Levelset visitors can also get a free Procore account.

Florida Retainage Guide and FAQs

Ready? Build Your Free Florida
Retainage Now

Get Your Lien Waiver Now
Florida Retainage FAQs

Florida Retainage Overview

Florida Retainage Requirements


  • Private Jobs
  • Public Jobs
  • Top Links
Retainage No Limit Icon
No Retainage Rules

Florida statute does not regulate retainage on private construction projects.

Retainage 5% Icon
5 Percent

On public projects in Florida, retainage cannot exceed 5% of each progress payment. (Effective October 1, 2020)


Payment Period 30 Days Icon
30 Day Pay Period

For projects estimated to cost less than $10 million, retainage funds must be released within 30 days after substantial completion.

For projects of $10 million or more, the retainage deadline is also 30 days from substantial completion, but may be extended by contract to a maximum of 60 days.


YES
PROCESS
There is a Process to Recover

Yes, there is a specific recovery process set out by Florida law.

Retainage, also called “retention,” is an amount of money “held back” from a contractor or subcontractor during the course of a construction project. In general, retainage serves two main purposes:

  1. To provide an incentive to the contractor or subcontractor to complete the project; &
  2. To give the owner some protection against problems like liens, contractual defaults, delays, and more.

In most states, laws exist to regulate how the parties use the retainage concept, mostly protecting some parties against abuse of the tool from others. The following are resources, legal information, and answers to frequently asked questions about Florida’s retainage requirements.

Florida’s retainage limits & deadlines

Florida retainage statutes only apply to public works projects where the original contract price is $200,000 or more. Retainage practices on private projects aren’t regulated in Florida. Retainage on private projects will be governed by the terms of the contract.


UPDATE: New Florida retainage requirements for public projects went into effect on October 1, 2020. Here’s a snapshot of the changes:

  • Retainage limit is now 5% for the lifetime of the project
  • Reduction in retainage percentage no longer required at 50% completion
  • Provision allowing the contractor to request early release of retainage was removed

All new projects advertised to bid after the effective date will be held to the updated requirements.


On public projects, the maximum amount of retainage that can be withheld is 10% from each progress payment. Upon 50% of completion, the public entity must reduce the amount of retainage withheld to 5% of the remaining progress payments. A contractor can elect to withhold more than 5% based on the subcontractor’s performance.

Once the project has reached substantial completion the deadline for the public entity to pay retainage depends on the overall contract price of the project:

  • Projects under $10M: within 30 days
  • Projects over $10M: within 30 days, unless extended by contract, not to exceed 60 days

If a good faith dispute exists, the public entity may withhold up to 150% of the value of the work to be completed. Once retainage has been released to the prime contractor, retainage must be paid to any subcontractors within 10 days. In turn, subcontractor must pay their subs and suppliers within 7 days of receipt of retainage. Failure to timely release retainage payments will be subject to an interest rate of 1% per month.

FAQs: Florida Retainage Requirements

When do Florida retainage laws apply?

The Florida retainage laws apply to any public works project funded by a state, county, or local government entity where the overall contract price is $200K or more. These regulations do not apply to private construction projects, or to projects that are funded in whole or in part with federal funds.

Unsure what type of project you’re on?

Does Florida limit the amount of retainage that can be withheld from a contractor?

For projects after October 1, 2020

Under Florida’s new retainage laws, retainage is capped at 5% of each progress payment. While the requirement to reduce retainage percentage at 50% completion is no longer in effect, the contract can provide for a reduction.

For existing projects

For projects that were advertised to bid prior to October 1, 2020, the maximum amount of retainage that can be withheld is 10%. Once the project reaches 50% completion, the retainage is required to be reduced to just 5% of each remaining progress payment. However, even after 50% completion, the contractor may withhold more than 5% retainage based on a particular subcontractor’s past performance, the likelihood that such performance will continue, and the  contractor’s ability to rely on other safeguards.

So how do you know when the project has reached 50% completion?

Under Florida retainage laws, 50% completion is defined by the terms of the construction contract. Or, if not defined in the contract, when the public entity has expended 50% of the total cost of construction services, along with any existing change orders and other additions/modifications to the contract.

How long can retainage be withheld in Florida?

The deadline for the release of retainage depends on the total contract price of the project:

  • Projects less than $10M: Retainage must be released within 30 calendar days after substantial completion of the project
  • Projects over $10M: Retainage may be released within 30 day, unless otherwise extended by contract, but cannot exceed 60 days after substantial completion

So how do you know if the project has reached substantial completion?

