On residential projects, when Mechanic Lien Agent identified in building permit, 30 day preliminary notice required.
Virginia Mechanics Lien Guide and FAQs
Quicklinks
“Levelset takes something that is pretty complex and makes it easy.”
Ready to file a lien in Virginia?
Not sure? Calculate your deadline for free.
Virginia lien law deadlines for:
Lien must be filed within 90 days from last day of the month which labor or materials furnished, & within 90 days from time the work is completed.
In Virginia, an action to enforce a mechanics lien must be initiated within the later of 6 months from date lien recorded or 60 days from the completion or termination of the project. This deadline may not be extended, and failure to meet the deadline results in the lien being rendered unenforceable.
On residential projects, when Mechanic Lien Agent identified in building permit, 30 day preliminary notice required. On other projects to make owner or general personally liable - not later than 30 days after completion of entire work.
Lien must be filed within 90 days from last day of the month which labor or materials furnished, & within 90 days from time the work is completed.
In Virginia, an action to enforce a mechanics lien must be initiated within the later of 6 months from date lien recorded or 60 days from the completion or termination of the project. This deadline may not be extended, and failure to meet the deadline results in the lien being rendered unenforceable.
On residential projects, when Mechanic Lien Agent identified in building permit, 30 day preliminary notice required. On other projects to make owner or general personally liable - not later than 30 days after completion of entire work.
Lien must be filed within 90 days from last day of the month which labor or materials furnished, & within 90 days from time the work is completed.
In Virginia, an action to enforce a mechanics lien must be initiated within the later of 6 months from date lien recorded or 60 days from the completion or termination of the project. This deadline may not be extended, and failure to meet the deadline results in the lien being rendered unenforceable.
Virginia Mechanics Lien FAQs
Who can file a Virginia mechanics lien?
In Virginia, parties who furnish labor, materials, or equipment valued at $150 or more for the construction, removal, repair, or improvement of any building or structure permanently annexed to land is entitled to mechanics lien rights protection.
It appears that suppliers to suppliers may be entitled to lien rights in Virginia. Mechanics lien protection also extends to design professionals, such as architects and engineers.
Is a written contract required to file a mechanics lien in Virginia?
No. Although it’s never a good idea to work without a written contract, it is not required in order to file a mechanics lien in Virginia.
• Dive deeper: Can You File a Lien Without a Written Contract?
Can an unlicensed contractor file a Virginia mechanics lien?
No. Anyone who is required to be licensed by the Virginia Board for Contractors for the work performed, and aren’t, are not entitled to lien rights. In fact, the lien form itself requires the claimant’s license or certificate number, along with their expiration dates. Furthermore, any party who supplies labor and/or materials to an unlicensed contractor or subcontractor will not have lien rights on the project either.
• Learn how to get licensed: Virginia Contractor Licensing Rules & Requirements
When is the deadline to file a Virginia mechanics lien?
In Virginia, a potential lien claimant must file a mechanics lien within 90 days from the last day of the last month in which he furnished labor and/or materials to the project (it must also be within 90 days from the completion or termination of the project).
However, the lien may ONLY include amounts for labor and/or materials provided in the 150 days preceding the day labor/materials were last furnished by the claimant – if the lien includes labor/materials provided more than 150 days from the last day the lien claimant furnished labor/materials the lien will be invalid. The lien claimant may file more than one lien notice, if necessary.
Also, to make the owner and/or general contractor personally liable, the lien claimant must file the mechanics lien after the claimant furnished labor and/or materials to the project, and within 30 days of completion or termination of the project. The property owner’s and/or general contractor’s liability will be limited to the amount owed to the party with whom the claimant contracted at the time the notice of lien is filed.
• Virginia’s Payment Chain- Why It’s Important to Lien Early
What information should be included in a Virginia mechanics lien?
Virginia has separate requirements for the mechanics lien form (referred to as a Memorandum of Lien) depending on the claimant’s role. It’s important to ensure that all of the information provided is as accurate as possible. However, minor errors will not affect the lien’s validity in VA. The following information needs to be included on the lien form itself:
• Owner’s name & address;
• Claimant’s name & address;
• Contractor license/certificate number, date of issuance, and expiration date (if applicable);
• Description of labor and/or materials;
• Amount claimed (and any amounts that will become due and the date such amounts will become due);
• Property description;
• Date from which interest is claimed;
• (GCs only) Certification of service of lien on owner; &
• (Sub & Sub-subs only) General contractor’s name & hiring subcontractor’s name (if applicable)
Download a free Virginia Mechanics Lien form here
→ VA Mechanics Lien form for GCs
→ VA Mechanics Lien form for Subs
→ VA Mechanics Lien form for Sub-subs
Does a Virginia mechanics lien need to include a legal property description?
No, a full legal property description isn’t required. In Virginia, a mechanics lien requires a “brief description of the property” on which the lien is claimed. Virginia mechanics lien law holds that “no inaccuracy…in the description of the property to be covered by the lien, shall invalidate the lien, if the property can be reasonably identified with the description given…and is not willfully false.”
Can attorney fees, collection costs, or other amounts be included in the lien amount?
Attorney fees and collections costs cannot be included in the lien amount in Virginia. An important thing to note is that amount can only include the value of labor and/or materials provided in the preceding 150 days of last furnishing (also referred to as the 150-Day Rule). However, a claimant may include retainage and payments that have yet to be due because the hiring party has yet to be paid.
Does a Virginia mechanics lien need to be notarized?
Yes, Virginia law requires that a mechanics lien must be notarized to be valid and accepted for recording.
• Learn more about notarizing construction payment documents
• Options for notarizing mechanics liens remotely
Can I file a Virginia lien on a condominium project?
Yes, to the extent you are a party otherwise allowed to file a mechanics lien. If the work is performed on common areas of the condominium , a single claim may be filed. However, if the work performed is on multiple units, the claim must apportion amounts due for each unit.
• For more on this: The Strict Nature of Virginia’s Apportionment Rules
Furthermore, for a claim to be valid, the claimant must file a document stating the nature of the lien, the total value of work contracted for, and the portion allocated to each unit. (§43-3(B))
Where do I file and record a Virginia mechanics lien?
Virginia mechanics liens are documents recorded in the county clerk’s office. For your mechanics lien to be properly recorded, it must be filed in the office of the county where the property is located. Each county has its own unique rules and requirements.
To help you, we’ve assembled all the offices in Virginia that record mechanics lien claims. These pages will walk you through the county’s specific formatting requirements, fees, filing procedures, and answers to frequently asked questions.
• Be prepared: Essential Questions to Ask The County Recorder Before Filing a Lien
How do I actually file a Virginia mechanics lien?
There are a lot of questions on this page about who can file a Virginia mechanics lien, when it must be filed, what types of rules apply, and more. But you may be wondering something much more practical: how do I actually get my mechanics lien recorded and filed?
• For a full breakdown of the process, you may want to consult: How to File a Virginia Mechanics Lien | A Step-by-Step Guide to Get You Paid
Do I need to send notice that the mechanics lien was recorded in Virginia?
