Massachusetts Prompt Payment Guide and FAQs

Ready? Build Your Free Massachusetts
Prompt Payment Now

Make Your Prompt Payment Demand Now
Mass-Prompt-Payment-FAQ

Massachusetts Prompt Payment Overview

Massachusetts Prompt Payment Requirements


45
DAYS
Prime Contractors

On private projects, Massachusetts Prompt Pay law requires property owners to make progress payments to Prime Contractors within 45 days after approval of invoice. The invoice must be approved or denied within 15 days.


45
DAYS
Subcontractors

Prime Contractors on private projects in Massachusetts must make payments to subcontractors within 45 days after approval of invoice. The invoice must be approved or denied within 15 days (but may be extended an additional 7 days).


45
DAYS
Suppliers

On private projects, Massachusetts Prompt Pay laws require payments to material suppliers within 45 days of invoice approval. The invoice must be approved or denied within 15 days (but may be extended an additional 7 days).


12%
/ YEAR
Interest & Fees

If payment is late according to Massachusetts Prompt Payment requirements, the state's general interest statute presumably applies, since this is a contract dispute. The general interest penalty is 12% per year.

15
DAYS
Prime Contractors

On a public project in Massachusetts, prompt payment laws require the public agency to make progress payments to the GC within 15 days of invoice. The deadline is extended to 30 days for payments from the Commonwealth. Final payment to prime contractors is due within 65 days of substantial completion of the project; the retainage payment is due within 30 days from submission of invoice.


37
DAYS
Subcontractors

On public projects, Massachusetts prompt pay laws require GCs to make progress payments to subcontractors immediately after receipt of payment from the public agency. Final payment is due within 65 days of substantial completion of the particular subcontractor's work. Retainage payments to subcontractors is due 37 days from submission of invoice.


37
DAYS
Suppliers

For suppliers in Massachusetts, progress payments are due immediately upon receipt of payment by their hiring party. Final payment is due within 65 days of the supplier's last day of furnishing. Retainage payment is due to suppliers within 37 days from invoice submission.


3%
Interest & Fees

If payment is late on a public project in Massachusetts, the Prompt Pay laws set the interest penalty at the federal rate plus 3%.

Prompt payment laws are a set of rules that regulate the acceptable amount of time in which payments must be made to contractors and subs. This is to ensure that everyone on a construction project is paid in a timely fashion. These statutes provide a framework for the timing of payments to ensure cash flow and working capital.

Projects Covered by Prompt Payment in Massachusetts

Massachusetts has two separate sets of statutes that govern payment on both private and public construction projects.

Private Projects

Private construction projects in Massachusetts are regulated by Mass. Gen. Laws. 149 § 29E. These rules apply to all private projects with an original contract price of $3 million or more, with one exception: MA prompt payment rules don’t apply to residential projects of 4 or fewer.

Payment Deadlines for Private Projects

Once a prime contractor has submitted a payment request on a private construction project, the owner has 15 days to either approve or deny the request. After approval, the owner then has 45 days to make payment to the prime. So Massachusetts private property owners have 60 total days from receipt of the pay request to release payment to the prime contractor.

Private project payments from the GC down the chain follow the same basic formula, except Massachusetts Prompt Pay laws give each party an additional 7 days to approve or deny invoices. So the GC has 22 days to approve or deny a payment request from a subcontractor or supplier. Following invoice approval, the GC has 45 days to submit payment to subs and suppliers.

Payments from subs to their sub-subs or suppliers must be approved within 29 days. If approved, payments must be released within 45 days. And so on down the payment chain.

MA Penalties for Late Payment on Private Projects

There are specific circumstances provided in the statute regarding when payments can be rightfully withheld. However, if none of those circumstances exist, or payment is otherwise late, The private prompt pay statutes does not specifically state an interest rate, but the general judgment interest rate for contract actions is 12% per year (1%/month).

Public Projects

Massachusetts public works projects are regulated by Mass. Gen. Laws 30 §§39F to 39K.

Payment Deadlines for Public Projects

Prompt Pay deadlines for public projects in Massachusetts depend on the type of payment – progress or final – being made and to whom. Progress payments to the prime contractor on a public project are due within 15 days after receipt of a proper request for payment. If the project is contracted by a commonwealth entity, then the time is extended to 30 days. As for final payments to the prime contractor, these payments must be made within 65 days of substantial completion.

Once the prime contractor has received a progress payment, they are required to pay their subcontractors and suppliers immediately upon receipt. Final payments to subcontractors must be made within 65 days of substantial completion of that subcontractor’s work.

MA Penalties for Late Payment on Public Projects

Any payments that are either late or wrongfully withheld on a public construction project in Massachusetts are subject to interest penalties on the unpaid balance. Interest will begin to accrue on the first day payment is past due at a rate equal to the discount rate charged by the Federal Reserve, plus 3% per year. There are no provisions regarding attorney fees.

Massachusetts Prompt Payment FAQs

Frequently asked questions about Massachusetts prompt pay laws, with answers written by

Massachusetts Prompt Payment Private Projects FAQs

What types of private projects are subject to Massachusetts’ prompt payment laws?

