Hello We signed a construction contract with a builder where we make payments on a turnkey project. The payments are now more than 50% of the contract sum but the actual work is about 30% done. Since we would like to exit the contract on the basis that the builder had done little on our ...Read More...Read More
The work related to the lien I am filing was done in Multiple Units throughout a Condo building...but technically the company I was doing the work for was working for the Home Owners Association, not the individual units. The HOA is providing Internet and TV to all the units in the building, and my ...Read More...Read More
Hi I hired a general contractor to redo my bathroom, and do a walk in shower. I requested a signed contract but he ignored my request, but furnished me with a detailed estimate. The floor of the tiled shower was not pitched right, neither was the shower threshold, and water was pooling. He redid it...Read More...Read More
We are currently building a multifamily building in Southern California that is 2 stories of wood frame over concrete foundation and podium. We have engaged with a General Contractor to subcontract the frame and concrete work at the project. For the sake of clarity lets call this GC as GC 1. GC...Read More...Read More
I am a subcontractor providing manufactured casework and architectural millwork for a new veterinary hospital in Wisconsin. In August, after the architect/GC approved shop drawings, the owner requested many scope changes. We submitted the cost impact of those changes as a change ...Read More...Read More
I am a subcontractor, I have submitted a mechanic lien to the property, the company own me more than 20k, and they called me offering 2k for remove the lien, mentioning me that I should take them, because the lean anyways would not work, since I applied for it after the 40 days I had started the w...Read More...Read More
We are a small stair company that works as a subcontractor on very large jobs in NYC. We do our best to submit the pencil reqs accurately and on time but if there is an issue or disagreement about payment it gets bounced out and cannot be re-submitted until the following month. It takes a lot of time ...Read More...Read More
I am a residential homeowner in Texas. My wife and I are contracted through a custom home builder to build our plan. We have continually paid him when draw requested initially after the job was completed, then during progress and lastly before work was even performed. The last several draws h...Read More...Read More
I was working a residential bathroom remodel, the contract was for 22627.01, including tile cost when selected and with change orders and additional work, verified through emails and verbal change orders the total became 27752.78, I was paid intermittently total of 13000. when it came to 1 more d...Read More...Read More
I’m a contractor that was hired to do a remodel. I completed most of the work then the owner saw that the project still needed more work so they requested a change order. Work was done they didn’t want to pay change orders. I have emails and text messages where he asked for the work to be done...Read More...Read More
I am a subcontractor, we have completed our scope of work per the contract signed. The GC held 10% as retention. I need to bill the retention, I have $23,000 in extra work that hasn't been billed because the GC has to issue a written change order first. The extra work has been approved by the...Read More...Read More
We are a subcontractor working for a GC on a puplic project .We filed a lien for non payment of change orders authorized(and work supervised) by the GC verbally .We notified the University that we where liening the GC. See response from GC's attorney....Read More
We have been working on collecting the balances for several invoices since we completed the project. Once the general contractor stopped answering our calls we reached out directly to the customer. They informed us that they would escalate our issue up the chain but we haven't received any res...Read More...Read More
Hi. I would like to learn that when preparing a change order should a sales tax be applied to the total amount of the line items in the change order? Or the total amount of the change order should be added to the original contract price which already included sales tax when signed....Read More