"Schedule of Values" was attached to A101 form as "a Exhibit". The Schedule of Values is composed of 3 columns like Division#s-Work descriptions-Prices. For example, Division 1. General Conditions / 1. Job site clean up / $12,000.00 etc. The Schedule of Values shows total 18 Divisions, 55 Work Descripti...Read More...Read More
We are a contractor just finishing a commercial T&I and getting little to no response on payment of contract and change orders. Can we file a lien? ...Read More
I am an Electrician. The customer wanted to do the work. The work went from 6 feeder terminations to 6 terminations plus a new swimming pool. After the rough inspection the inspector wants a final on the swimming pool. This requires more work and trips for the job. When I let someone o their own...Read More...Read More
electrical subcontractor wants to change order us 22,200 on a 120,000 dollar contract but we cannot pass the cost on to the customer what do i do ...Read More
We are contracted with a door manufacture under a GC on a Navy installation, and our contract is with a subcontractor of the GC, and in our contract we have standby and delay times and have over $70k in change orders for being delayed and put on standby numerous times, and the company we...Read More...Read More
Can a homeowner say the contractor is responsible for additional work by saying the plans/blue prints under "General Notes"and are considered the contract if the contractor has a detailed scope that does not indicate other ?...Read More
HomeWise Builders is handling a remodeling job for the Willis Property owners. The Willis Property is now unwilling to pay milestone payments per the signed agreement stating that they want more things done and wanting documentation showing where monies have been applied, etc. They are contes...Read More...Read More
New home build in Maine. Financed through a construction loan. Home is almost finished and I just got a final invoice and it is significantly more than the original estimate (which is how much my loan is for). We have made some changes along the way but never signed any change orders. The cont...Read More...Read More
we are a subcontractor on a commercial Job we have a signed contract with the builder, however they requested us to perform extra work not included in our contract. they requested it via email and they approved the proposals we sent for the extra work. however they never created an official sig...Read More...Read More
Is it legal for a general contractor to default on agreed upon amendments to the original contract that were made with text proof, such as labor draw points and change orders for additional work to be done? ...Read More
I am having a disagreement about a proposed change order the GC has submitted to me (related to framing and drywalling 3 ft walls at the top of the stairs). My view, supported by the initial contract scope of work, is that this charge (about $5000) is unwarranted and the work was part of the original s...Read More...Read More
Backstory: In early 2020 we were approached about doing the Electrical portion for a New Construction Maintenance Facility County Project in Texas. The GC had already received Electrical Bids from other Contractors (so he said), and since we were doing another similar project for GC asked if we coul...Read More...Read More
hello , Say If was working for a builder in scheme contract where appointed on an hourly rate. is the builder able to holding a sum of money and then after a letter of demand claiming they have to carry out reworks. is the builder entitled to hold this sum and if there is reworks should the contractor ...Read More...Read More