Levelset visitors can also get a free Procore account.

Georgia Prompt Payment Guide and FAQs

Ready? Build Your Free Georgia
Prompt Payment Now

Get Your Lien Waiver Now
Georgia-Prompt-Payment FAQ

Georgia Prompt Payment Overview

Georgia Prompt Payment Requirements


  • Private Jobs
  • Public Jobs
  • Top Links
15
DAYS
Prime Contractors

For Prime (General) Contractors, payment is due within 15 days of request for payment.


10
DAYS
Subcontractors

For Subcontractors, payment is due within 10 days after payment is received above.


10
DAYS
Suppliers

For Suppliers, payment is due within 10 days after payment is received above.


1%
/ MONTH
Interest & Fees

Interest at 1% month; unless otherwise agreed. Attorney fees awarded to the prevailing party.

15
DAYS
Prime Contractors

For Prime (General) Contractors, payment due within 15 days of request for payment. Note, regulation doesn't apply to counties of less than 10,000 people or towns of less than 2,500 people.


10
DAYS
Subcontractors

For Subcontractors, payment due within 10 days after payment is received above.


10
DAYS
Suppliers

For Suppliers, payment due within 10 days after payment is received above.


1%
/ MONTH
Interest & Fees

Interest at 1% month; unless otherwise agreed. Attorneys fees awarded to prevailing party.

Prompt payment laws are a set of rules that regulate the acceptable amount of time in which payments must be made to contractors and subs. This is to ensure that everyone on a construction project is paid in a timely fashion. These statutes provide a framework for the timing of payments to ensure cash flow and working capital.

In Georgia, the same set of prompt payment rules apply to both public and private construction jobs. These statutes can be found in O.C.G.A. §§13-11-1 to 13-11-11. These timeframes apply to almost every construction project in Georgia, with two notable exceptions.

  • In the residential projects world, these regulations don’t apply to residential projects of 12 units or fewer
  • As for public projects, the prompt pay deadlines won’t apply in counties of less than 10,000 people, or towns with a population of less than 2,500.

Once a contractor has satisfied the conditions of their contract, they are entitled to payment. A proper invoice, submitted to the owner according to the contract payment terms, will start the clock on the payment deadline. Upon receipt, the owner will have 15 days to release payment to the prime contractor. Payments are considered received when the funds are actually received in the contractor or sub’s bank account. 

Now that the prime contractor has received project funds from the owner, they will then have 10 days to pass payment down to any subs or suppliers hired by them. This same 10-day period applies to all other payments down the chain. Payment is considered “paid” when the money is actually received in the contractor’s bank account.

The statutes provide a list of acceptable reasons to withhold payments. Any payments that are late or wrongfully withheld will be subject to interest accruing on the unpaid balance. The default rule is 1% per month, but the parties can agree ahead of time to a different rate of interest in their contract. In addition to interest penalties, in an action to enforce a prompt payment claim, the prevailing party will be awarded reasonable attorney fees. The payment deadlines and interest rates will act as the default rule, the parties can agree by contract to alter these if they so choose.

Georgia quick guide to prompt payment in construction

Georgia Prompt Payment Frequently Asked Questions

Georgia Prompt Payment Private Projects FAQs

Do I have to send a letter or file anything to qualify for Prompt Payment Penalties or Remedies in Georgia?

In Georgia, parties are entitled to pay subject to the timing requirements of the prompt pay act after performance of the work, and upon satisfactions of any conditions to payment set forth in the contract.

Attorneys’ fees would only be awarded upon a successful claim for withheld pay.

Can I include Prompt Payment Fees in my Georgia Mechanics Liens Claim or Bond Claim?

It’s unclear. Georgia law allows interest to be included on a lien claim in certain situations, but the interest allowed is pursuant to Georgia Code 7-4-2 and 7-4-16, which are not the prompt pay statutes.

If I am paid late according to Prompt Payment statutes, can I obtain interest or other Penalty Payments?

If payment is received late, and none of the valid reasons for late payment apply, the party to be paid is entitled to recover interest at the rate of 1% per month.

Are there reasons for which payment may be withheld past the general deadline?

Georgia allows payments to be withheld for the following reasons:

Unsatisfactory job progress,
Defective construction,
Disputed work,
Third party claims have been filed or reasonable evidence a claim will be filed,
Failure of the contractor or subcontractor to make timely payments for labor, equipment and materials,
Damage caused by the contractor or subcontractor, or
Reasonable evidence that the contract cannot be completed for the unpaid contract balance.

