Is the AIA Change Order Contract in working days or calendar days?

1 reply

May 25, 2021

If you are working with AIA construction documents, then you are likely operating under the AIA A201: General Conditions of the Contract for Construction. Article 8 of these general conditions relates to time and §8.1.4 states that:

The term "day" as used in the Construction Documents shall mean calendar day unless otherwise specifically defined.