The Massachusetts prompt payment laws apply to nearly all private construction projects valued at over $3M. The only exception is if the property contains or is designed to contain 1-4 residential dwelling units.

Summary
Massachusetts Prompt Payment Law
Article Name
Massachusetts Prompt Payment Law
Description
Summary of Massachusetts Prompt Payment requirements and laws for Massachusetts construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

When is the deadline for payment under Massachusetts' prompt payment laws?

Owners to prime contractors

Payments must be made no later than a total of 60 days after the pay application is submitted.

Progress payment applications must be submitted within 30 days of the end of the month that labor and/or materials were provided. Once received, the application must be approved or denied within 15 days. Lastly, once approved payment must be released within 45 days.

Contractors to subs/suppliers

Payments by contractors and each subsequent tier are subject to the same payment time frames. However, the time for payment may be extended by up to 7 additional days.

Summary
Massachusetts Prompt Payment Law
Article Name
Massachusetts Prompt Payment Law
Description
Summary of Massachusetts Prompt Payment requirements and laws for Massachusetts construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Are there reasons for which payment may be withheld past the general deadline?

On private construction projects, Massachusetts does not specifically identify reasons for which payment may be withheld. So it is likely that the contract between the parties, and case law, will govern the particular reasons why payments may be withheld. If payments are late on a private project, parties still have the right to file a mechanics lien in Mass.

Summary
Massachusetts Prompt Payment Law
Article Name
Massachusetts Prompt Payment Law
Description
Summary of Massachusetts Prompt Payment requirements and laws for Massachusetts construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

If I am paid late according to Massachusetts’ prompt payment laws, can I obtain interest or other penalty payments?

The private prompt payment statute in Massachusetts does not define the interest penalty for late payments. However, the state does have a statute that sets the interest rate for contract disputes (MA Gen. Law Ch. 231 Sec. 6C). If the construction contract does not specify an interest penalty, this general interest rate of 12% would presumably apply.

Summary
Massachusetts Prompt Payment Law
Article Name
Massachusetts Prompt Payment Law
Description
Summary of Massachusetts Prompt Payment requirements and laws for Massachusetts construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Can I include prompt payment fees in a Massachusetts mechanics lien claim?

No, no miscellaneous amounts may be included in a Massachusetts mechanics lien claim. In order to recover interest penalties for late payment, claimants will need to file a lawsuit for a claim under the prompt pay laws.

Summary
Massachusetts Prompt Payment Law
Article Name
Massachusetts Prompt Payment Law
Description
Summary of Massachusetts Prompt Payment requirements and laws for Massachusetts construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

What is the best practice for making a demand to a non-paying party to get prompt payment fees?

Sending a notice of intent to lien along with a prompt payment demand letter is generally the best method for encouraging parties to make payment. If payment still isn’t forthcoming, a lawsuit may be necessary.

• See: How to Make a Claim Under State Prompt Payment Laws

Summary
Massachusetts Prompt Payment Law
Article Name
Massachusetts Prompt Payment Law
Description
Summary of Massachusetts Prompt Payment requirements and laws for Massachusetts construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Massachusetts Prompt Payment Public Projects FAQs

What types of public projects are subject to Massachusetts’ prompt payment laws?

On projects awarded by a Commonwealth entity, the prompt payment laws apply to all such projects where the original contract is valued at $5,000 or more. All other public works projects commissioned by a county, city, town, or other public entity will be subject to the prompt payment laws if the original contract price is at least $2,000 or more.

Summary
Massachusetts Prompt Payment Law
Article Name
Massachusetts Prompt Payment Law
Description
Summary of Massachusetts Prompt Payment requirements and laws for Massachusetts construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

When is the deadline for payment under Massachusetts' prompt payment laws?

The timing of progress payments varies depending on whether the project was commissioned by the Commonwealth or some other public entity.

• Commonwealth projects: 30 days after receipt of an invoice

• All other projects: 15 days after receipt of an invoice

Final payments on all covered projects must be made by the public entity within 65 days from the earlier of either:

• Full/substantial completion when less than 1% of the original contract price remains; or

• The date the awarding authority takes possession for the occupancy of the substantially completed building.

Summary
Massachusetts Prompt Payment Law
Article Name
Massachusetts Prompt Payment Law
Description
Summary of Massachusetts Prompt Payment requirements and laws for Massachusetts construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Are there reasons for which payment may be withheld past the general deadline?

The awarding authority may withhold from final payments either the fair value of claims against the contractor and the cost to complete unsatisfactory or incomplete items, or funds sufficient to pay any direct payment claims by subcontractors on the project.

Summary
Massachusetts Prompt Payment Law
Article Name
Massachusetts Prompt Payment Law
Description
Summary of Massachusetts Prompt Payment requirements and laws for Massachusetts construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

If I am paid late according to Massachusetts’ prompt payment laws, can I obtain interest or other penalty payments?

