Massachusetts Retainage Requirements
- Private Jobs
- Public Jobs
- Top Links
5 Percent
On private projects valued at $3M or more, no more than 5% retainage may be withheld.
30 Days
Once the project has reached substantial completion the prime may submit an invoice for retainage, which must be paid within 30 days of receipt of the invoice.
There's No Process to Recover
N/A
Not Held In Escrow
In Massachusetts, contractors and owners do not need to hold retainage funds in a separate escrow account.
5 Percent
Retainage cannot exceed 5%. The public entity may hold 1% retainage after substantial completion pending final completion of entire work.
65 Day Pay Period
Release (minus the estimated cost to complete or correct unfinished/ unsatisfactory work) is required within 65 days of substantial completion.
There is a Process to Recover
Yes, a certificate from the architect that work is complete is required.
Not Held In Escrow
In Massachusetts, contractors and owners do not need to hold retainage funds in a separate escrow account.
Retainage, also called “retention,” is an amount of money “held back” from a contractor or subcontractor during the course of a construction project. In general, retainage serves two main purposes:
- To provide an incentive to the contractor or subcontractor to complete the project; &
- To give the owner some protection against problems like liens, contractual defaults, delays, and more.
In most states, laws exist to regulate how the parties use the retainage concept, mostly protecting some parties against abuse of the tool from others. The following are resources, legal information, and answers to frequently asked questions about Massachusetts’ retainage requirements.
Massachusetts’ retainage limits and deadlines
On private projects valued at $3M or more, the amount of retainage that can be withheld is not more than 5% of each progress payment. The only exception is projects involving residential dwelling units of 4 or fewer. Upon substantial completion of the project, the prime may submit an invoice for retainage, which must be paid within 30 days of receipt of the invoice. The same 30-day invoice to payment period applies to retainage for subcontractors and suppliers as well.
As far as public projects in Massachusetts are concerned, if the project is awarded by the commonwealth and valued at over $5K, or public works contract awarded by any other governmental entity within the state valued at $2K or more; the amount of retainage that may be withheld is also capped at 5% of each progress payment. The public entity must release retainage to the prime contractor within 65 days of full/substantial completion of the project, or occupancy of the improvement by the public entity; whichever is earlier. Retainage payments to subs and suppliers must be made within 30 days of submission of an invoice for retainage, but may be extended an additional 7 days.