Yes, and this requirement varies depending on the claimant’s role on the project, all of which should be sent by registered or certified mail.
• General contractors must give a copy of the claim to the owner prior to the lien filing, and Certification of the Mailing must be filed with the lien claim.
• Subcontractors must send the first page of the lien claim “Notice to Owner” to the owner at the time of filing.
• All other claimants must send the first page of the lien claim “Notice to Owner” to the owner and the general contractor at the time of filing.
When is the deadline to enforce a Virginia mechanics lien, or, how long is my lien effective?
In Virginia, an action to enforce a mechanics lien must be initiated 6 months of filing the claim, or 60 days from completion or termination of the project; whichever is later. Otherwise, the claim will expire and no longer be enforceable.
Can I collect the entire unpaid amount from the property owner if they have already paid the general contractor in full in Virginia?
No, Virginia is what we refer to as an “unpaid balance lien state.” Under Virginia’s lien statutes, a lien cannot exceed the amount in which the hiring party is owed by the owner/general contractor/subcontractor (where applicable).
Does a Virginia lien have priority over pre-existing mortgages or construction loans?
Priority of mechanics liens in Virginia is complicated. Prior recorded deeds of trust have priority over mechanics liens to the extent of the value of the land, but mechanics liens have priority over prior recorded deeds of trust to the extent of the value of the building. Mechanics liens have priority over all deeds of trust recorded after the commencement of work. However, as to repair and improvement work to pre-existing structures, prior recorded deeds of trust have priority to the extent of both the land and the building.
As to competing mechanics liens, priority is in reverse order of tier:
- Sub-subcontractors
- Subcontractors
- General contractors
Who cancels the Virginia mechanics lien if/when I get paid?
Virginia’s mechanics lien law does not have a specific provision as to who is required to have the lien released upon satisfaction, and when the lien release is required. However, generally speaking, any payment to a lien claimant after a lien has been filed is made in consideration of, and contingent upon, the lien being released by the lien claimant.
People are asking Virginia construction attorneys:
Can I increase an already recorded lien in Virginia?
Can I file mechanic lien?
Can I file a mechanics lein?
See link below to applicable statutory requirements. Note that unless you fit into one of th elimited exceptions, your right to recover by any means (lien, breach of contract, etc.) is prohibited and you could also be subject to both criminal and civil penalties.
See https://law.lis.virginia.gov/vacode/title54.1/chapter11/section54.1-1115/
Best rated general contractors in Virginia
6 essential things to know about Virginia mechanics lien law
Contractors & suppliers have strong lien rights in Virginia. If a contractor or supplier isn’t paid on an Virginia job, they can turn to filing a lien to speed up payment and protect themselves. However, there are specific requirements and rules that must be followed. Here are 6 essential things you need to know about Virginia’s mechanics lien law.
Most licensed parties have mechanics lien rights
In Virginia licensed parties that provide service or labor for a construction project, removal or repair or improvement on a completed project is entitled to mechanics lien (given that the total contract amount is over $50). This extends to 3rd tier suppliers (suppliers to suppliers), architects and design professionals. Note, however, that even if a party is licensed if he/she supplies labor and/or materials to an unlicensed contractor or subcontractor he/she will not have lien rights.
When in doubt, file early to avoid missing complicated deadlines (150-day rule)
In Virginia, it’s important to lien early. Though a mechanics lien must be filed within 90 days from the last day of the month in which the project participant provided labor and/or materials & within 90 days of the date on which the project was completed as a whole, there is an additional 150-day deadline in order to receive payment. The lien can only include the amount of service or materials supplied 150 days prior to the last day that the participant worked on a given project. If necessary, a participant can file more than one lien. Further, subcontractors are required to send a 30 day (from the last date service or materials were provided) Post Work Notice in order to hold the property owner or general contractors liable.
Residential projects may require preliminary notice to a mechanics lien agent
Where residential projects are concerned, a property owner might appoint a “mechanics lien agent” to handle contractor legalities. If this is the case, a project participant must provide preliminary notice to the mechanics lien agent within 30 days of last providing service or labor for a project or 30 days from the date that the building permit was issued. Labor or materials provided prior to providing preliminary notice cannot be included in the lien.
On all other projects, preliminary notice may work to make the make owner or general personally liable, but in order to be effective it must be delivered not later than 30 days after completion of entire work.
A Virginia Notice of Intent to Lien may be enough to push for payment without a Mechanics Lien
Only licensed parties have rights
In Virginia, mechanics lien law absolutely requires that all project participants are licensed in order to file a mechanics lien. What’s more, if a general contractor or sub-contractor supplies labor or materials to someone unlicensed, they, in turn, forfeit their right to lien as well.
Determining priority is complicated
Knowing who has mechanics lien priority in Virginia can be tricky.
Prior recorded deeds of trust have priority over mechanic’s liens to the extent of the value of the land, but mechanic’s liens have priority over prior recorded deeds of trust to the extent of the value of the building. Mechanic’s liens have priority over all deeds of trust recorded after the commencement of work. However, as to repair and improvement work to pre-existing structures, prior recorded deeds of trust have priority to the extent of both the land and the building.
As to competing mechanic’s liens, priority is in reverse order of tier, i.e. a sub-subcontractor’s mechanics lien has priority over a subcontractor’s mechanic’s lien, and a subcontractor’s lien has priority over a general contractor’s.
Using Virginia's statutory mechanics lien forms helps avoid lien issues
Virginia has statutory mechanics lien forms (which were recently updated!), but they aren’t necessarily required. Still – it’s a good idea to use the statutory forms! Virginia’s lien statute literally says that the forms provided are sufficient for making a lien claim (as long as the right one is used), and when the statutory form is utilized, minor errors are less likely to cause major problems. More on that here: Virginia Mechanics Lien Claimants: Lien Errors Aren’t Always Fatal.
Do It Yourself: How to file a lien in Virginia
Read the guide
The state of Virginia has one of the most powerful mechanics liens in the country. Because of this, there are many strict requirements that must be met in order to secure your lien rights. It’s important you do your research before starting the process. Measure twice – cut once.
Get the right form
First and foremost, you need to start with the correct mechanics lien form, also known as a Memorandum of Lien in Virginia. There is a different form for each role on the project: one form for general contractors, a form for sub-contractors, and another form that is just for sub-subcontractors.
Fill out the form
Virginia’s lien law sets out what needs to be included in your lien form. It’s important to make sure that the lien contains all the required information in order to be valid. Smaller mistakes arent going to be fatal here, but don’t tempt fate. Other mistakes could cost you the payment you are owed.
File your lien with the county recorder
The timing and deadline requirements in Virginia are a bit complicated; including a general filing deadline, a 150-day rule, something known as the “imposing personal liability”. Getting the lien to the right Virginia county recorders office is another challenge you will need to think through.
Send notice of filing
This requirement is solely for subcontractors and sub-subcontractors. The first page on both lien claim forms is essentially your notice forms. Subcontractors will need to send the first page “Notice to Owner” to the owner at the time of filing. Again, be careful with these final steps.