On public construction projects, the Massachusetts statute for prompt payment sets the interest penalty at the Federal Reserve discount rate plus 3% per year. Interest will begin to accrue:

• Commonwealth progress payments: 24th day after receipt of the pay app

• All other progress payments: 15 days after receipt of the pay app.

Summary
Massachusetts Prompt Payment Law
Article Name
Massachusetts Prompt Payment Law
Description
Summary of Massachusetts Prompt Payment requirements and laws for Massachusetts construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Can I include prompt payment fees in a Massachusetts payment bond claim?

No, no miscellaneous amounts may be included in a Massachusetts payment bond claim. In order to recover interest penalties for late payment, claimants will need to file a lawsuit for a claim under the prompt pay laws.

Summary
Massachusetts Prompt Payment Law
Article Name
Massachusetts Prompt Payment Law
Description
Summary of Massachusetts Prompt Payment requirements and laws for Massachusetts construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

What is the best practice for making a demand to a non-paying party to get prompt payment fees?

Sending a notice of intent to make a bond claim along with a prompt payment demand letter is generally the best method for encouraging parties to make payment. If payment still isn’t forthcoming, a lawsuit may be necessary.

• See: How to Make a Claim Under State Prompt Payment Laws

Summary
Massachusetts Prompt Payment Law
Article Name
Massachusetts Prompt Payment Law
Description
Summary of Massachusetts Prompt Payment requirements and laws for Massachusetts construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Need More Help with Massachusetts Prompt Payment? We're Here.

Ask an expert for free

Check out our payment experts
Construction attorneys: Courtney Stricklen, Christopher Ng, Andrea Goldman, and Peter Ryan

Massachusetts Prompt Payment
Recent Questions & Answers

Prompt payment

I got a construction job done yesterday and the contractor is urging me pay today. How long do I legally have to pay him?

I am sending $600 worth of beer from my brewery in San Diego, CA to a liquor store in Ipswich, MA.

I have stipulated shipping cost be paid ahead of time and Net 30 terms for product payment. If the owner were to become delinquent on payment, how would I recoup my loss? Can I file a lien? What is the Massachusetts law on prompt payment of a product B2B?

How long does a contractor have to submit an invoice

Contractor hires a sub-cotractor to do work for a homeowner. How long does the contractor have to submit sub-contractor's invoice to homeowner ? Thanks !

How to file a lien in Massachusetts

Need to file a Massachusetts mechanics lien? File your mechanics lien with Levelset, the lien experts quickly and easily. Or you can follow the 3 steps below to file a lien yourself with Levelset’s free information.
File with the Mechanics Lien Experts
Product screenshot suggesting a found material supplier on a project details screen.
We’re the Mechanics Lien experts. With us it’s fast, easy, affordable, and done right!
File Now

Want to Learn More about How Massachusetts Contractors Pay?
Core & Main
Rating 5.0
Prologis
Rating 5.0
CBRE Group
Rating 5.0
Brookfield Properties
Rating 5.0
See other Lists of Contractors and How to Best Work With Them

Massachusetts Prompt Payment Statutes

Getting informed about prompt payment laws is important. An examination of Massachusetts’ prompt payment laws, the rules and regulations related to payment timing, is important to know your rights and responsibilities as a party on a construction project. Massachusetts’ specific laws can be found in: Mass. Gen. Laws c. 149 §29E for private projects and M.G.L. c. 30 §§39F-39K on public projects, which are reproduced below. Updated as of September 2021.

Prompt Payment Statute on Private Projects

149 § 29E. Fairness in private construction contracts

(a) As used in this section the following words shall have the following meanings, unless the context clearly requires otherwise:

“Contract for construction”, a contract for which a lien may be established under sections 2 or 4 of chapter 254 on a project for which the person whose contract with the project owner has an original contract price of $3,000,000 or more; provided, however, this shall not include projects containing or designed to contain at least 1 but not more than 4 dwelling units.

“Insolvent”, insolvent as defined under federal bankruptcy law or being a debtor in a proceeding commenced under federal bankruptcy law or under the corresponding law of another country, or being a debtor in a receivership proceeding or having made an assignment for the benefit of creditors.

(b) A communication required in this section to be in writing may be submitted in electronic form and by electronic means.

(c) Every contract for construction shall provide reasonable time periods within which: (i) a person seeking payment under the contract shall submit written applications for periodic progress payments; (ii) the person receiving the application shall approve or reject the application, whether in whole or in part; and (iii) the person approving the application shall pay the amount approved. The time periods for each application for a periodic progress payment shall not exceed: (i) for submission, 30 days, beginning with the end of the first calendar month occurring at least 14 days after the person seeking payment has commenced performance; (ii) for approval or rejection, 15 days after submission; provided, however, that the time period, as applicable to approval or rejection by the person at each tier of contract below the owner of the project, may be extended by 7 days more than the time period applicable to the person at the tier of contract above the person; and (iii) for payment, 45 days after approval, unless the payment is subject to the condition of receipt of payment by a third person but only to the extent enforceable under subsection (e). An application for a periodic progress payment which is neither approved nor rejected within the time period shall be deemed to be approved unless it is rejected before the date payment is due. A rejection of an application for a periodic progress payment, whether in whole or in part, shall be made in writing and shall include an explanation of the factual and contractual basis for the rejection and shall be certified as made in good faith. A rejection of an application for a periodic progress payment shall be subject to the applicable dispute resolution procedure. A provision in the contract which requires a party to delay commencement of the procedure until a date later than 60 days after the rejection shall be void and unenforceable.