What is the best practice for making a demand to a non-paying party to get Prompt Payment Fees?

Sending a notice of intent to lien and prompt payment demand is generally the best method for encouraging parties to make payment.

Georgia Prompt Payment Public Projects FAQs

Do I have to send a letter or file anything to qualify for Prompt Payment Penalties or Remedies in Georgia?

In Georgia, parties are entitled to pay subject to the timing requirements of the prompt pay act after performance of the work, and upon satisfactions of any conditions to payment set forth in the contract.

Attorneys’ fees would only be awarded upon a successful claim for withheld pay.

Can I include Prompt Payment Fees in my Georgia Mechanics Liens Claim or Bond Claim?

It is unclear. Georgia law allows interest to be included on a lien claim in certain situations, but the interest allowed is pursuant to Georgia Code 7-4-2 and 7-4-16, which are not the prompt pay statutes.

If I am paid late according to Prompt Payment statutes, can I obtain interest or other Penalty Payments?

If payment is received late, and none of the valid reasons for late payment apply, the party to be paid is entitled to recover interest at the rate of 1% per month.

Are there reasons for which payment may be withheld past the general deadline?

Georgia allows payments to be withheld for the following reasons:

  1. Unsatisfactory job progress,
  2. Defective construction,
  3. Disputed work,
  4. Third party claims have been filed or reasonable evidence a claim will be filed,
  5. Failure of the contractor or subcontractor to make timely payments for labor, equipment and materials,
  6. Damage caused by the contractor or subcontractor,
  7. Reasonable evidence that the contract cannot be completed for the unpaid contract balance.

Need More Help with Georgia Prompt Payment? We're Here.

Georgia Prompt Payment
Recent Questions & Answers

Partial project payment when cut short?

Hi. If you are a contractor who is late fulfilling a contract and you are asked to stop mid-project due to this, are you due...

Can I add damages for ruining my reputation on social media??

I have a customer that slander my business on social media site where I do 100 of my advertising. It has hurt me financially. And...

Does the Ga prompt pay act apply if the construction contract is governed by a different state?

The contract was governed by Mississippi law however, the construction was done in Georgia.

How to file a lien in Georgia

Need to file a Georgia mechanics lien? File your mechanics lien with Levelset, the lien experts quickly and easily. Or you can follow the 3 steps below to file a lien yourself with Levelset's free information.

Want to Learn More about How Georgia Contractors Pay?
Progress Residential
Rating 5.0
FirstKey Homes
Rating 5.0
Zillow Group Inc.
Rating 5.0
Dick's Sporting Goods
Rating 5.0
See other Lists of Contractors and How to Best Work With Them

Georgia Prompt Payment Statutes

Getting informed about prompt payment laws is important. An examination of Georgia’s prompt payment laws, the rules and regulations related to payment timing, is important to know your rights and responsibilities as a party on a construction project. Georgia’s specific laws can be found in: Ga. Code §§ 13-11-1 to 13-11-11, and are reproduced below.

Prompt Payment Statute on Private Projects

13-11-1: Title

This chapter shall be known and may be cited as the ‘Georgia Prompt Pay Act.’

13-11-2: Definitions

As used in this chapter, the term:

(1) “Contractor” means a person who contracts with an owner to improve real property, to perform construction services, or to perform construction management services for an owner.

(2) “Improve” means to build, effect, alter, repair, or demolish any improvement upon, connected with, or on or beneath the surface of any real property or to excavate, clear, grade, fill, or landscape any real property or to construct driveways and private roadways or to furnish materials, including trees and shrubbery, for any of such purposes or to perform any labor upon such improvements.

(3) “Improvement” means all or any part of any building, structure, erection, alteration, demolition, excavation, clearing, grading, filling, or landscaping, including trees and shrubbery, driveways, and roadways, on real property.

(4) “Owner” means a person who has an interest in the real property improved and for whom an improvement is made and who ordered the improvement to be made. “Owner” includes private persons and entities and state, local, or municipal government agencies, instrumentalities, or entities; provided, however, that the provisions of this chapter shall not apply when the owner is a county having a population of less than 10,000 according to the United States decennial census of 1990 or any such future census or when the owner is a municipality having a population of less than 2,500 according to the United States decennial census of 1990 or any such future census.