Follow up on your lien
Virginia mechanics liens are only valid for a certain amount of time. Now that you’ve successfully secured your mechanics lien rights, there are still a few steps you can take to finish up the process and get the best results.
Virginia's Mechanics Lien Statutes
The provisions of the Virginia statutes that permit the filing of mechanics liens and materialman’s liens on construction projects can be found in Virginia’s Mechanics’ and Materialmen’s Lien Law, VA Code § 43-1 et. seq. The full text of the Virginia Construction Lien Law is provided below. Updated as of May 2023.
Chapter 1. Mechanics And Materialmen's Liens
§ 43-1. Definitions
As used in this chapter, the term “general contractor” includes contractors, laborers, mechanics, and persons furnishing materials, who contract directly with the owner, and the term “subcontractor” includes all such contractors, laborers, mechanics, and persons furnishing materials, who do not contract with the owner but with the general contractor. As used in this chapter, the term “owner” shall not be construed to mean any person holding bare legal title under an instrument to secure a debt or indemnify a surety. As used in this chapter, the term “mechanics’ lien agent” means a person (i) designated in writing by the owner of real estate or a person authorized to act on behalf of the owner of such real estate and (ii) who consents to act, as the owner’s designee for purposes of receiving notice pursuant to § 43-4.01.S uch person shall be an attorney at law licensed to practice in the Commonwealth, a title insurance company authorized to write title insurance in the Commonwealth or one of its subsidiaries or licensed title insurance agents, or a financial institution authorized to accept deposits and to hold itself out to the public as engaged in the banking or savings institution business in the Commonwealth or a service corporation, subsidiary or affiliate of such financial institution. Any such person may perform mechanics’ lien agent services as any legal entity. Provided that nothing herein shall be construed to affect pending litigation.
§ 43-2. Structures, materials, etc., deemed permanently annexed to freehold
For the purpose of this chapter, a well, excavation, sidewalk, driveway, pavement, parking lot, retaining wall, curb and/or gutter, breakwater (either salt or fresh water), underground or field-constructed above-ground storage tank and connected dispensing equipment, water system, drainage structure, filtering system (including septic or waste disposal systems) or swimming pool shall be deemed a structure permanently annexed to the freehold, and all shrubbery, earth, sod, sand, gravel, brick, stone, tile, pipe or other materials, together with the reasonable rental or use value of equipment and any surveying, grading, clearing or earth moving required for the improvement of the grounds upon which such building or structure is situated shall be deemed to be materials furnished for the improvement of such building or structure and permanently annexed to the freehold.
§ 43-3. Lien for work done and materials furnished; waiver of right to file or enforce lien
A. All persons performing labor or furnishing materials of the value of $150 or more, including the reasonable rental or use value of equipment, for the construction, removal, repair or improvement of any building or structure permanently annexed to the freehold, and all persons performing any labor or furnishing materials of like value for the construction of any railroad, shall have a lien, if perfected as hereinafter provided, upon such building or structure, and so much land therewith as shall be necessary for the convenient use and enjoyment thereof, and upon such railroad and franchises for the work done and materials furnished, subject to the provisions of § 43-20.B ut when the claim is for repairs or improvements to existing structures only, no lien shall attach to the property repaired or improved unless such repairs or improvements were ordered or authorized by the owner, or his agent.
If the building or structure being constructed, removed or repaired is part of a condominium as defined in § 55.1-1900 or under the Horizontal Property Act (§ 55.1-2000 et seq.), any person providing labor or furnishing material to one or more units or limited common elements within the condominium pursuant to a single contract may perfect a single lien encumbering the one or more units which are the subject of the contract or to which those limited common elements pertain, and for which payment has not been made. All persons providing labor or furnishing materials for the common elements pertaining to all the units may perfect a single lien encumbering all such condominium units. Whenever a lien has been or may be perfected encumbering two or more units, the proportionate amount of the indebtedness attributable to each unit shall be the ratio that the percentage liability for common expenses appertaining to that unit computed pursuant to subsection D of § 55.1-1964 bears to the total percentage liabilities for all units which are encumbered by the lien. The lien claimant shall release from a perfected lien an encumbered unit upon request of the unit owner as provided in subsection B of § 55.1-1908 upon receipt of payment equal to that portion of the indebtedness evidenced by the lien attributable to such unit determined as herein provided. In the event the lien is not perfected, the lien claimant shall upon request of any interested party execute lien releases for one or more units upon receipt of payment equal to that portion of the indebtedness attributable to such unit or units determined as herein provided but no such release shall preclude the lien claimant from perfecting a single lien against the unreleased unit or units for the remaining portion of the indebtedness.
B. Any person providing labor or materials for site development improvements or for streets, stormwater facilities, sanitary sewers or water lines for the purpose of providing access or service to the individual lots in a development or condominium units as defined in § 55.1-1900 or under the Horizontal Property Act (§ 55.1-2000 et seq.) shall have a lien on each individual lot in the development for the fractional part of the total value of the work contracted for by the claimant in the subdivision as is obtained by using “one” as the numerator and the number of lots being developed as the denominator and in the case of a condominium on each individual unit in an amount computed by reference to the liability of that unit for common expenses appertaining to that condominium pursuant to subsection D of § 55.1-1964, provided, however, that no such lien shall be valid as to any lot or condominium unit unless the person providing such work shall, prior to the sale of such lot or condominium unit, file with the clerk of the circuit court of the jurisdiction in which such land lies a document setting forth a full disclosure of the nature of the lien which may be claimed, the total value of the work contracted for by the claimant in the subdivision and the portion thereof allocated to each lot as required herein, and a description of the development or condominium, and shall, thereafter, comply with all other applicable provisions of this chapter. “Site development improvements” means improvements which are provided for the development, such as project site grading, traffic signalization, and installation of electric, gas, cable, or other utilities, for the benefit of the development rather than for an individual lot. In determining the individual lots in the development for the purpose of allocating value of the work contracted for by the claimant, parcels of land within the development which are common area, or which are being developed for the benefit of the development as a whole and not for resale, shall not be included in the denominator of the disclosure statement.
Nothing contained herein shall be construed to prevent the filing of a mechanics’ lien under the provisions of subsection A, or require the lien claimant to elect under which subsection the lien may be enforced.
C. Any right to file or enforce any mechanics’ lien granted hereunder may be waived in whole or in part at any time by any person entitled to such lien, except that a general contractor, subcontractor, lower-tier subcontractor, or material supplier may not waive or diminish his lien rights in a contract in advance of furnishing any labor, services, or materials. A provision that waives or diminishes a general contractor’s, subcontractor’s, lower-tier subcontractor’s, or material supplier’s lien rights in a contract executed prior to providing any labor, services, or materials is null and void. In the event that payments are made to the contractor without designating to which lot the payments are to be applied, the payments shall be deemed to apply to any lot previously sold by the developer such that the remaining lots continue to bear liability for an amount up to but not exceeding the amount set forth in any disclosure statement filed under the provisions of subsection B.
