oregon.

(f) Irrevocable letters of credit issued by an insured institution, as defined in ORS 706.008.

(7) The contractor, with the approval of the contracting agency, may deposit a surety bond for all or any portion of the amount of funds retained, or to be retained, by the contracting agency in a form acceptable to the contracting agency. The bond and any proceeds of the bond must be made subject to all claims and liens and in the same manner and priority as set forth for retainage under ORS 279C. 550 to 279C. 570 and 279C. 600 to 279C. 625. The contracting agency shall reduce the moneys the contracting agency holds as retainage in an amount equal to the value of the bond and pay the amount of the reduction to the contractor in accordance with ORS 279C. 570. Whenever a contracting agency accepts a surety bond from a contractor in lieu of retainage, the contractor shall accept like bonds from a subcontractor or supplier from which the contractor has retainage. The contractor shall then reduce the moneys the contractor holds as retainage in an amount equal to the value of the bond and pay the amount of the reduction to the subcontractor or supplier.

§ 279C.565. Limitation on retainage requirements

Unless otherwise specifically included by statute, the provisions of ORS 279C. 560 or 279C. 625 apply only as between the contracting agency or public body and the party with whom it contracts.

§ 279C.570. Prompt payment policy; progress payments; retainage; interest; exception; settlement of compensation disputes

(1) It is the policy of the State of Oregon that all payments due on a public improvement contract and owed by a contracting agency shall be paid promptly. No contracting agency is exempt from the provisions of this section.

(2) Contracting agencies shall make progress payments on the contract monthly as work progresses on a public improvement contract. Payments shall be based upon estimates of work completed that are approved by the contracting agency. A progress payment is not considered acceptance or approval of any work or waiver of any defects therein. The contracting agency shall pay to the contractor interest on the progress payment, not including retainage, due the contractor. The interest shall commence 30 days after receipt of the invoice from the contractor or 15 days after the payment is approved by the contracting agency, whichever is the earlier date. The rate of interest charged to the contracting agency on the amount due shall equal three times the discount rate on 90-day commercial paper in effect at the Federal Reserve Bank in the Federal Reserve district that includes Oregon on the date that is 30 days after receipt of the invoice from the contractor or 15 days after the payment is approved by the contracting agency, whichever is the earlier date, but the rate of interest may not exceed 30 percent. If the contract price exceeds $500,000, the contracting agency shall place amounts deducted as retainage into an interest-bearing escrow account. Interest on the retainage amount accrues from the date the payment request is approved until the date the retainage is paid to the contractor to which it is due.

(3) Interest shall be paid automatically when payments become overdue. The contracting agency shall document, calculate and pay any interest due when payment is made on the principal. Interest payments shall accompany payment of net due on public improvement contracts. The contracting agency may not require the contractor to petition, invoice, bill or wait additional days to receive interest due.

(4) When an invoice is filled out incorrectly, when there is any defect or impropriety in any submitted invoice or when there is a good faith dispute, the contracting agency shall so notify the contractor within 15 days stating the reason or reasons the invoice is defective or improper or the reasons for the dispute. A defective or improper invoice, if corrected by the contractor within seven days of being notified by the contracting agency, may not cause a payment to be made later than specified in this section unless interest is also paid.

(5) If requested in writing by a first-tier subcontractor, the contractor, within 10 days after receiving the request, shall send to the first-tier subcontractor a copy of that portion of any invoice, request for payment submitted to the contracting agency or pay document provided by the contracting agency to the contractor specifically related to any labor or materials supplied by the first-tier subcontractor.

(6) Payment of interest may be postponed when payment on the principal is delayed because of disagreement between the contracting agency and the contractor. Whenever a contractor brings formal administrative or judicial action to collect interest due under this section, the prevailing party is entitled to costs and reasonable attorney fees.

(7) A contracting agency may reserve as retainage from any progress payment on a public improvement contract an amount not to exceed five percent of the payment. As work progresses, a contracting agency may reduce the amount of the retainage and the contracting agency may eliminate retainage on any remaining monthly contract payments after 50 percent of the work under the contract is completed if, in the contracting agency’s opinion, such work is progressing satisfactorily. Elimination or reduction of retainage shall be allowed only upon written application by the contractor, and the application shall include written approval of the contractor’s surety. However, when the contract work is 97.5 percent completed the contracting agency may, at the contracting agency’s discretion and without application by the contractor, reduce the retained amount to 100 percent of the value of the contract work remaining to be done. Upon receipt of a written application by the contractor, the contracting agency shall respond in writing within a reasonable time.

(8) The retainage held by a contracting agency shall be included in and paid to the contractor as part of the final payment of the contract price. The contracting agency shall pay to the contractor interest at the rate of 1.5 percent per month on the final payment due the contractor, interest to commence 30 days after the work under the contract has been completed and accepted and to run until the date when the final payment is tendered to the contractor. The contractor shall notify the contracting agency in writing when the contractor considers the work complete and the contracting agency shall, within 15 days after receiving the written notice, either accept the work or notify the contractor of work yet to be performed on the contract. If the contracting agency does not, within the time allowed, notify the contractor of work yet to be performed to fulfill contractual obligations, the interest provided by this subsection shall commence to run 30 days after the end of the 15-day period.

(9)

(a) The contracting agency shall pay, upon settlement or judgment in favor of the contractor regarding any dispute as to the compensation due a contractor for work performed under the terms of a public improvement contract, the amount due plus interest at the rate of two times the discount rate, but not to exceed 30 percent, on 90-day commercial paper in effect at the Federal Reserve Bank in the Federal Reserve district that includes Oregon on the date of the settlement or judgment, and accruing from the later of:

(A) The due date of any progress payment received under the contract for the period in which such work was performed; or

(B) Thirty days after the date on which the claim for the payment under dispute was presented to the contracting agency by the contractor in writing or in accordance with applicable provisions of the contract.

(b) Interest shall be added to and not made a part of the settlement or judgment.

Trusted by Thousands of Oregon Contractors Like You
For Help With Retainage