Under Florida retainage laws, substantial completion is defined by the terms of the contract. Or, if not defined in the contract, upon reaching beneficial use or occupancy of the property.

Is there an option for the early release of retainage in Florida?

For new projects as of October 1, 2020

While Florida law no longer requires retainage to be reduced, parties can change retainage terms by agreement.

For existing projects

Upon 50% completion of the project, the contractor may elect to request the release of half of the retainage held on the project, which the public entity will approve unless there is a good faith dispute to justify the denial.

Does Florida require retained funds be deposited in a special account? Can securities be substituted for retainage?

Florida retainage is not required to be deposited in any escrow or interest-bearing account. As far as securities, Florida law does allow a contractor to substitute securities in lieu of retainage, as long as the substitution is approved by the public entity.

Is there a specific notice required to recover retainage in Florida?

On projects subject to Florida’s new retainage rules

The statutory provision that allowed a contractor to request up to half of the retained amounts once the project reaches 50% completion was removed. However, this does not prevent the parties from including a contract provision that allows for the request of early return of retainage.

On projects subject to Florida’s prior rules

The contractor may present the public entity with a payment request for up to half of the held retainage after 50% completion of the services.

For final retainage, the contract between the contractor and public entity must contain a list of items that must be completed in order to render complete, satisfactory, and acceptable construction services. Otherwise referred to as a punch list. Once the items are completed, the contractor can submit a request for retainage and trigger the recovery process.

If, however, there is a good faith dispute regarding the completion of one or more items contained in the list, the public entity may continue to withhold up to 150% of the value of the work to be completed.

How can I make a claim to recover retainage in Florida?

Any one providing labor, services, or materials to the a public project may file a verified complaint  to recover improperly withheld retainage under Fla. Stat. §255.071 of the Florida Prompt Payment Act.

Alternatively, retainage may be included in a Notice of Nonpayment, when making a claim against the payment bond on the project.

Need More Help with Florida Retainage? We're Here.

Florida Retainage
Recent Questions & Answers

what is the regulation regarding retainage on actual materials purchased?

In Florida, I read the private projects are not regulated for retainage practices. As such, we have only been withholding retainage on the actual labor...

I was contacted by the attorney for the my previous client that hasn't paid me anything. They sent a letter to counter

I did a house in Vero Beach Fl and the homeowner did not pay me so I put a lien on her house after she...

File a lien for a contractor

I’m a subcontractor working for post construction cleaning, me and my team finished on may 30th 2022, they require the key to access the building,...

How to file a lien in Florida

Need to file a Florida mechanics lien? File your mechanics lien with Levelset, the lien experts quickly and easily. Or you can follow the 3 steps below to file a lien yourself with Levelset's free information.

Want to Learn More about How Florida Contractors Pay?
Progress Residential
Rating 5.0
Dick's Sporting Goods
Rating 5.0
Details Construction Group
Rating 5.0
Texeira Contracting, Inc.
Rating 5.0
See other Lists of Contractors and How to Best Work With Them

Florida Retainage Statutes

Getting informed about prompt payment laws is important. An examination of Florida’s retainage laws, the rules and regulations related to the amount and timing of allowable retained payments, is important to know your rights and responsibilities as a party on a construction project. Florida’s specific laws for local government projects can be found under Fla. Stat. §218.735, and for state government projects under Fla. Stat. §§255.052255.077, and 255.078, which are reproduced below.

Retainage Statutes on Private Projects

N/A

Florida does not provide a retainage statute for private projects.

Retainage Statutes on Public Projects (Local Government)

§ 218.735. Timely payment for purchases of construction services

(1) The due date for payment for the purchase of construction services by a local governmental entity is determined as follows:

(a) If an agent must approve the payment request or invoice before the payment request or invoice is submitted to the local governmental entity, payment is due 25 business days after the date on which the payment request or invoice is stamped as received as provided in s. 218.74(1). The contractor may send the local government an overdue notice. If the payment request or invoice is not rejected within 4 business days after delivery of the overdue notice, the payment request or invoice shall be deemed accepted, except for any portion of the payment request or invoice that is fraudulent or misleading.

(b) If an agent need not approve the payment request or invoice submitted by the contractor, payment is due 20 business days after the date on which the payment request or invoice is stamped as received as provided in s. 218.74(1).

A local governmental entity shall identify the agent or employee of the local governmental entity, or the facility or office, to which the contractor may submit its payment request or invoice. This requirement shall be included in the contract between the local governmental entity and contractor, or shall be provided by the local governmental entity through a separate written notice, as required under the contract, no later than 10 days after the contract award or notice to proceed. A contractor’s submission of a payment request or invoice to the identified agent, employee, facility, or office of the local governmental entity shall be stamped as received as provided in s. 218.74(1) and shall commence the time periods for payment or rejection of a payment request or invoice as provided in this subsection and subsection (2).