D. A person who performs labor without a valid license or certificate issued by the Board for Contractors pursuant to Chapter 11 (§ 54.1-1100 et seq.) of Title 54.1, or without the proper class of license for the value of the work to be performed, when such a license or certificate is required by law for the labor performed shall not be entitled to a lien pursuant to this section.
§ 43-4. Perfection of lien by general contractor; recordation and notice
A general contractor, or any other lien claimant under §§ 43-7 and 43-9, in order to perfect the lien given by § 43-3, provided such lien has not been barred by § 43-4.01C, shall file a memorandum of lien at any time after the work is commenced or material furnished, but not later than 90 days from the last day of the month in which he last performs labor or furnishes material, and in no event later than 90 days from the time such building, structure, or railroad is completed, or the work thereon otherwise terminated. The memorandum shall be filed in the clerk’s office in the county or city in which the building, structure or railroad, or any part thereof is located. The memorandum shall show the names and addresses of the owner of the property sought to be charged, and of the claimant of the lien, the amount and consideration of his claim, the time or times when the same is or will be due and payable, and the date from which interest is claimed, verified by the oath of the claimant, or his agent, including a statement declaring his intention to claim the benefit of the lien, and giving a brief description of the property on which he claims a lien. The memorandum shall also contain the claimant’s license or certificate number issued by the Board for Contractors pursuant to Chapter 11 (§ 54.1-1100 et seq.) of Title 54.1, if any, and the date such license or certificate was issued and the date such license or certificate expires. It shall be the duty of the clerk in whose office the memorandum is filed to record and index the same as provided in § 43-4.1, in the name of the claimant of the lien and of the owner of the property. From the time of such recording and indexing all persons shall be deemed to have notice thereof. A lien claimant who is a general contractor, and not lien claimants under §§ 43-7 and 43-9, also shall file along with the memorandum of lien, a certification of mailing of a copy of the memorandum of lien on the owner of the property at the owner’s last known address. The cost of recording the memorandum shall be taxed against the person found liable in any judgment or decree enforcing such lien. The lien claimant may file any number of memoranda but no memorandum filed pursuant to this chapter shall include sums due for labor or materials furnished more than 150 days prior to the last day on which labor was performed or material furnished to the job preceding the filing of such memorandum. However, any memorandum may include (i) sums withheld as retainages with respect to labor performed or materials furnished at any time before it is filed, but not to exceed 10 percent of the total contract price and (ii) sums which are not yet due because the party with whom the lien claimant contracted has not yet received such funds from the owner or another third party. The time limitations set forth herein shall apply to all labor performed or materials furnished on construction commenced on or after July 1, 1980. An inaccuracy in the memorandum as to the claimant’s license or certificate number, if any, the date such license or certificate was issued, or the date such license or certificate expires shall not bar a person from perfecting a lien if the claimant can otherwise be reasonably identified in the records of the Board for Contractors.
§ 43-4.01. Posting of building permit; identification of mechanics' lien agent in building permit; notice to mechanics' lien agent; effect of notice
A. The building permit for any one- or two-family residential dwelling unit issued pursuant to the Uniform Statewide Building Code shall be conspicuously and continuously posted on the property for which the permit is issued until all work is completed on the property. The permit shall be posted on the property before any labor is performed or any material furnished on the property for which the building permit is issued. Nothing herein shall be construed to prohibit a permit being amended after it has been initially issued to name a mechanics’ lien agent or a new mechanics’ lien agent.
B. If the building permit contains the name, mailing address, and telephone number of the mechanics’ lien agent as defined in § 43-1, any person entitled to claim a lien under this title may notify the mechanics’ lien agent then named on the permit or amended permit that he seeks payment for labor performed or material furnished by registered or certified mail or by physical delivery. Such notice shall contain (i) the name, mailing address, and telephone number of the person sending such notice, (ii) the person’s license or certificate number issued by the Board for Contractors pursuant to Chapter 11 (§ 54.1-1100 et seq.) of Title 54.1, if any, and the date such license or certificate was issued and the date such license or certificate expires, (iii) the building permit number on the building permit, (iv) a description of the property as shown on the building permit, and (v) a statement that the person filing such notice seeks payment for labor performed or material furnished. A return receipt or other receipt showing delivery of the notice to the addressee or written evidence that such notice was delivered by the postal service or other carrier to but not accepted by the addressee shall be prima facie evidence of receipt. An inaccuracy in the notice as to the description of the property shall not bar a person from claiming a lien under this title or filing a memorandum or otherwise perfecting or enforcing a lien as provided in subsection C if the property can otherwise be reasonably identified from the description.
In the event that the mechanics’ lien agent dies, resigns, or otherwise becomes unable or unwilling to serve during the construction period, the owner or the general contractor shall immediately appoint a successor mechanics’ lien agent with all the rights, duties, and obligations of the predecessor mechanics’ lien agent. An amended permit shall be displayed as provided in subsection A. Until such time as the successor is named and displayed as provided, notice given hereunder to the predecessor mechanics’ lien agent at the address shown shall be deemed good notice, notwithstanding the fact that the agent may have died, resigned or become otherwise unable or unwilling to serve.
C. Except as provided otherwise in this subsection, no person other than a person claiming a lien under subsection B of § 43-3 may claim a lien under this title or file a memorandum or otherwise perfect and enforce a lien under this title with respect to a one or two family residential dwelling unit if such person fails to notify any mechanics’ lien agent identified on the building permit in accordance with subsection B above (i) within 30 days of the first date that he performs labor or furnishes material to or for the building or structure or (ii) within 30 days of the date such a permit is issued, if such labor or materials are first performed or furnished by such person prior to the issuance of a building permit. However, the failure to give any such notices within the appropriate 30-day period as required by the previous sentence shall not bar a person from claiming a lien under this title or from filing a memorandum or otherwise perfecting and enforcing a lien under this title, provided that such lien is limited to labor performed or materials furnished on or after the date a notice is given by such person to the mechanics’ lien agent in accordance with subsection B above. A person performing labor or furnishing materials with respect to a one or two family residential dwelling unit on which a building permit is not posted at the time he first performs his labor or first furnishes his material or, if posted, does not state the name of the mechanics’ lien agent, shall determine from appropriate authorities whether a permit of the type described in subsection B above has been issued, the date on which it is issued, and the name of the mechanics’ lien agent, if any, that has been appointed. The issuing authority shall maintain the mechanics’ lien agent information in the same manner and in the same location in which it maintains its record of building permits issued.
No person shall be required to comply with this subsection as to any memorandum of lien which is recorded prior to the issuance of a building permit nor shall any person be required to comply with this subsection when the building permit does not designate a mechanics’ lien agent.
D. Unless otherwise agreed in writing, the only duties of the mechanics’ lien agent shall be to receive notices delivered to him pursuant to subsection B and to provide any notice upon request to a settlement agent, as defined in § 55.1-900, involved in a transaction relating to the residential dwelling unit.
