I hired a general contractor in late Sept and my project (job) started in Oct. I have made several payments to the general contractor as the job progressed for all the sub contractors work and he has not paid the sub contractors. I have been in conversation with the electrical sub contractor and he w...Read More...Read More
We painted a house and was not paid. Is it worth the expense to foreclose or should we just let the lien sit on the property until they sell. It was only for 9k...Read More
Lien has been filed; order #5825027. No settlement made to-date. Once lien expires after 12mo & if client sells home in future, will it still show on record that she had a lien previously placed on the property?...Read More
I performed the labor for another contractor who is now not answering his phone. I do not have a contract with him on these 6 homes we roofed. Labor only no material. Do I have lien rights?...Read More
I had a lien filed against a property I own by a sub who was not paid by the contractor I hired and I paid contractor in full. Now the dub has filed paperwork against the property as he hasn’t been paid. What can I do?...Read More
We are a contractor and I finished the job in Minnesota on August 12, 2021. I am coming close to my 120 days and I would like to file a lien against the property we remodeled. We did not send a preliminary notice at the beginning of the job. We have done several jobs with this customer and neve...Read More...Read More
Hired by contractor to the progress of work being done by a sub-contractor who was eventually let go. From that point on I was to prepare reports on the contractors project status and definiens in the work for a potential law suit. Reports were prepared and photos taken to substantiate the claims. ...Read More...Read More
i worked for a painting company for 28 yrs when we worked on prevailing wage jobs he paid me the cash part but he said he had the right to keep the benefit side because he pays for my vacation, he didnt pay for my health or 401 in any way i've sat down and figured it out over 28 yrs it adds up to abo...Read More...Read More
I am a subcontractor and we filed a pre lien notice on a job. We completed a dig/backfill so I entered the start and end date. Now the contractor came back and wants us to put in the septic system as well. What do I need to do if I entered an end date for the job if we are not done now?...Read More
Plumber did some rough in work on my house in 2019. Did not return. Finished the job myself, meaning I installed my own toilets and sinks. Now he claims I owe him a staggering amount. Out of line. He has piled up a fee from another job on my (finally) an invoice. I requested invoices along the way ...Read More...Read More
We have a customer who is a subcontractor with a new job. We know that this customer borrowed significant amounts of materials we supplied to another job for this new job. We have been fully paid on the old job. Does knowing this fact change anything about how we prepare for the preliminary no...Read More...Read More
We are a Levelset subscriber. We have contracted with MN United FC a professional soccer team who is a tenant (not the owner) in a facility owned by MN United National Sports Center. Basically we are doing a tenant improvement to the soccer field making it more playable for the professional soc...Read More...Read More
I am in the process of building a house on a lake and the neighbors keep complaining because they don’t like change or are jealous. Once the complaint hits the county, the county immediately places a stop work order without visiting the site going off the neighbors “photos.” We have literally done not...Read More...Read More