(2) If a payment request or invoice does not meet the contract requirements, the local governmental entity must reject the payment request or invoice within 20 business days after the date on which the payment request or invoice is stamped as received as provided in s. 218.74(1). The rejection must be written and must specify the deficiency and the action necessary to make the payment request or invoice proper.

(3) If a payment request or an invoice is rejected under subsection (2) and the contractor submits a payment request or invoice that corrects the deficiency, the corrected payment request or invoice must be paid or rejected on the later of:

(a) Ten business days after the date the corrected payment request or invoice is stamped as received as provided in s. 218.74(1); or

(b) If the local governmental entity is required by ordinance, charter, or other law to approve or reject the corrected payment request or invoice, the first business day after the next regularly scheduled meeting of the local governmental entity held after the corrected payment request or invoice is stamped as received as provided in s. 218.74(1).

(4) If a dispute between the local governmental entity and the contractor cannot be resolved by the procedure in subsection (3), the dispute must be resolved in accordance with the dispute resolution procedure prescribed in the construction contract or in any applicable ordinance, which shall be referenced in the contract. In the absence of a prescribed procedure, the dispute must be resolved by the procedure specified in s. 218.76(2).

(5) If a local governmental entity disputes a portion of a payment request or an invoice, the undisputed portion shall be paid timely, in accordance with subsection (1).

(6) If a contractor receives payment from a local governmental entity for labor, services, or materials furnished by subcontractors and suppliers hired by the contractor, the contractor must remit payment due to those subcontractors and suppliers within 10 days after the contractor’s receipt of payment. If a subcontractor receives payment from a contractor for labor, services, or materials furnished by subcontractors and suppliers hired by the subcontractor, the subcontractor must remit payment due to those subcontractors and suppliers within 7 days after the subcontractor’s receipt of payment. This subsection does not prohibit a contractor or subcontractor from disputing, pursuant to the terms of the relevant contract, all or any portion of a payment alleged to be due to another party if the contractor or subcontractor notifies the party whose payment is disputed, in writing, of the amount in dispute and the actions required to cure the dispute. The contractor or subcontractor must pay all undisputed amounts due within the time limits imposed by this section.

(7) Each contract for construction services between a local governmental entity and a contractor must provide for the development of a single list of items and the estimated cost to complete each item on the list required to render complete, satisfactory, and acceptable the construction services purchased by the local governmental entity.

(a) The contract must specify the process for developing the list and for determining the cost to complete each item on the list, and should include the responsibilities of the local governmental entity and the contractor in developing and reviewing the list and a reasonable time for developing the list:

1. For construction projects having an estimated cost of less than $10 million, within 30 calendar days after reaching substantial completion of the construction services purchased as defined in the contract, or, if not defined in the contract, upon reaching beneficial occupancy or use; or

2. For construction projects having an estimated cost of $10 million or more, within 30 calendar days, or, if extended by contract, up to 45 calendar days after reaching substantial completion of the construction services purchased as defined in the contract, or, if not defined in the contract, upon reaching beneficial occupancy or use.

The contract must also specify a date for the delivery of the list of items, not to exceed 5 days after the list of items has been developed and reviewed in accordance with the time periods set forth in subparagraphs 1. and 2.

(b) If the contract between the local governmental entity and the contractor relates to the purchase of construction services on more than one building or structure, or involves a multiphased project, the contract must provide for the development of a list of items required to render complete, satisfactory, and acceptable all the construction services purchased pursuant to the contract for each building, structure, or phase of the project within the time limitations provided in paragraph (a).

(c) The final contract completion date must be at least 30 days after the delivery of the list of items. If the list is not provided to the contractor by the agreed upon date for delivery of the list, the contract time for completion must be extended by the number of days the local governmental entity exceeded the delivery date. Damages may not be assessed against a contractor for failing to complete a project within the time required by the contract, unless the contractor failed to complete the project within the contract period as extended under this paragraph.

(d) The failure to include any corrective work or pending items not yet completed on the list does not alter the responsibility of the contractor to complete all the construction services purchased pursuant to the contract.

(e) Within 20 business days after the list is created, the local governmental entity must pay the contractor the remaining contract balance that includes all retainage previously withheld by the local governmental entity less an amount equal to 150 percent of the estimated cost to complete the items on the list.