(5) “Owner’s representative” means the architect or engineer in charge of the project for the owner or such other contract representative or officer as designated in the contract documents as the party representing the owner’s interest regarding administration and oversight of the project.

(6) “Real property” means the real estate that is improved, including lands, leaseholds, tenements, and improvements placed on the real property.

(7) “Receipt” means actual receipt of cash or funds in the contractor’s or subcontractor’s bank account.

(8) “Subcontractor” means any person who has contracted to furnish labor or materials to, or has performed labor or supplied materials for, a contractor or another subcontractor in connection with a contract to improve real property. For purposes of this chapter, the term “subcontractor” shall also include materialmen as defined in Code Section 44-14-360.

13-11-3: Contractors' and Subcontractors' Entitlement to Pay

Performance by a contractor or subcontractor in accordance with the provisions of his or her contract and the satisfaction of the conditions of his or her contract precedent to payment entitles such person to payment from the party with whom he or she contracts.

13-11-4: Time Limits for Payments to Contractors and Subcontractors

(a) When a contractor has performed in accordance with the provisions of a contract, the owner shall pay the contractor within 15 days of receipt by the owner or the owner’s representative of any payment request based upon work completed or service provided under the contract.

(b) When a subcontractor has performed in accordance with the provisions of its subcontract and the subcontract conditions precedent to payment have been satisfied, the contractor shall pay to that subcontractor and each subcontractor shall pay to its subcontractor, within ten days of receipt by the contractor or subcontractor of each periodic or final payment, the full amount received for such subcontractor’s work and materials based on work completed or service provided under the subcontract, provided that the subcontractor has provided or provides such satisfactory reasonable assurances of continued performance and financial responsibility to complete his or her work as the contractor in his or her reasonable discretion may require, including but not limited to a payment and performance bond.

13.11.5: Grounds for Withholding Payments

(a) Nothing in this chapter shall prevent the owner from withholding payment to its contractor because of the following: unsatisfactory job progress; defective construction which has not been remedied; disputed work; third-party claims filed or reasonable evidence that a claim will be filed; failure of the contractor or its subcontractor to make timely payments for labor, equipment, and materials; damage caused by the contractor to the owner, other contractors, or subcontractors; or reasonable evidence that the contract cannot be completed for the unpaid balance of the contract sum. In addition to the other bases for withholding set forth in this subsection, the owner may withhold a reasonable amount for retainage, provided that the retainage withheld by the owner shall not exceed the retainage percentage set forth in the contract between the contractor and the owner.

(b) Nothing in this chapter shall prevent the contractor or a subcontractor from withholding payment to a subcontractor for: unsatisfactory job progress; defective construction which has not been remedied; disputed work; third-party claims filed or reasonable evidence that a claim will be filed; failure of the subcontractor to make timely payments for labor, equipment, and materials; damage caused by the subcontractor to the owner, the contractor, or contractors or subcontractors; or reasonable evidence that the subcontract cannot be completed for the unpaid balance of the subcontract sum. In addition to the other bases for withholding set forth in this subsection, the contractor or the subcontractor, as the case may be, may withhold a reasonable amount for retainage, provided that the retainage withheld shall not exceed the percentage retained from the contractor by the owner on account of the subcontractor’s work.

13.11.6: Conditions Authorizing Payments to Subcontractors

The contractor shall, within ten days from the contractor’s receipt of retainage from the owner, pass through payments to subcontractors and shall reduce each subcontractor’s retainage in the same manner as the contractor’s retainage is reduced by the owner, provided that the value of the subcontractor’s work complete and in place equals 50 percent of his or her subcontract value, including approved change orders and other additions to the subcontract value and, provided, further, that the work of the subcontractor is proceeding satisfactorily and, provided, further, that the subcontractor has provided or provides such satisfactory reasonable assurances of continued performance and financial responsibility to complete his or her work as the contractor in his or her reasonable discretion may require, including but not limited to a payment and performance bond.

