Per Fla. Stat. § 713.13(1)(d)2, if work is not commenced within 90 days of NOC being filed, the NOC is void. We got an NOC filed on our property on 6/12/20 by a window company. We are 83 days in from that date and no work has commenced. We are being told our windows are not due to arrive till la...Read More...Read More
A municipality is denying a recorded notice of commencement which had all the legally required information on it and forcing me to use an a certain notice of commencement of theirs....Read More
I signed an NOC with a CGC on 5/19/20. The CGC was extremely behind in their timeframe to complete the project and kept dragging their feet. In addition, they performed work outside the scope of their license (electrical and plumbing). Due to their prolonged delay, I took it upon myself to hire oth...Read More...Read More
We has sent out a notice on commencement for a customer and it has yet to be signed and filed with the city. Are we able to start this job without it being filed and signed with the city? Would we need to Revise this in any way?...Read More
I am a prime contractor finishing up a job and the owner does not want to pay. The notice of commencement on the job is expired, but would I still have lien rights if I furnished materials within 90 days?...Read More
I am an owner and by law it appears that I need to file a Notice of Commencement before I start construction of a house on a lot that I own. Due to recent hurricane damages, it is hard to find contractors in the area to do a job. Many of them state that they "currently do not have any resources to ta...Read More...Read More
Our company (contracting, not ownership) has been requested by an AHJ to hand in a certified NOC. The copy of the NOC we presented is notarized and recorded in the County. How do we get a certified copy, given that we are not the issuers of the document?...Read More
There was a new roof put on my mothers house, however, she has passed and is unable to sign the notice of commencement. Am I able to sign it as her heir while we are waiting for her estate to be closed out since the property hasn't been transferred yet?...Read More
we have a contractor who will be doing a project for us turnkey. This hiring their own subcontactors including paying their own subcontractors. The contractor will not be the qualifier. He is asking for us to add his name to the NOC in order to receive Notice to Owners and know who they mu...Read More...Read More
I was never issued a NTO from the GC roofer but was notified of a lien 4 months after the job started. I contested the lien and never received any response from the roofer in the 60 days period and still have not. All inspections on my new construction was done through a Private provider hired by my ...Read More...Read More