(d) Every contract for construction shall provide a reasonable time period within which a written request submitted by a person seeking an increase in the contract price shall be approved or rejected, whether in whole or in part. The time period shall not exceed 30 days after the later of commencement of the performance of the work on which the request is based or submission of the written request; provided, however, that the time period, as applicable to approval or rejection by the person at each tier of contract below the owner of the project, may be extended by 7 days more than the time period applicable to the person at the tier of contract above the person. A request which is neither approved nor rejected within such time period shall be deemed to be approved and may be submitted for payment within the next application for a periodic progress payment, unless it is rejected before the date payment is due. A rejection of a request, whether in whole or in part, shall be made in writing, shall include an explanation of the factual and contractual basis for the rejection and shall be certified as made in good faith. A rejection of a request shall be subject to the applicable dispute resolution procedure. A provision in the contract which requires a party to delay commencement of the procedure until a date later than 60 days after the rejection shall be void and unenforceable.

(e) A provision in a contract for construction which makes payment to a person performing the construction conditioned upon receipt of payment from a third person that is not a party to the contract shall be void and unenforceable, except:

(1) to the extent of amounts not received from the third person because the person performing the construction failed to perform under its contract and failed to cure the non-performance within the time required by the contract after receipt of written notice as provided in the contract or, in the case of contract lacking a cure and notice provision, failed to cure the non-performance within 14 days after receipt of written notice of the failure to perform; or

(2) to the extent of amounts not received from the third person because the third person is insolvent or becomes insolvent within 90 days after the date of submission of the requisition for which payment is sought; provided, however, that the person seeking to enforce the payment condition (i) filed a notice of contract under chapter 254 and in the case of a person having no direct contractual relationship with the original contractor, also sent a notice of identification within the time required under said chapter 254, prior to the person’s submission of the first application for payment after commencement of performance at the project site and did not dissolve the lien created by the filing of such notice of contract; and (ii) within the time periods allowed by said chapter 254 files a statement of amount due and commenced or commences a civil action to enforce the lien; and (iii) pursues all reasonable legal remedies to obtain payment from the person with whom the person had a direct contract unless and until there is a reasonable likelihood the action shall not result in obtaining payment.

The foregoing exceptions shall be expressly stated in any conditional payment provision and the person seeking to enforce the payment condition shall have the burden of proof as to each element. Nothing in this section or in a conditional payment provision shall be valid as a defense to enforcement of a lien claimed under said chapter 254 by the person furnishing the construction nor shall it excuse compliance with said chapter 254. A party aggrieved by the failure of the party seeking to enforce the payment condition to pursue all reasonable legal remedies to obtain payment may avail itself of the procedure set forth in section 15A of said chapter 254, for a summary determination of whether all reasonable legal remedies have been fulfilled with respect to the particular lien claim at issue; provided, however, that the aggrieved party has first made a request in writing that the party seeking to assert the payment provision identify the legal remedies the aggrieved party has pursued and either: (i) has not received a response in writing within 10 days after making the request; or (ii) having received a response, has requested the party to pursue specific additional legal remedies and the party has failed unreasonably to take such actions.

(f) A provision in a contract for construction, including without limitation a payment condition enforceable under subsection (e), purporting to require a person to continue performance of the construction if payment of an approved amount is due under the terms of the contract but is not received, and more than 30 days have elapsed since the date payment was due, shall be void and unenforceable, except for: (i) a dispute regarding the quality or quantity of the construction so furnished; or (ii) a default by the person under the contract for construction after approval of the payment; provided, however, that the person has received (i) a prior written notice of such dispute or default certified as made in good faith; and (ii) all sums due less any amounts attributable to the dispute or default.

(g) A provision in a contract for construction which purports to waive or limit any provisions of this section shall be void and unenforceable.

Summary
Massachusetts Prompt Payment Law
Article Name
Massachusetts Prompt Payment Law
Description
Summary of Massachusetts Prompt Payment requirements and laws for Massachusetts construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Prompt Payment Statute on Public Projects

30 § 39F. Construction contracts; assignment and subrogation; subcontractor defined; enforcement of claim for direct payment; deposit, reduction of disputed amounts

(1) Every contract awarded pursuant to sections forty-four A to L, inclusive, of chapter one hundred and forty-nine shall contain the following subparagraphs (a) through (i) and every contract awarded pursuant to section thirty-nine M of chapter thirty shall contain the following subparagraphs (a) through (h) and in each case those subparagraphs shall be binding between the general contractor and each subcontractor.

