North Carolina Retainage Requirements
- Private Jobs
- Public Jobs
- Top Links
Retainage Limit
Not Regulated by State Law
Pay Period
Not Regulated by State Law
There's No Process to Recover
Not specified
Not Held In Escrow
In North Carolina, contractors and owners do not need to hold retainage funds in a separate escrow account.
5 Percent
Retainage not allowed on projects under $100,000. Otherwise, retainage is limited to 5% until 50% completion of the project.
60 Day Pay Period
Retainage must be released within 60 days of completion. The prime contractor must pay their subcontractors within 7 days of receipt of payment.
There is a Process to Recover
Yes, a request must be made by the direct contractor to the owner, and owner must receive certificate of substantial completion.
Retainage, also called “retention,” is an amount of money “held back” from a contractor ir subcontractor during the course of a construction project. In general, retainage serves two main purposes:
- To provide an incentive to the contractor or subcontractor to complete the project; &
- To give the owner some protection against problems like liens, contractual defaults, delays, and more.
In most states, laws exist to regulate how the parties use the retainage concept, mostly protecting some parties against abuse of the tool from others. The following are resources, legal information, and frequently asked questions about North Carolina’s retainage requirements. The North Carolina retainage statutes are reproduced below on this page.
North Carolina’s retainage limits and deadlines
North Carolina’s retainage statutes only apply to public works projects valued at over $100,000. Public works projects valued at less are not allowed to withhold retainage. On private projects within the state, retainage will be governed by the terms of the contract.
Retainage on such public projects is capped at 5% of each progress payment. Upon 50% completion, retainage must no longer be withheld unless the job progress is unsatisfactory.
The public entity is required to release retainage within 60 days of receipt of the pay request and a certificate of substantial completion, or beneficial use by the public entity is received.