13-11-7:Interest on Late Payments

(a) Except as provided in Code Section 13-11-5, if a periodic or final payment to a contractor is delayed by more than 15 days or if a periodic or final payment to a subcontractor is delayed more than ten days after receipt of periodic or final payment by the contractor or subcontractor, the owner, contractor, or subcontractor, as the case may be, shall pay his or her contractor or subcontractor interest, beginning on the day following the due date, at the rate of 1 percent per month or a pro rata fraction thereof on the unpaid balance as may be due. However, no interest is due unless the person being charged interest has been notified of the provision of this Code section at the time the request for payment is made. Acceptance of progress payments or final payment shall release all claims for interest on said payments.

(b) Nothing in this chapter shall prohibit owners, contractors, and subcontractors from agreeing by contract to rates of interest, payment periods, and contract and subcontract terms different from those stipulated in this Code section, and in this event, these contractual provisions shall control. In case of a willful breach of the contract provisions as to the time of payment, the interest rate specified in this Code section shall apply.

13-11-8: Attorney's Fees

In any action to enforce a claim under this chapter, the prevailing party is entitled to recover a reasonable fee for the services of its attorney including but not limited to trial and appeal and arbitration, in an amount to be determined by the court or the arbitrators, as the case may be.

13-11-9: Nonexclusive Remedies

Neither the right to recover interest on a payment nor the right to recover attorneys’ fees under this chapter are exclusive remedies. This chapter does not modify the remedies available to any person under the terms of a contract or by another statute.

13-11-10: Improvements Excepted from Chapter

The provisions of this chapter do not apply to improvements to real property intended for residential purposes which consist of 12 or fewer residential units.

13-11-11: Applicability of Chapter

The provisions of this chapter do not apply to contracts or subcontracts entered into prior to January 1, 1995.

Prompt Payment Statute on Public Projects

13-11-1: Title

This chapter shall be known and may be cited as the ‘Georgia Prompt Pay Act.’

 

13-11-2: Definitions

 As used in this chapter, the term:

(1) “Contractor” means a person who contracts with an owner to improve real property, to perform construction services, or to perform construction management services for an owner.

(2) “Improve” means to build, effect, alter, repair, or demolish any improvement upon, connected with, or on or beneath the surface of any real property or to excavate, clear, grade, fill, or landscape any real property or to construct driveways and private roadways or to furnish materials, including trees and shrubbery, for any of such purposes or to perform any labor upon such improvements.

(3) “Improvement” means all or any part of any building, structure, erection, alteration, demolition, excavation, clearing, grading, filling, or landscaping, including trees and shrubbery, driveways, and roadways, on real property.

(4) “Owner” means a person who has an interest in the real property improved and for whom an improvement is made and who ordered the improvement to be made. “Owner” includes private persons and entities and state, local, or municipal government agencies, instrumentalities, or entities; provided, however, that the provisions of this chapter shall not apply when the owner is a county having a population of less than 10,000 according to the United States decennial census of 1990 or any such future census or when the owner is a municipality having a population of less than 2,500 according to the United States decennial census of 1990 or any such future census.

(5) “Owner’s representative” means the architect or engineer in charge of the project for the owner or such other contract representative or officer as designated in the contract documents as the party representing the owner’s interest regarding administration and oversight of the project.

(6) “Real property” means the real estate that is improved, including lands, leaseholds, tenements, and improvements placed on the real property.

(7) “Receipt” means actual receipt of cash or funds in the contractor’s or subcontractor’s bank account.

(8) “Subcontractor” means any person who has contracted to furnish labor or materials to, or has performed labor or supplied materials for, a contractor or another subcontractor in connection with a contract to improve real property. For purposes of this chapter, the term “subcontractor” shall also include materialmen as defined in Code Section 44-14-360.

13-11-3: Contractors' and Subcontractors' Entitlement to Pay

Performance by a contractor or subcontractor in accordance with the provisions of his or her contract and the satisfaction of the conditions of his or her contract precedent to payment entitles such person to payment from the party with whom he or she contracts.

13-11-4: Time Limits for Payments to Contractors and Subcontractors

(a) When a contractor has performed in accordance with the provisions of a contract, the owner shall pay the contractor within 15 days of receipt by the owner or the owner’s representative of any payment request based upon work completed or service provided under the contract.