(f) Upon completion of all items on the list, the contractor may submit a payment request for the amount withheld by the local governmental entity pursuant to paragraph (e) . If a good faith dispute exists as to whether one or more items identified on the list have been completed pursuant to the contract, the local governmental entity may continue to withhold up to 150 percent of the total costs to complete such items.

(g) All items that require correction under the contract which are identified after the preparation and delivery of the list remain the obligation of the contractor as defined by the contract.

(h) Warranty items or items not included in the list of items required under paragraph (a) may not affect the final payment of retainage as provided in paragraph (e) or as provided in the contract between the contractor and its subcontractors and suppliers.

(i) Retainage may not be held by a local governmental entity or a contractor to secure payment of insurance premiums under a consolidated insurance program or series of insurance policies issued to a local governmental entity or a contractor for a project or group of projects, and the final payment of retainage as provided in this section may not be delayed pending a final audit by the local governmental entity’s or contractor’s insurance provider.

(j) If a local governmental entity fails to comply with its responsibilities to develop the list required under paragraph (a) or paragraph (b) within the time limitations provided in paragraph (a), the contractor may submit a payment request to the local governmental entity for the remaining balance of the contract, including all remaining retainage withheld by the local governmental entity. The local governmental entity must pay the contractor within 20 business days after receipt of a proper invoice or payment request. If the local governmental entity has provided written notice to the contractor specifying the failure of the contractor to meet contract requirements in the development of the list of items to be completed, the local governmental entity must pay the contractor the remaining balance of the contract, less an amount equal to 150 percent of the estimated cost to complete the items that the local governmental entity intended to include on the list .

(8)

(a) With regard to any contract for construction services, a local governmental entity may withhold from each progress payment made to the contractor an amount not exceeding 5 percent of the payment as retainage.

(b) This section does not prohibit a local governmental entity from withholding retainage at a rate less than 5 percent of each progress payment, from incrementally reducing the rate of retainage pursuant to a schedule provided for in the contract, or from releasing at any point all or a portion of any retainage withheld by the local governmental entity which is attributable to the labor, services, or materials supplied by the contractor or by one or more subcontractors or suppliers. If a local governmental entity makes any payment of retainage to the contractor which is attributable to the labor, services, or materials supplied by one or more subcontractors or suppliers, the contractor must timely remit payment of such retainage to those subcontractors and suppliers.

(c) This section does not require the local governmental entity to pay or release any amounts that are the subject of a good faith dispute made in writing pursuant to the contract or the subject of a claim brought pursuant to s. 255.05 .

(d) The time limitations set forth in this section for payment of payment requests apply to any payment request for retainage made pursuant to this section.

(e) Paragraph (a) does not apply to construction services purchased by a local governmental entity which are paid for, in whole or in part, with federal funds and are subject to federal grantor laws and regulations or requirements that are contrary to any provision of the Local Government Prompt Payment Act.

(f) This subsection does not apply to any construction services purchased by a local governmental entity if the total cost of the construction services purchased as identified in the contract is $200,000 or less.

(9) All payments due under this section and not made within the time periods specified by this section shall bear interest at the rate of 2 percent per month, or the rate specified by contract, whichever is greater.

Retainages Statutes on Public Projects (State Government)

§ 255.052. Substitution of securities for amount retained on public contracts

(1) Under any contract made or awarded by the state or any county, city, or political subdivision thereof, or other public authority, the contractor may, from time to time, withdraw the whole or any portion of the amount retained for payments to the contractor pursuant to the terms of the contract, upon depositing with the Chief Financial Officer:

(a) United States Treasury bonds, United States Treasury notes, United States Treasury certificates of indebtedness, or United States Treasury bills;

(b) Bonds or notes of the State of Florida; or

(c) Bonds of any political subdivision in the state; or

(d) Cash delivered to the State Treasury for the Treasury Cash Deposit Trust Fund; or

(e) Certificates of deposit from state or national banks or state or federal savings and loan associations in the state. Certificates of deposit shall possess the eligibility characteristics defined in s. 625.52.

No amount shall be withdrawn in excess of the market value of the securities listed in paragraphs (a), (b), and (c) at the time of withdrawal or of the par value of such securities, whichever is lower.

(2) The Chief Financial Officer shall regularly collect all interest or income on the obligations so deposited, and shall pay the same, when and as collected, to the contractor who deposited the obligations. If the deposit is in the form of coupon bonds, the Chief Financial Officer shall deliver each coupon as it matures to the contractor.