E. Mechanics’ lien agents are authorized to enter into written agreements with third parties with regard to funds to be advanced to them for disbursement, and the transfer, disbursement, return and other handling of such funds shall be governed by the terms of such written agreements.
F. A mechanics’ lien agent as defined in § 43-1 may charge a reasonable fee for services rendered in connection with administration of notice authorized herein and the disbursement of funds for payment of labor and materials for the construction or repair of improvements on real estate.
§ 43-4.1. Liens to be recorded in deed books and indexed in general index of deeds
Notwithstanding the provision of any other section of this title, or any other provision of law requiring documents to be recorded in the miscellaneous lien book or the deed books in the clerk’s office of any court, on and after July 1, 1964, all memoranda or notices of liens, in the discretion of the clerk, shall be recorded in the deed books in such clerk’s office, and shall be indexed in the general index of deeds, and such general index shall show the type of such lien.
§ 43-5. Sufficiency of memorandum and affidavit required by 43-4
The memorandum and affidavit required by § 43-4 shall be sufficient if substantially in form and effect as follows:
Memorandum for Mechanic’s Lien Claimed by General Contractor.
Name of owner: ___________________________________________________________________________
Address of owner: ___________________________________________________________________________
Name of claimant: ___________________________________________________________________________
Address of claimant: ___________________________________________________________________________
Contractor license or certificate number of claimant
(if applicable): ___________________________________________________________________________
Issuance date of license or certificate
(if applicable): ___________________________________________________________________________
Expiration date of license or certificate
(if applicable): ___________________________________________________________________________
If no contractor license or certificate number is included, the claimant certifies that such a valid license or certificate is not required by law for the work done for which the benefit of a lien is claimed.
1. Type of materials or services furnished: ___________________________________________________________________________ ___________________________________________________________________________ ___________________________________________________________________________
___________________________________________________________________________
___________________________________________________________________________
2. Amount claimed: $ ___________________________________________________________________________
If any part of the Amount claimed is not due as of the date of this mechanic’s lien, identify the date or event upon which it will be due and the sum(s) to which the due date(s) or event(s) apply: ___________________________________________________________________________
3. Type of structure on which work done or materials furnished: ___________________________________________________________________________
___________________________________________________________________________
4. Brief description and location of real property:
___________________________________________________________________________
5. Date from which interest on the above amount is claimed:
Date: _______________________
It is the intent of the claimant to claim the benefit of a lien.
The undersigned hereby certifies that he has mailed a copy of this memorandum of lien to the owner of the property at the owner’s last known address: ……………………………. (address), on …….. (date of mailing).
___________________________________________________________________________ (Name of claimant).
Affidavit.
State of Virginia,
County (or city) of ………………, to wit:
I, _______________________ (notary or other officer) for the county (or city) aforesaid, do certify that …………………. claimant, or ……………., agent for claimant, this day made oath before me in my county (or city) aforesaid that ………………… (the owner) is justly indebted to claimant in the sum of ………….. dollars, for the consideration stated in the foregoing memorandum, and that the same is payable as therein stated.
Given under my hand this the …….. day of …………….., 20….
___________________________________________________________________________ (Notary Public or Magistrate, et cetera.)
§ 43-6. Repealed
[Repealed]
§ 43-8. Sufficiency of memorandum, affidavit and notice required by 43-7
The memorandum, affidavit and notice required by § 43-7 shall be sufficient if substantially in form and effect as follows:
Memorandum for Mechanic’s Lien Claimed by Subcontractor.
Name of owner: ___________________________________________________________________________
Address of owner: ___________________________________________________________________________
Name of general contractor (if any): ___________________________________________________________________________
Name of claimant: ___________________________________________________________________________
Address of claimant: ___________________________________________________________________________
Contractor license or certificate number of claimant
(if applicable): ___________________________________________________________________________
Issuance date of license or certificate
(if applicable): ___________________________________________________________________________
Expiration date of license or certificate
(if applicable): ___________________________________________________________________________
If no contractor license or certificate number is included, the claimant certifies that such a valid license or certificate is not required by law for the work done for which the benefit of a lien is claimed.
1. Type of materials or services furnished: ___________________________________________________________________________
___________________________________________________________________________
2. Amount claimed: $?___________________________________________________________________________
If any part of the Amount claimed is not due as of the date of this mechanic’s lien, identify the date or event upon which it will be due and the sum(s) to which the due date(s) or event(s) apply: ___________________________________________________________________________
3. Type of structure on which work done or materials furnished: ___________________________________________________________________________
___________________________________________________________________________
4. Brief description and location of real property: ___________________________________________________________________________
___________________________________________________________________________
5. Date from which interest on above amount is claimed:
Date: _________________________
It is the intent of the claimant to claim the benefit of a lien.
___________________________________________________________________________ (Name of claimant).
Affidavit.
State of Virginia,
County (or city) of __________________________________ to wit:
I, _____________________________ (notary or other officer) for the county (or city) aforesaid, do certify that ______________, claimant, or ________________, agent for claimant, this day made oath before me in my county (or city) aforesaid that __________________________ is justly indebted to claimant in the sum of ______________ dollars, for the consideration stated in the foregoing memorandum, and that the same is payable as therein stated.
Given under my hand this the ______ day of ____________, 20___.
_______________________ (Notary Public or Magistrate, et cetera.)
Notice.
To _______________________ (owner).
You are hereby notified that ____________________ (general contractor) is indebted to me in the sum of ________________ dollars ($__________) with interest thereon from the __________ day of __________, 20___, for work done (or materials furnished, as the case may be,) in and about the construction (or removal, etc.,) of a ____________________________ (describe structure, whether dwelling, store, or etc.,) which he has contracted to construct (or remove, etc.,) for you or on property owned by you in the county (or city) of _____________, and that I have duly recorded a mechanic’s lien for the same.
Given under my hand this the ________________ day of ___________, 20_____.
____________________________ (Subcontractor).
§ 43-9. Perfection of lien by person performing labor or furnishing materials for a subcontractor; extent of lien
Any person performing labor or furnishing materials for a subcontractor, in order to perfect the lien given him by § 43-3, shall comply with the provisions of § 43-4, and in addition thereto give notice in writing to the owner of the property, or his agent, and to the general contractor, or his agent, of the amount and character of his claim. But the amount for which a lien may be perfected by such person shall not exceed the amount for which such subcontractor could himself claim a lien under § 43-7.
§ 43-10. Sufficiency of memorandum, affidavit and notice required by 43-9
The memorandum, affidavit and notice required by § 43-9 shall be sufficient if substantially in form and effect as follows:
Memorandum for Mechanic’s Lien Claimed by Sub-subcontractor.
Name of owner: ___________________________________________________________________________
Address of owner: ___________________________________________________________________________
Name of general contractor (if any) and subcontractor:
___________________________________________________________________________
Name of claimant: ___________________________________________________________________________
Address of claimant: ___________________________________________________________________________
Contractor license or certificate number of claimant
(if applicable): ___________________________________________________________________________
Issuance date of license or certificate
(if applicable): ___________________________________________________________________________
Expiration date of license or certificate
(if applicable): ___________________________________________________________________________
If no contractor license or certificate number is included, the claimant certifies that such a valid license or certificate is not required by law for the work done for which the benefit of a lien is claimed.