(a) Forthwith after the general contractor receives payment on account of a periodic estimate, the general contractor shall pay to each subcontractor the amount paid for the labor performed and the materials furnished by that subcontractor, less any amount specified in any court proceedings barring such payment and also less any amount claimed due from the subcontractor by the general contractor.

(b) Not later than the sixty-fifth day after each subcontractor substantially completes his work in accordance with the plans and specifications, the entire balance due under the subcontract less amounts retained by the awarding authority as the estimated cost of completing the incomplete and unsatisfactory items of work, shall be due the subcontractor; and the awarding authority shall pay that amount to the general contractor. The general contractor shall forthwith pay to the subcontractor the full amount received from the awarding authority less any amount specified in any court proceedings barring such payment and also less any amount claimed due from the subcontractor by the general contractor.

(c) Each payment made by the awarding authority to the general contractor pursuant to subparagraphs (a) and (b) of this paragraph for the labor performed and the materials furnished by a subcontractor shall be made to the general contractor for the account of that subcontractor; and the awarding authority shall take reasonable steps to compel the general contractor to make each such payment to each such subcontractor. If the awarding authority has received a demand for direct payment from a subcontractor for any amount which has already been included in a payment to the general contractor or which is to be included in a payment to the general contractor for payment to the subcontractor as provided in subparagraphs (a) and (b), the awarding authority shall act upon the demand as provided in this section.

(d) If, within seventy days after the subcontractor has substantially completed the subcontract work, the subcontractor has not received from the general contractor the balance due under the subcontract including any amount due for extra labor and materials furnished to the general contractor, less any amount retained by the awarding authority as the estimated cost of completing the incomplete and unsatisfactory items of work, the subcontractor may demand direct payment of that balance from the awarding authority. The demand shall be by a sworn statement delivered to or sent by certified mail to the awarding authority, and a copy shall be delivered to or sent by certified mail to the general contractor at the same time. The demand shall contain a detailed breakdown of the balance due under the subcontract and also a statement of the status of completion of the subcontract work. Any demand made after substantial completion of the subcontract work shall be valid even if delivered or mailed prior to the seventieth day after the subcontractor has substantially completed the subcontract work. Within ten days after the subcontractor has delivered or so mailed the demand to the awarding authority and delivered or so mailed a copy to the general contractor, the general contractor may reply to the demand. The reply shall be by a sworn statement delivered to or sent by certified mail to the awarding authority and a copy shall be delivered to or sent by certified mail to the subcontractor at the same time. The reply shall contain a detailed breakdown of the balance due under the subcontract including any amount due for extra labor and materials furnished to the general contractor and of the amount due for each claim made by the general contractor against the subcontractor.

(e) Within fifteen days after receipt of the demand by the awarding authority, but in no event prior to the seventieth day after substantial completion of the subcontract work, the awarding authority shall make direct payment to the subcontractor of the balance due under the subcontract including any amount due for extra labor and materials furnished to the general contractor, less any amount (i) retained by the awarding authority as the estimated cost of completing the incomplete or unsatisfactory items of work, (ii) specified in any court proceedings barring such payment, or (iii) disputed by the general contractor in the sworn reply; provided, that the awarding authority shall not deduct from a direct payment any amount as provided in part (iii) if the reply is not sworn to, or for which the sworn reply does not contain the detailed breakdown required by subparagraph (d). The awarding authority shall make further direct payments to the subcontractor forthwith after the removal of the basis for deductions from direct payments made as provided in parts (i) and (ii) of this subparagraph.

(f) The awarding authority shall forthwith deposit the amount deducted from a direct payment as provided in part (iii) of subparagraph (e) in an interest-bearing joint account in the names of the general contractor and the subcontractor in a bank in Massachusetts selected by the awarding authority or agreed upon by the general contractor and the subcontractor and shall notify the general contractor and the subcontractor of the date of the deposit and the bank receiving the deposit. The bank shall pay the amount in the account, including accrued interest, as provided in an agreement between the general contractor and the subcontractor or as determined by decree of a court of competent jurisdiction.

(g) All direct payments and all deductions from demands for direct payments deposited in an interest-bearing account or accounts in a bank pursuant to subparagraph (f) shall be made out of amounts payable to the general contractor at the time of receipt of a demand for direct payment from a subcontractor and out of amounts which later become payable to the general contractor and in the order of receipt of such demands from subcontractors. All direct payments shall discharge the obligation of the awarding authority to the general contractor to the extent of such payment.

(h) The awarding authority shall deduct from payments to a general contractor amounts which, together with the deposits in interest-bearing accounts pursuant to subparagraph (f), are sufficient to satisfy all unpaid balances of demands for direct payment received from subcontractors. All such amounts shall be earmarked for such direct payments, and the subcontractors shall have a right in such deductions prior to any claims against such amounts by creditors of the general contractor.