(3) Any amount deducted by the state or by any county, city, or political subdivision thereof, or by other public authority, pursuant to the terms of the contract, from the amounts retained for payments due the contractor shall be deducted, first from that portion of the amounts retained for which no security has been substituted, then from the proceeds of any deposited security. In the latter case, the contractor shall be entitled to receive interest, coupons, or income only from those securities which remain after such amount has been deducted.

Nothing in this section shall be construed to require the state or any county, city, or political subdivision thereof, or other public authority, to allow the contractor to withdraw the whole or any portion of the amount retained for payments to the contractor except pursuant to the terms of the contract.

§ 255.077. Project closeout and payment of retainage

(1) Each contract for construction services between a public entity and a contractor must provide for the development of a list of items and the estimated cost to complete each item on the list required to render complete, satisfactory, and acceptable the construction services purchased by the public entity. The contract must specify the process for the development of the list and for determining the cost to complete each item on the list, and should include the responsibilities of the public entity and the contractor in developing and reviewing the list and a reasonable time for developing the list, as follows:

(a) For construction projects having an estimated cost of less than $10 million, within 30 calendar days after reaching substantial completion of the construction services purchased as defined in the contract, or, if not defined in the contract, upon reaching beneficial occupancy or use; or

(b) For construction projects having an estimated cost of $10 million or more, within 30 calendar days, unless otherwise extended by contract not to exceed 45 calendar days, after reaching substantial completion of the construction services purchased as defined in the contract, or, if not defined in the contract, upon reaching beneficial occupancy or use.

(2) If the contract between the public entity and the contractor relates to the purchase of construction services on more than one building or structure, or involves a multiphased project, the contract must provide for the development of a list of items required to render complete, satisfactory, and acceptable all the construction services purchased pursuant to the contract for each building, structure, or phase of the project within the time limitations provided in subsection (1).

(3) The failure to include any corrective work or pending items not yet completed on the list developed pursuant to subsection (1) or subsection (2) does not alter the responsibility of the contractor to complete all the construction services purchased pursuant to the contract.

(4) Within 20 business days after developing the list, and after receipt of a proper invoice or payment request, the public entity must pay the contractor the remaining balance of the contract, including any remaining retainage withheld by the public entity pursuant to s. 255.078, less an amount equal to 150 percent of the estimated cost to complete the items on the list.

(5) Upon completion of all items on the list, the contractor may submit a payment request for all remaining retainage withheld by the public entity pursuant to s. 255.078. If a good faith dispute exists as to whether one or more items identified on the list have been completed pursuant to the contract, the public entity may continue to withhold an amount not to exceed 150 percent of the total costs to complete such items.

(6) All items that require correction under the contract and that are identified after the preparation and delivery of the list remain the obligation of the contractor as defined by the contract.

(7) Warranty items may not affect the final payment of retainage as provided in this section or as provided in the contract between the contractor and its subcontractors and suppliers.

(8) Retainage may not be held by a public entity or a contractor to secure payment of insurance premiums under a consolidated insurance program or series of insurance policies issued to a public entity or a contractor for a project or group of projects, and the final payment of retainage as provided in this section may not be delayed pending a final audit by the public entity’s or contractor’s insurance provider.

§ 255.078. Public construction retainage

(1) With regard to any contract for construction services, a public entity may withhold from each progress payment made to the contractor an amount not exceeding 5 percent of the payment as retainage.

(2) This section and s. 255.077 do not prohibit a public entity from withholding retainage at a rate less than 5 percent of each progress payment, from incrementally reducing the rate of retainage pursuant to a schedule provided for in the contract, or from releasing at any point all or a portion of any retainage withheld by the public entity which is attributable to the labor, services, or materials supplied by the contractor or by one or more subcontractors or suppliers. If a public entity makes any payment of retainage to the contractor which is attributable to the labor, services, or materials supplied by one or more subcontractors or suppliers, the contractor must timely remit payment of such retainage to those subcontractors and suppliers.

(3) This section and s. 255.077 do not require the public entity to pay or release any amounts that are the subject of a good faith dispute made in writing pursuant to the contract or the subject of a claim brought pursuant to s. 255.05 .

(4) The same time limits for payment of a payment request apply regardless of whether the payment request is for, or includes, retainage.

(5) Subsection (1) does not apply to construction services purchased by a public entity which are paid for, in whole or in part, with federal funds and are subject to federal grantor laws and regulations or requirements that are contrary to any provision of the Florida Prompt Payment Act.

(6) This section does not apply to any construction services purchased by a public entity if the total cost of the construction services purchased as identified in the contract is $200,000 or less.

Trusted by Thousands of Florida Contractors Like You
For Help With Retainage