1. Type of materials or services furnished: ___________________________________________________________________________
___________________________________________________________________________
2. Amount claimed: $ ___________________________________________________________________________
If any part of the Amount claimed is not due as of the date of this mechanic’s lien, identify the date or event upon which it will be due, and the sum(s) to which the due date(s) or event(s) apply: ___________________________________________________________________________
3. Type of structure on which work done or materials furnished: ___________________________________________________________________________
___________________________________________________________________________
4. Brief description and location of real property: ___________________________________________________________________________
___________________________________________________________________________
5. Date from which interest on above amount is claimed:
Date: ____________________________
It is the intent of the claimant to claim the benefit of a lien.
____________________________ (Name of claimant).
______________ (Signature of claimant or agent for claimant).
Affidavit.
State of Virginia,
County (or city) of ________________________, to wit:
I, ___________________________________________________________________________ (notary or other officer) for the county (or city)
aforesaid do certify that ___________________________________________ claimant, or ___________________________________________, agent for claimant, this day made oath before me in my county (or city) aforesaid that _______________ is justly indebted to claimant in the sum of __________ dollars for the consideration stated in the foregoing memorandum, and that the same is payable as therein stated.
Given under my hand this the ……………. day of ……………, 20….
________________________________________ (Notary Public or
Magistrate, et cetera.)
Notice.
To __________________________ (owner) and __________________________ (general contractor):
You are hereby notified that ___________________________________________________________________________ , a subcontractor under you,
said ___________________________________________________________________________ (general contractor) for the construction (or removal,
etc.,) of a ___________________________________________________________________________ (describe structure) for you, or on property owned by
you, said ___________________________________________________________________________ (owner) is indebted to me in the sum of ………….
…………….. dollars ($ ______________) with interest thereon from the …. day of ……., 20…, for work done (or materials furnished) in and about the construction (or removal, etc.,) of _________________________ (naming structure), situate in the county (or city) of _______________ Virginia, and that I have duly recorded a mechanic’s lien for the same.
Given under my hand this the ……………… day of ……………, 20…….
__________________________________________________ (Sub-subcontractor).
§ 43-11. How owner or general contractor made personally liable to subcontractor, laborer or materialman
1. Any subcontractor or person furnishing labor or material to the general contractor or subcontractor, may give a preliminary notice in writing to the owner or his agent or the general contractor, stating the nature and character of his contract and the probable amount of his claim.
2. Additionally, if such subcontractor, or person furnishing labor or material shall at any time after the work is done or material furnished by him and before the expiration of thirty days from the time such building or structure is completed or the work thereon otherwise terminated furnish the owner thereof or his agent and also the general contractor, or the general contractor alone in case he is the only one notified, with a second notice stating a correct account, verified by affidavit, of his actual claim against the general contractor or subcontractor, for work done or materials furnished and of the amount due, then the owner, or the general contractor, if he alone was notified, shall be personally liable to the claimant for the actual amount due to the subcontractor or persons furnishing labor or material by the general contractor or subcontractor, provided the same does not exceed the sum in which the owner is indebted to the general contractor at the time the second notice is given or may thereafter become indebted by virtue of his contract with the general contractor, or in case the general contractor alone is notified the sum in which he is indebted to the subcontractor at the time the second notice is given or may thereafter become indebted by virtue of his contract with the general contractor. But the amount which a person supplying labor or material to a subcontractor can claim shall not exceed the amount for which such subcontractor could file his claim.
3. Any bona fide agreement for deductions by the owner because of the failure or refusal of the general contractor to comply with his contract shall be binding upon such subcontractor, laborer or materialman.
4. The provisions of this section are subject to the qualification that before any such personal liability of the owner or general contractor herein provided for shall be binding the two notices herein required, with such returns thereon as is sufficient under § 8.01-325, shall be recorded and indexed as provided in § 43-4.1 in the appropriate clerk’s office; or the two notices herein required shall be mailed by registered or certified mail to and received by the owner or general contractor upon whom personal liability is sought to be imposed, and a return receipt therefor showing delivery to the addressee shall be prima facie evidence of receipt.
§ 43-12. Repealed
[Repealed]
§ 43-13. Funds paid to general contractor or subcontractor must be used to pay persons performing labor or furnishing material
Any contractor or subcontractor or any officer, director or employee of such contractor or subcontractor who shall, with intent to defraud, retain or use the funds, or any part thereof, paid by the owner or his agent, the contractor, or the lender to such contractor or by the owner or his agent, the contractor, or the lender to a subcontractor under any contract for the construction, removal, repair, or improvement of any building or structure permanently annexed to the freehold for any other purpose than to pay persons performing labor upon or furnishing material for such construction, repair, removal, or improvement is guilty of larceny in appropriating such funds for any other use while any amount for which the contractor or subcontractor may be liable or become liable under his contract for such labor or materials remains unpaid and may be prosecuted upon complaint of any person or persons who have not been fully paid any amount due them.
The use by any such contractor or subcontractor or any officer, director, or employee of such contractor or subcontractor of any moneys paid under the contract before paying all amounts due or to become due for labor performed or material furnished for such building or structure for any other purpose than paying such amounts due on the project shall be prima facie evidence of intent to defraud. Any breach or violation of this section may give rise to a civil cause of action for a party in contract with the general contractor or subcontractor, as appropriate; however, this right does not affect a contractor’s or subcontractor’s right to withhold payment for failure to properly perform labor or furnish materials on the project. Any contract or subcontract provision that allows a contracting party to withhold funds due under one contract or subcontract for alleged claims or damages due on another contract or subcontract is void as against public policy.
§ 43-13.2. When an affidavit or a signed statement of payment required of owner prior to sale
A person who is both the owner of a one- or two-family residential dwelling unit and either a developer of such property, a contractor in connection with the development or improvement of such property or a contractor or subcontractor furnishing labor or material in connection with the development or improvement of such property shall, at the time of settlement on the sale of such property, provide the purchaser with an affidavit or a signed statement attested to by a witness stating either (i) that all persons performing labor or furnishing materials in connection with the improvements on such property and with whom such owner is in privity of contract have been paid in full or (ii) the name, address and amount payable or claimed to be payable to any person so performing labor or furnishing materials and with whom such owner is in privity of contract. Willful failure to provide such statement or any willful material misrepresentation with respect to such a statement which causes a monetary loss to a financial institution, title company, contractor, subcontractor, supplier, owner, mechanics’ lien agent or any other person or institution shall be punishable as a Class 5 felony.