(b) When a subcontractor has performed in accordance with the provisions of its subcontract and the subcontract conditions precedent to payment have been satisfied, the contractor shall pay to that subcontractor and each subcontractor shall pay to its subcontractor, within ten days of receipt by the contractor or subcontractor of each periodic or final payment, the full amount received for such subcontractor’s work and materials based on work completed or service provided under the subcontract, provided that the subcontractor has provided or provides such satisfactory reasonable assurances of continued performance and financial responsibility to complete his or her work as the contractor in his or her reasonable discretion may require, including but not limited to a payment and performance bond.

13.11.5: Grounds for Withholding Payments

(a) Nothing in this chapter shall prevent the owner from withholding payment to its contractor because of the following: unsatisfactory job progress; defective construction which has not been remedied; disputed work; third-party claims filed or reasonable evidence that a claim will be filed; failure of the contractor or its subcontractor to make timely payments for labor, equipment, and materials; damage caused by the contractor to the owner, other contractors, or subcontractors; or reasonable evidence that the contract cannot be completed for the unpaid balance of the contract sum. In addition to the other bases for withholding set forth in this subsection, the owner may withhold a reasonable amount for retainage, provided that the retainage withheld by the owner shall not exceed the retainage percentage set forth in the contract between the contractor and the owner.

(b) Nothing in this chapter shall prevent the contractor or a subcontractor from withholding payment to a subcontractor for: unsatisfactory job progress; defective construction which has not been remedied; disputed work; third-party claims filed or reasonable evidence that a claim will be filed; failure of the subcontractor to make timely payments for labor, equipment, and materials; damage caused by the subcontractor to the owner, the contractor, or contractors or subcontractors; or reasonable evidence that the subcontract cannot be completed for the unpaid balance of the subcontract sum. In addition to the other bases for withholding set forth in this subsection, the contractor or the subcontractor, as the case may be, may withhold a reasonable amount for retainage, provided that the retainage withheld shall not exceed the percentage retained from the contractor by the owner on account of the subcontractor’s work.

13.11.6: Conditions Authorizing Payments to Subcontractors

The contractor shall, within ten days from the contractor’s receipt of retainage from the owner, pass through payments to subcontractors and shall reduce each subcontractor’s retainage in the same manner as the contractor’s retainage is reduced by the owner, provided that the value of the subcontractor’s work complete and in place equals 50 percent of his or her subcontract value, including approved change orders and other additions to the subcontract value and, provided, further, that the work of the subcontractor is proceeding satisfactorily and, provided, further, that the subcontractor has provided or provides such satisfactory reasonable assurances of continued performance and financial responsibility to complete his or her work as the contractor in his or her reasonable discretion may require, including but not limited to a payment and performance bond.

13-11-7:Interest on Late Payments

(a) Except as provided in Code Section 13-11-5, if a periodic or final payment to a contractor is delayed by more than 15 days or if a periodic or final payment to a subcontractor is delayed more than ten days after receipt of periodic or final payment by the contractor or subcontractor, the owner, contractor, or subcontractor, as the case may be, shall pay his or her contractor or subcontractor interest, beginning on the day following the due date, at the rate of 1 percent per month or a pro rata fraction thereof on the unpaid balance as may be due. However, no interest is due unless the person being charged interest has been notified of the provision of this Code section at the time the request for payment is made. Acceptance of progress payments or final payment shall release all claims for interest on said payments.

(b) Nothing in this chapter shall prohibit owners, contractors, and subcontractors from agreeing by contract to rates of interest, payment periods, and contract and subcontract terms different from those stipulated in this Code section, and in this event, these contractual provisions shall control. In case of a willful breach of the contract provisions as to the time of payment, the interest rate specified in this Code section shall apply.

13-11-8: Attorney's Fees

In any action to enforce a claim under this chapter, the prevailing party is entitled to recover a reasonable fee for the services of its attorney including but not limited to trial and appeal and arbitration, in an amount to be determined by the court or the arbitrators, as the case may be.

13-11-9: Nonexclusive Remedies

Neither the right to recover interest on a payment nor the right to recover attorneys’ fees under this chapter are exclusive remedies. This chapter does not modify the remedies available to any person under the terms of a contract or by another statute.

13-11-10: Improvements Excepted from Chapter

The provisions of this chapter do not apply to improvements to real property intended for residential purposes which consist of 12 or fewer residential units.

13-11-11: Applicability of Chapter

The provisions of this chapter do not apply to contracts or subcontracts entered into prior to January 1, 1995.

Trusted by Thousands of Georgia Contractors Like You
For Help With Prompt Payment