What is a three family residential building considered in New Jersey? Commercial or Residential? If we file a lien, it would be for non payment up to the finish (which still needs to be done since January of this year and scaffolding is still in place). The amount owed includes wall preparation and scratch c...Read More...Read More
After filing a lien the homeowner finally reached out because their investor stopped all construction. They want us to remove the lien and to get an agreement notarized of a payment plan because apparently they don't have the money. Would this be something I could actually enforce if I needed to? ...Read More
Hi, We are in the process of filing a lien for an unpaid balance on a construction contract. According to our construction contract, the owner of the hotel is Secaucus Lodging Assoc, 5701 Progress Rd., Indianapolis, IN 46241. Your research team found that HMGL LLC owns the actual property. We are i...Read More...Read More
Im a subcontractor that did work on Hunterdon County justice Center in NJ. We are 100% finished and there was no punch list and we have a warranty. The GC was shady and not doing his part so we thought it was in our best interest to lien the project. the bonding company is telling me it is taking lo...Read More...Read More
What happens if the mechanics lien expires in the year then does it get taken off their records. Or will it still get paid when they go to sell their home? Do we have to reapply every year?...Read More
Found some one on facebook and he claimed he is a licensed and insured contractor who agreed to do some flooring work. the work wasnt done right and made significant damages to my property. done a very sloppy job and threatening me they will put a lien against my property which i am going t...Read More...Read More
i have filed the notice to lien and unpaid balance. i see you sent to homeowner and bank. when will it be recorded? when or how do i then get docs to arbitration?...Read More
There are a few pending change orders on the project should we list the final contract amount including the change orders or without the change orders?...Read More
Hi there, We have a customer that we did commercial work for and they have now filed Chapter 11 Bankruptcy. They are telling us our lien for payment is no longer valid. From what I am reading, this is a reorganization and bills will be paid so we wish to leave our lien rights in place. ...Read More
We are building an office as a commercial property and our contractor has decided to add multiple costs to the final bill that were NOT approved change orders (cost to take out trash and accept deliveries). Thus, we have not agreed on the final price. He is completing the punch list and now threat...Read More...Read More
Hi, Im in NJ getting ready to file a Lien Claim. Questions: Am I obligated to send the customer a notice? After the Lein claim is filed, do I get assigned an arbitrator? How do I find out how much the arbitrator fees are?...Read More
For NJ, it says "Lien must be filed within 90 days of last providing labor or materials". Can I file a lien from the last day I provided labor to pick up stored materials? I worked on a project for a couple of months, my last day working there was 7/12/2019 At this point the project was on hold, then on S...Read More...Read More
we are a manufacturer and supplier of windows. if we custom-make windows for a project in New Jersey, and then our customer refuses acceptance of the windows upon delivery, are we allowed to lien the project? even if the materials were not provided? they were custom-made for the project. please advise....Read More