§ 43-13.3. An affidavit or a signed statement of payment required of owner prior to sale or refinance; penalty
Any person who is the owner of a one- or two-family residential dwelling unit not included within the scope of § 43-13.2 shall, at the time of settlement on the sale of such property, provide the purchaser, or lender in the case of a permanent loan or refinance, with an affidavit or a signed statement attested to by a witness stating either (i) that all persons performing labor or furnishing materials in connection with any improvements on such property within 120 days prior to the date of settlement and with whom such owner is in privity of contract have been paid in full, or (ii) the name, address and amount payable or claimed to be payable to any person so performing labor or furnishing materials and with whom such owner is in privity of contract. Any willful material misrepresentation in the affidavit or signed statement attested to by a witness which causes a monetary loss to any financial institution, title company, or purchaser shall be punishable as a Class 3 misdemeanor.
§ 43-14. Repealed
[Repealed]
§ 43-14.1. Service of notices
Any notice authorized or required by this chapter, except the notice required by § 43-11, may be served by any sheriff or constable who shall make return of the time and manner of service; or any such notice may be served by certified or registered mail and a return receipt therefor shall be prima facie evidence of receipt.
§ 43-15. Inaccuracies in memorandum or description not affecting lien
No inaccuracy in the memorandum filed, or in the description of the property to be covered by the lien, shall invalidate the lien, if the property can be reasonably identified by the description given and the memorandum conforms substantially to the requirements of §§ 43-5, 43-8 and 43-10, respectively, and is not wilfully false.
§ 43-16. What owner may do when contractor fails or refuses to complete building, etc
If the owner is compelled to complete his building, structure, or railroad, or any part thereof undertaken by a general contractor in consequence of the failure or refusal of the general contractor to do so, the amount expended by the owner for such completion shall have priority over all mechanics’ liens which have been or may be placed on such building, structure, or railroad by such general contractor, a subcontractor under him, or any person furnishing labor or materials to either of them.
§ 43-17. Limitation on suit to enforce lien
No suit to enforce any lien perfected under §§ 43-4, 43-5 and 43-7 to 43-10 shall be brought after six months from the time when the memorandum of lien was recorded or after sixty days from the time the building, structure or railroad was completed or the work thereon otherwise terminated, whichever time shall last occur; provided, however, that the filing of a petition to enforce any such lien in any suit wherein such petition may be properly filed shall be regarded as the institution of a suit under this section; and, provided further, that nothing herein shall extend the time within which such lien may be perfected.
§ 43-17.1. Hearing on validity of lien
Any party, having an interest in real property against which a lien has been filed, may, upon a showing of good cause, petition the court of equity having jurisdiction wherein the building, structure, other property, or railroad is located to hold a hearing to determine the validity of any perfected lien on the property. After reasonable notice to the lien claimant and any party to whom the benefit of the lien would inure and who has given notice as provided in § 43-18 of the Code of Virginia, the court shall hold a hearing and determine the validity of the lien. If the court finds that the lien is invalid, it shall forthwith order that the memorandum or notice of lien be released from record.
§ 43-18. Lien of general contractor to inure to benefit of subcontractor
The perfected lien of a general contractor on any building or structure shall inure to the benefit of any subcontractor, and of any person performing labor or furnishing materials to a subcontractor who has not perfected a lien on such building or structure, provided such subcontractor, or person performing labor or furnishing materials shall give written notice of his claim against the general contractor, or subcontractor, as the case may be, to the owner or his agent before the amount of such lien is actually paid off or discharged.
§ 43-19. Validity and priority of lien not affected by assignments
Every assignment or transfer by a general contractor, in whole or in part, of his contract with the owner or of any money or consideration coming to him under such contract, or by a subcontractor of his contract with the general contractor, in whole or in part, or of any money or consideration coming to him under his contract with the general contractor, and every writ of fieri facias, attachment or other process against the general contractor or subcontractor to subject or encumber his interest arising under such contract, shall be subject to the liens given by this chapter to laborers, mechanics, and materialmen. No such assignment or transfer shall in any way affect the validity or the priority of satisfaction of liens given by this chapter.
§ 43-20. Extent of lien where owner has less than fee in land
Subject to the provisions of § 43-3, if the person who shall cause a building or structure to be erected or repaired owns less than a fee simple estate in the land, then only his interest therein shall be subject to liens created under this chapter. When the vendee under a contract for the sale of real estate causes a building or structure to be erected or repaired on the land which is the subject of the contract and the owner has actual knowledge of such erection or repairs, the interest of the owner in the land shall be subject to liens created under this chapter; and for the purposes of § 43-21, the interest of such an owner in the land, to the extent of the unpaid purchase price, shall be deemed to be a recorded purchase money deed of trust lien created at the time the contract of sale was fully executed. As used in this section, “a contract for the sale of real estate” shall not include a lease of real estate containing an option to purchase the leased real estate or an option to purchase real estate unless the option is enforceable against the optionee.
§ 43-21. Priorities between mechanics' and other liens
No lien or encumbrance upon the land created before the work was commenced or materials furnished shall operate upon the building or structure erected thereon, or materials furnished for and used in the same, until the lien in favor of the person doing the work or furnishing the materials shall have been satisfied; nor shall any lien or encumbrance upon the land created after the work was commenced or materials furnished operate on the land, or such building or structure, until the lien in favor of the person doing the work or furnishing the materials shall have been satisfied.
Unless otherwise provided in the subordination agreement, if the holder of the prior recorded lien of a purchase money deed of trust subordinates to the lien of a construction money deed of trust, such subordination shall be limited to the construction money deed of trust and said prior lien shall not be subordinate to mechanics’ and materialmen’s liens to the extent of the value of the land by virtue of such agreement.
In the enforcement of the liens acquired under the previous sections of this chapter, any lien or encumbrance created on the land before the work was commenced or materials furnished shall be preferred in the distribution of the proceeds of sale only to the extent of the value of the land estimated, exclusive of the buildings or structures, at the time of sale, and the residue of the proceeds of sale shall be applied to the satisfaction of the liens provided for in the previous sections of this chapter. Provided that liens filed for performing labor or furnishing materials for the repair or improvement of any building or structure shall be subject to any encumbrance against such land and building or structure of record prior to the commencement of the improvements or repairs or the furnishing of materials or supplies therefor. Nothing contained in the foregoing proviso shall apply to liens that may be filed for the construction or removal of any building or structure.
Notwithstanding the provisions of subsection C of § 43-3, a general contractor may, prior to or after providing any labor, services, or materials, contract to subordinate his lien rights to prior recorded and later recorded deeds of trust, provided that such contract is (i) in writing and (ii) signed by any general contractor whose lien rights are subordinated pursuant to such contract.
§ 43-22. How liens enforced
The liens created and perfected under this chapter may be enforced in a court of equity by a bill filed in the county or city wherein the building, structure, or railroad, or some part thereof is situated, or wherein the owner, or if there be more than one, any of them, resides. The plaintiff shall file with his bill an itemized statement of his account, showing the amount and character of the work done or materials furnished, the prices charged therefor, the payments made, if any, the balance due, and the time from which interest is claimed thereon, the correctness of which account shall be verified by the affidavit of himself, or his agent. When suit is brought for the enforcement of any such lien against the property bound thereby, all parties entitled to such liens upon the property or any portion thereof may file petitions in such suit asking for the enforcement of their respective liens to have the same effect as if an independent suit were brought by each claimant.