(i) If the subcontractor does not receive payment as provided in subparagraph (a) or if the general contractor does not submit a periodic estimate for the value of the labor or materials performed or furnished by the subcontractor and the subcontractor does not receive payment for same when due less the deductions provided for in subparagraph (a), the subcontractor may demand direct payment by following the procedure in subparagraph (d) and the general contractor may file a sworn reply as provided in that same subparagraph. A demand made after the first day of the month following that for which the subcontractor performed or furnished the labor and materials for which the subcontractor seeks payment shall be valid even if delivered or mailed prior to the time payment was due on a periodic estimate from the general contractor. Thereafter the awarding authority shall proceed as provided in subparagraph (e), (f), (g) and (h).

(2) Any assignment by a subcontractor of the rights under this section to a surety company furnishing a bond under the provisions of section twenty-nine of chapter one hundred forty-nine shall be invalid. The assignment and subrogation rights of the surety to amounts included in a demand for direct payment which are in the possession of the awarding authority or which are on deposit pursuant to subparagraph (f) of paragraph (1) shall be subordinate to the rights of all subcontractors who are entitled to be paid under this section and who have not been paid in full.

(3) “Subcontractor” as used in this section (i) for contracts awarded as provided in sections forty-four A to forty-four H, inclusive, of chapter one hundred forty-nine shall mean a person who files a sub-bid and receives a subcontract as a result of that filed sub-bid or who is approved by the awarding authority in writing as a person performing labor or both performing labor and furnishing materials pursuant to a contract with the general contractor, (ii) for contracts awarded as provided in paragraph (a) of section thirty-nine M of chapter thirty shall mean a person approved by the awarding authority in writing as a person performing labor or both performing labor and furnishing materials pursuant to a contract with the general contractor, and (iii) for contracts with the commonwealth not awarded as provided in forty-four A to forty-four H, inclusive, of chapter one hundred forty-nine shall also mean a person contracting with the general contractor to supply materials used or employed in a public works project for a price in excess of five thousand dollars.

(4) A general contractor or a subcontractor shall enforce a claim to any portion of the amount of a demand for direct payment deposited as provided in subparagraph (f) of paragraph 1 by a petition in equity in the superior court against the other and the bank shall not be a necessary party. A subcontractor shall enforce a claim for direct payment or a right to require a deposit as provided in subparagraph (f) of paragraph 1 by a petition in equity in the superior court against the awarding authority and the general contractor shall not be a necessary party. Upon motion of any party the court shall advance for speedy trial any petition filed as provided in this paragraph. Sections fifty-nine and fifty-nine B of chapter two hundred thirty-one shall apply to such petitions. The court shall enter an interlocutory decree upon which execution shall issue for any part of a claim found due pursuant to sections fifty-nine and fifty-nine B and, upon motion of any party, shall advance for speedy trial the petition to collect the remainder of the claim. Any party aggrieved by such interlocutory decree shall have the right to appeal therefrom as from a final decree. The court shall not consolidate for trial the petition of any subcontractor with the petition of one or more subcontractors or the same general contract unless the court finds that a substantial portion of the evidence of the same events during the course of construction (other than the fact that the claims sought to be consolidated arise under the same general contract) is applicable to the petitions sought to be consolidated and that such consolidation will prevent unnecessary duplication of evidence. A decree in any such proceeding shall not include interest on the disputed amount deposited in excess of the interest earned for the period of any such deposit. No person except a subcontractor filing a demand for direct payment for which no funds due the general contractor are available for direct payment shall have a right to file a petition in court of equity against the awarding authority claiming a demand for direct payment is premature and such subcontractor must file the petition before the awarding authority has made a direct payment to the subcontractor and has made a deposit of the disputed portion as provided in part (iii) of subparagraph (e) and in subparagraph (f) of paragraph (1).

(5) In any petition to collect any claim for which a subcontractor has filed a demand for direct payment the court shall, upon motion of the general contractor, reduce by the amount of any deposit of a disputed amount by the awarding authority as provided in part (iii) of subparagraph (e) and in subparagraph (f) of paragraph (1) any amount held under a trustee writ or pursuant to a restraining order or injunction.

Summary
Massachusetts Prompt Payment Law
Article Name
Massachusetts Prompt Payment Law
Description
Summary of Massachusetts Prompt Payment requirements and laws for Massachusetts construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

30 § 39G. Completion of public works; semi-final and final estimates; payments; extra work; disputed items

Upon substantial completion of the work required by a contract with the commonwealth, or any agency or political subdivision thereof, for the construction, reconstruction, alteration, remodeling, repair or improvement of public ways, including bridges and other highway structures, sewers and, water mains, airports and other public works, the contractor shall present in writing to the awarding authority its certification that the work has been substantially completed. Within twenty-one days thereafter, the awarding authority shall present to the contractor either a written declaration that the work has been substantially completed or an itemized list of incomplete or unsatisfactory work items required by the contract sufficient to demonstrate that the work has not been substantially completed. The awarding authority may include with such list a notice setting forth a reasonable time, which shall not in any event be prior to the contract completion date, within which the contractor must achieve substantial completion of the work. In the event that the awarding authority fails to respond, by presentation of a written declaration or itemized list as aforesaid, to the contractor’s certification within the twenty-one day period, the contractor’s certification shall take effect as the awarding authority’s declaration that the work has been substantially completed.

