Menu

Change Orders Questions

All Status
Change Orders
All States
Hello We signed a construction contract with a builder where we make payments on a turnkey project. The payments are now more than 50% of the
contract sum but the actual work is about 30% done. Since we would like to exit the contract on the basis that the builder had done little on our ...Read More
...Read More
Anonymous Contractor
1 answerAdd commentAug 30, 2019
WashingtonChange OrdersConstruction Contract
The work related to the lien I am filing was done in Multiple Units throughout a Condo building...but technically the company I was doing the work for was
working for the Home Owners Association, not the individual units. The HOA is providing Internet and TV to all the units in the building, and my ...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentApr 16, 2020
FloridaChange OrdersCollectionsMechanics LienPayment Disputes
Hi I hired a general contractor to redo my bathroom, and do a walk in shower. I requested a signed contract but he ignored my request, but furnished me
with a detailed estimate. The floor of the tiled shower was not pitched right, neither was the shower threshold, and water was pooling. He redid it...Read More
...Read More
Anonymous Contractor
1 answerAdd commentAug 21, 2019
MassachusettsChange OrdersPayment Disputes
We are currently building a multifamily building in Southern California that is 2 stories of wood frame over concrete foundation and podium. We have
engaged with a General Contractor to subcontract the frame and concrete work at the project. For the sake of clarity lets call this GC as GC 1. GC...Read More
...Read More
Anonymous Contractor
3 answersAdd commentFeb 10, 2022
CaliforniaChange OrdersConstruction ContractDefectsLicenses
I am a subcontractor providing manufactured casework and architectural millwork for a new veterinary hospital in Wisconsin. In August, after the
architect/GC approved shop drawings, the owner requested many scope changes. We submitted the cost impact of those changes as a change ...Read More
...Read More
Anonymous Contractor
1 answerAdd commentJan 7, 2020
WisconsinChange OrdersMechanics LienPreliminary Notice
I am a subcontractor, I have submitted a mechanic lien to the property, the company own me more than 20k, and they called me offering 2k for remove the
lien, mentioning me that I should take them, because the lean anyways would not work, since I applied for it after the 40 days I had started the w...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 19, 2022
FloridaChange OrdersLien Priority
We are a small stair company that works as a subcontractor on very large jobs in NYC. We do our best to submit the pencil reqs accurately and on time but if
there is an issue or disagreement about payment it gets bounced out and cannot be re-submitted until the following month. It takes a lot of time ...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentJun 5, 2020
New YorkChange OrdersPay ApplicationsSlow Payment
I am a residential homeowner in Texas. My wife and I are contracted through a custom home builder to build our plan. We have continually paid him when
draw requested initially after the job was completed, then during progress and lastly before work was even performed. The last several draws h...Read More
...Read More
Anonymous Contractor
4 answersAdd commentApr 30, 2021
TexasBack ChargesChange OrdersLien ReleasesLien WaiversPayment Disputes
I was working a residential bathroom remodel, the contract was for 22627.01, including tile cost when selected and with change orders and additional work,
verified through emails and verbal change orders the total became 27752.78, I was paid intermittently total of 13000. when it came to 1 more d...Read More
...Read More
Anonymous Contractor
2 answersAdd commentMay 31, 2023
WashingtonBack ChargesChange OrdersConstruction ContractLawsuitMechanics LienNotice of Intent to LienPayment DisputesRight to Lien
I’m a contractor that was hired to do a remodel. I completed most of the work then the owner saw that the project still needed more work so they requested
a change order. Work was done they didn’t want to pay change orders. I have emails and text messages where he asked for the work to be done...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentJun 6, 2023
TexasChange Orders
I am a subcontractor, we have completed our scope of work per the contract signed. The GC held 10% as retention. I need to bill the retention, I have
$23,000 in extra work that hasn't been billed because the GC has to issue a written change order first. The extra work has been approved by the...Read More
...Read More
Brenda Pettibone
1 answerAdd commentMay 23, 2023
CaliforniaChange Orders
We are a subcontractor working for a GC on a puplic project .We filed a lien for non payment of change orders authorized(and work supervised) by the GC
verbally .We notified the University that we where liening the GC. See response from GC's attorney.
...Read More
Paul Fay
1 answerAdd commentDec 23, 2020
GeorgiaChange OrdersConstruction Contract
We have been working on collecting the balances for several invoices since we completed the project. Once the general contractor stopped answering our
calls we reached out directly to the customer. They informed us that they would escalate our issue up the chain but we haven't received any res...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentApr 11, 2023
TexasBankruptcyChange OrdersConstruction ContractLien DeadlinesLien WaiversMechanics LienPreliminary NoticeRetainageMaterials
Hi. I would like to learn that when preparing a change order should a sales tax be applied to the total amount of the line items in the change order? Or the
total amount of the change order should be added to the original contract price which already included sales tax when signed.
...Read More
Anonymous Contractor
2 answersAdd commentMay 26, 2022
WashingtonChange OrdersConstruction Contract
What happen if the GC has a lot of money extra in material cost without a change order for it?...Read More
Jorge Cunningham
1 answerAdd commentApr 2, 2023
GeorgiaChange OrdersMechanics LienMaterials