§ 43-23. Priority among liens perfected under this chapter
There shall be no priority among the liens created and perfected under this chapter, except that the lien of a subcontractor shall be preferred to that of his general contractor; the lien of persons performing labor or furnishing materials for a subcontractor, shall be preferred to that of such subcontractor; and liens filed by persons performing manual labor shall have priority over materialmen to the extent of the labor performed during the thirty days immediately preceding the date of the performance of the last labor.
§ 43-23.1. Forfeiture of lien
Any person who shall, with intent to mislead, include in his memorandum of lien work not performed upon, or materials not furnished for, the property described in his memorandum shall thereby forfeit any right to a lien under this chapter.
§ 43-23.2. Remedies cumulative
The remedies afforded by this chapter shall be deemed cumulative in nature and not be construed to be in lieu of any other legal or equitable remedies.
Chapter 8. Miscellaneous Provisions
§ 43-64. How notices served, acts done, etc., in case of bankruptcy, death or absconding
Whenever any act is required to be done by, or notice is to be given to, a person mentioned in any section of this title, or of Chapter 17 (§ 8.01-426 et seq.) of Title 8.01, if such person become bankrupt, the act may be done by, or the notice given to, either the bankrupt or his trustee; or if such person die, the act may be done by, or the notice given to, his personal representative; or if he abscond, the notice may be given to any person over the age of sixteen years found at his last known place of business or residence, or if no such person be found there, by posting the same at the front door of such place of business or residence, or at some other conspicuous part of the building, or he may be proceeded against by order of publication as a nonresident of the Commonwealth.
§ 43-65. Protection of assignees, transferees or endorsees of debts secured by mechanics' or crop liens
Whenever any debt secured on real estate or personal property by a mechanics’ or crop lien has been assigned, transferred, or endorsed to another, in whole or in part by the original payee thereof, such payee, assignee, transferee, or endorsee may cause a memorandum or statement of the assignment to such assignee, transferee, or endorsee to be recorded, which memorandum or statement shall be signed by the assignor, transferrer, or endorser, or his duly authorized agent or attorney, and when so signed and the signature thereto attested by the clerk in whose office such encumbrance is recorded the same shall operate as a notice of such assignment and transfer. Such assignment, transfer, or endorsement shall reference the book and page where the original debt secured on real estate or personal property is recorded. And where such transfer by the payee is so entered in the proper book, subsequent transfers may likewise be entered in the same manner and with like effect. Provided, however, this section shall not apply to conditional sales contracts of personal property.
§ 43-66. Purchaser not affected by liens of Mutual Assurance Society against Fire
The lien of the Mutual Assurance Society against Fire on buildings in the Commonwealth of Virginia upon property insured therein for quotas assessed against the policies of such property owners shall not be valid against purchasers of such property for valuable consideration without notice of the existence of such insurance, except from the time the Society shall have complied with the provisions of this section. The Society shall have prepared and kept in the clerk’s office of the Circuit Court of the City of Richmond, and of the circuit court of each county and the circuit court of each city in which the Society insures property, a book to be called the “Mutual Assurance Society’s Lien Book.” Such book when left with the clerk shall become a public record and shall be kept open to the inspection of the public. The Society shall have entered in such book a brief description of the property insured by it upon which it claims a lien, the date and amount of the policy and the name of the parties to whom the policy was issued, and the date of the entry shall be made in such book.
Chapter 9. Release of Liens
§ 43-67. Release of mechanic's lien upon payment or satisfaction
When payment or satisfaction has been made of a debt secured by a mechanic’s lien it shall be released in the manner provided in §§ 55.1-339 and 55.1-341, insofar as appropriate.
§ 43-68. Releases made by court
Any person who owns or has any interest in real estate or personal property on which such lien exists may, after twenty days’ notice thereof to the person entitled to such lien, apply to the circuit or corporation court of the county or corporation in whose clerk’s office such encumbrance is recorded, or to the Circuit Court of the City of Richmond, if it be in the clerk’s office of such court, to have the same released or discharged; and upon proof that it has been paid or discharged, or upon its appearing to the court that more than twenty years have elapsed since the maturity of the lien, raising a presumption of payment, and which is not rebutted at the hearing, or upon proof that no suit, as defined by § 43-17, has been brought to enforce the same within the time prescribed by such section; such court shall order the same to be recorded by the clerk. Such release shall reference the book and page where the original lien securing such interest in real estate or personal property is recorded.
All releases made prior to June 24, 1944, by any court under this section upon such presumption of payment so arising and not rebutted, shall be validated.
§ 43-69. [Repealed]
[Repealed]
§ 43-70. Release of mechanic's lien upon payment into court or filing of bond after suit brought
In any suit brought under the provisions of § 43-22, the owner of the building and premises to which the lien, or liens, sought to be enforced shall have attached, the general contractor for such building or other parties in interest may, after five days’ notice to the lienor, or lienors, apply to the court in which such suit shall be pending, or to the judge thereof in vacation, for permission to pay into court an amount of money sufficient to discharge such lien, or liens, and the costs of the suit or for permission to file a bond in the penalty of double the amount of such lien, or liens, and costs, with surety to be approved by the court, or judge, conditioned for the payment of such judgment adjudicating the lien or liens to be valid and determining the amount for which the same would have been enforceable against the real estate as may be rendered by the court upon the hearing of the case on its merits, which permission shall be granted by the court, or judge, in either such case, unless good cause be shown against the same by some party in interest.
Upon the payment of such money into court, or upon the filing of such bond, as the case may be, after the court has granted permission for the same to be done, the property affected thereby shall stand released from such lien, or liens, and the money so paid in, or the bond so filed, as the case may be, shall be subject to the final judgment of the court upon the hearing of the case on its merits.
§ 43-71. Release of mechanic's lien upon payment into court or filing bond before suit
At any time after the perfecting of any such lien and before a suit be brought for the enforcement thereof, the owner of the property affected thereby, the general contractor or other parties in interest may, after five days’ notice to the lienor, apply to the court having jurisdiction of a suit for the enforcement of such lien, or to the judge thereof in vacation, for permission to make such payment into court, or to file such bond, as prescribed in § 43-70, which permission, in either such event, shall be granted by such court, or judge, unless good cause be shown against the same by some party in interest. Upon the granting of such permission, and the payment of such money into court, or the filing of such bond, as the case may be, the property affected thereby shall stand released from such lien.
Such money, or bond, as the case may be, shall be held under the control of the court and shall be subject to the final judgment of the court adjudicating the lien or liens to be valid and determining the amount for which the same would have been enforceable against the real estate in any suit or action thereafter brought for the ascertainment of the rights of the parties in interest, with respect hereto, or, shall be paid out and disposed of as the parties in interest may direct, in the event the matters in controversy with respect thereto be settled and adjusted between the parties without suit or action.
The sureties on any such bond, which may be involved in any suit or action brought under the provisions of this section, shall be made parties to such suit or action.