Within sixty-five days after the effective date of a declaration of a substantial completion, the awarding authority shall prepare and forthwith send to the contractor for acceptance a substantial completion estimate for the quantity and price of the work done and all but one per cent retainage, if held by the awarding authority, on that work, including the quantity, price and all but one per cent retainage, if held by the awarding authority, for the undisputed part of each work item and extra work item in dispute but excluding the disputed part thereof, less the estimated cost of completing all incomplete and unsatisfactory work items and less the total periodic payments made to date for the work. The awarding authority also shall deduct from the substantial completion estimate an amount equal to the sum of all demands for direct payment filed by subcontractors and not yet paid to subcontractors or deposited in joint accounts pursuant to section thirty-nine F, but no contract subject to said section thirty-nine F shall contain any other provision authorizing the awarding authority to deduct any amount by virtue of claims asserted against the contract by subcontractors, material suppliers or others.

If the awarding authority fails to prepare and send to the contractor any substantial completion estimate required by this section on or before the date herein above set forth, the awarding authority shall pay to the contractor interest on the amount which would have been due to the contractor pursuant to such substantial completion estimate at the rate of three percentage points above the rediscount rate then charged by the Federal Reserve Bank of Boston from such date to the date on which the awarding authority sends that substantial completion estimate to the contractor for acceptance or to the date of payment therefor, whichever occurs first. The awarding authority shall include the amount of such interest in the substantial completion estimate.

Within fifteen days after the effective date of the declaration of substantial completion, the awarding authority shall send to the contractor by certified mail, return receipt requested, a complete list of all incomplete or unsatisfactory work items, and, unless delayed by causes beyond his control, the contractor shall complete all such work items within forty-five days after the receipt of such list or before the then contract completion date, whichever is later. If the contractor fails to complete such work within such time, the awarding authority may, subsequent to seven days’ written notice to the contractor by certified mail, return receipt requested, terminate the contract and complete the incomplete or unsatisfactory work items and charge the cost of same to the contractor.

Within thirty days after receipt by the awarding authority of a notice from the contractor stating that all of the work required by the contract has been completed, the awarding authority shall prepare and forthwith send to the contractor for acceptance a final estimate for the quantity and price of the work done and all retainage, if held by the awarding authority, on that work less all payments made to date, unless the awarding authority’s inspection shows that work items required by the contract remain incomplete or unsatisfactory, or that documentation required by the contract has not been completed. If the awarding authority fails to prepare and send to the contractor the final estimate within thirty days after receipt of notice of completion, the awarding authority shall pay to the contractor interest on the amount which would have been due to the contractor pursuant to such final estimate at the rate hereinabove provided from the thirtieth day after such completion until the date on which the awarding authority sends the final estimate to the contractor for acceptance or the date of payment therefor, whichever occurs first, provided that the awarding authority’s inspection shows that no work items required by the contract remain incomplete or unsatisfactory. Interest shall not be paid hereunder on amounts for which interest is required to be paid in connection with the substantial completion estimate as hereinabove provided. The awarding authority shall include the amount of the interest required to be paid hereunder in the final estimate.

The awarding authority shall pay the amount due pursuant to any substantial completion or final estimate within thirty-five days after receipt of written acceptance for such estimate from the contractor and shall pay interest on the amount due pursuant to such estimate at the rate hereinabove provided from that thirty-fifth day to the date of payment. Within 15 days, 30 days in the case of the commonwealth, after receipt from the contractor, at the place designated by the awarding authority, if such place is so designated, of a periodic estimate requesting payment of the amount due for the preceding periodic estimate period, the awarding authority shall make a periodic payment to the contractor for the work performed during the preceding periodic estimate period and for the materials not incorporated in the work but delivered and suitably stored at the site, or at some location agreed upon in writing, to which the contractor has title or to which a subcontractor has title and has authorized the contractor to transfer title to the awarding authority, upon certification by the contractor that he is the lawful owner and that the materials are free from all encumbrances. The awarding authority shall include with each such payment interest on the amount due pursuant to such periodic estimate at the rate herein above provided from the due date. In the case of periodic payments, the contracting authority may deduct from its payment a retention based on its estimate of the fair value of its claims against the contractor, a retention for direct payments to subcontractors based on demands for same in accordance with the provisions of section thirty-nine F, and a retention to secure satisfactory performance of the contractual work not exceeding five per cent of the approved amount of any periodic payment, and the same right to retention shall apply to bonded subcontractors entitled to direct payment under section thirty-nine F of chapter thirty; provided, that a five per cent value of all items that are planted in the ground shall be deducted from the periodic payments until final acceptance.

No periodic, substantial completion or final estimate or acceptance or payment thereof shall bar a contractor from reserving all rights to dispute the quantity and amount of, or the failure of the awarding authority to approve a quantity and amount of, all or part of any work item or extra work item.

Substantial completion, for the purposes of this section, shall mean either that the work required by the contract has been completed except for work having a contract price of less than one per cent of the then adjusted total contract price, or substantially all of the work has been completed and opened to public use except for minor incomplete or unsatisfactory work items that do not materially impair the usefulness of the work required by the contract.

Summary
Massachusetts Prompt Payment Law
Article Name
Massachusetts Prompt Payment Law
Description
Summary of Massachusetts Prompt Payment requirements and laws for Massachusetts construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

30 § 39K. Public construction, etc., contracts; payments

Every contract for the construction, reconstruction, alteration, remodeling, repair or demolition of any public building by the commonwealth, or by any county, city, town, district, board, commission or other public body, when the amount is more than five thousand dollars in the case of the commonwealth and more than two thousand dollars in the case of any county, city, town, district, board, commission or other public body, shall contain the following paragraph:– Within fifteen days (30 days in the case of the commonwealth, including local housing authorities) after receipt from the contractor, at the place designated by the awarding authority if such a place is so designated, of a periodic estimate requesting payment of the amount due for the preceding month, the awarding authority will make a periodic payment to the contractor for the work performed during the preceding month and for the materials not incorporated in the work but delivered and suitably stored at the site (or at some location agreed upon in writing) to which the contractor has title or to which a subcontractor has title and has authorized the contractor to transfer title to the awarding authority, upon certification by the contractor that he is the lawful owner and that the materials are free from all encumbrances, but less (1) a retention based on its estimate of the fair value of its claims against the contractor and less (2) a retention for direct payments to subcontractors based on demands for same in accordance with the provisions of section thirty-nine F, and less (3) a retention not exceeding five per cent of the approved amount of the periodic payment. After the receipt of a periodic estimate requesting final payment and within sixty-five days after (a) the contractor fully completes the work or substantially completes the work so that the value of the work remaining to be done is, in the estimate of the awarding authority, less than one per cent of the original contract price, or (b) the contractor substantially completes the work and the awarding authority takes possession for occupancy, whichever occurs first, the awarding authority shall pay the contractor the entire balance due on the contract less (1) a retention based on its estimate of the fair value of its claims against the contractor and of the cost of completing the incomplete and unsatisfactory items of work and less (2) a retention for direct payments to subcontractors based on demands for same in accordance with the provisions of section thirty-nine F, or based on the record of payments by the contractor to the subcontractors under this contract if such record of payment indicates that the contractor has not paid subcontractors as provided in section thirty-nine F. If the awarding authority fails to make payment as herein provided, there shall be added to each such payment daily interest at the rate of three percentage points above the rediscount rate than charged by the Federal Reserve Bank of Boston commencing on the first day after said payment is due and continuing until the payment is delivered or mailed to the contractor; provided, that no interest shall be due, in any event, on the amount due on a periodic estimate for final payment until fifteen days (twenty-four days in the case of the commonwealth) after receipt of such a periodic estimate from the contractor, at the place designated by the awarding authority if such a place is so designated. The contractor agrees to pay to each subcontractor a portion of any such interest paid in accordance with the amount due each subcontractor.

The awarding authority may make changes in any periodic estimate submitted by the contractor and the payment due on said periodic estimate shall be computed in accordance with the changes so made, but such changes or any requirement for a corrected periodic estimate shall not affect the due date for the periodic payment or the date for the commencement of interest charges on the amount of the periodic payment computed in accordance with the changes made, as provided herein; provided, that the awarding authority may, within seven days after receipt, return to the contractor for correction, any periodic estimate which is not in the required form or which contains computations not arithmetically correct and, in that event, the date of receipt of such periodic estimate shall be the date of receipt of the corrected periodic estimate in proper form and with arithmetically correct computations. The date of receipt of a periodic estimate received on a Saturday shall be the first working day thereafter. The provisions of section thirty-nine G shall not apply to any contract for the construction, reconstruction, alteration, remodeling, repair or demolition of any public building to which this section applies.

All periodic estimates shall be submitted to the awarding authority, or to its designee as set forth in writing to the contractor, and the date of receipt by the awarding authority or its designee shall be marked on the estimate. All periodic estimates shall contain a separate item for each filed subtrade and each sub-subtrade listed in sub-bid form as required by specifications and a column listing the amount paid to each subcontractor and sub-subcontractor as of the date the periodic estimate is filed. The person making payment for the awarding authority shall add the daily interest provided for herein to each payment for each day beyond the due date based on the date of receipt marked on the estimate.

A certificate of the architect to the effect that the contractor has fully or substantially completed the work shall, subject to the provisions of section thirty-nine J, be conclusive for the purposes of this section.

Summary
Massachusetts Prompt Payment Law
Article Name
Massachusetts Prompt Payment Law
Description
Summary of Massachusetts Prompt Payment requirements and laws for Massachusetts construction projects including free forms, FAQs, resources and more.
Author
Publisher Name
Levelset
Publisher Logo

Trusted by Thousands of Massachusetts Contractors Like You
For Help With Prompt Payment