Private projects
General contractors are not required to send notice on private projects.
General contractors are not required to send notice on private projects.
General contractors are not required to send notice on public projects.
Since GCs will not make a claim against their own bond or their own money for non-payment, they do not have bond claim or lien on fund rights, and have no preliminary notice requirement.
Subcontractors and suppliers are required to send notice on private projects.
Notice of furnishing due within 21 days of first furnishing labor or materials - or 21 days from the filing of a notice of commencement.
Subcontractors and suppliers must send notice on public projects.
All claimants without a direct contract with the general contractor (excluding wage laborers), who will provide more than $30,000 of work or material must send a preliminary notice in order to preserve their bond claim rights and lien rights.
All parties who did not contract directly with the property owner (with the exception of laborers) must send a Notice of Furnishing. If the property owner does not record a Notice of Commencement, or records a defective Notice of Commencement, a preliminary notice is not required – but it is still generally considered best practice to give notice anyway.
Additionally, Ohio does not require preliminary notices for home purchase contracts, but again, it’s a good idea to give notice even if not required.
A Notice of Furnishing must be served on the property owner, part owner, or lessee (or their designee) as provided in the Notice of Commencement. If no designee is given, or the designee has died or otherwise ceased to exist, the notice must be provided to the owner, part owner, or lessee.
Also, parties who didn’t contract directly with the general contractor must provide the notice to the general contractor as well.
Lastly, the statutes state that if a lender is named in the NOC, the notice of furnishing may be served on the lender as well; but this is purely at the discretion of the lien claimant.
Generally, the deadline to serve an Ohio Notice of Furnishing is within 21 days after first furnishing labor and/or materials to the project. Note the emphasis on after, an Ohio Notice of Furnishing cannot be given prior to the first date of furnishing.
• See: Send Ohio Notice of Furnishing Fast… Not Early
However, if the Notice of Commencement is filed late, then the Notice of Furnishing must be served within 21 days of when the NOC was filed. A potential lien claimant is not required to give preliminary notice prior to the filing of the NOC. If the Notice of Commencement is never filed, then preliminary notice is not necessary.
• See the answer to this OH supplier’s question for a full breakdown of how Ohio’s Notice of Furnishing requirements and how they interact with the Notice of Commencement requirements: As a material supplier, is the Preliminary Notice to a General Contractor mandatory if they are not known yet?
Finally, if the property owner, or any other party with an interest in the property or contractor requests it, the lien claimant must provide a written statement of the work and/or material provided and the amount unpaid within 10 days of the request. Failure to do so may extinguish lien rights.
The notice must be in substantially the same form as provided under ORC §1311.05(B) and contain the following information:
• Name & address of the owner/part owner/lessee/designee provided in the Notice of Commencement
• General contractor’s name & address
• Description of the property “sufficient to reasonably identify the property”
• Date of first furnishing labor and/or materials
• Notifying party’s name & address
• Following warning statement:
WARNING TO OWNER: THIS NOTICE IS REQUIRED BY THE OHIO MECHANICS’ LIEN LAW. IF YOU HAVE ANY QUESTIONS ABOUT YOUR RIGHTS AND DUTIES UNDER THESE STATUTES YOU SHOULD SEEK LEGAL ASSISTANCE TO PROTECT YOU FROM THE POSSIBILITY OF PAYING TWICE FOR THE IMPROVEMENTS TO YOU PROPERTY.
→ Download a free Ohio private Notice of Furnishing form here
The preliminary notice must either be personally served by the county sheriff (or by other means as provided by Ohio law) or by certified mail, registered mail, overnight delivery, or hand delivery, provided that a written receipt is obtained.
• See more at How To Send Notice to Owners – Standard Certified Mail, or Certified Mail with Return Receipt Requested?
Notice by personal service is complete when actually served. If sent by certified mail, the preliminary notice is considered complete on the date of mailing. If service on the owner is attempted at the address listed on the notice of commencement and the service is returned or refused, the service is considered complete on the first date of the first attempt.
However, while service may be considered complete on the date of mailing, the actual delivery of the mail piece is the burden of the sending party. An Ohio Court of Appeals case specifically stated that “[t]he statute clearly contemplates that mailing a document by certified mail will provide written evidence of receipt. Thus, we cannot conclude that requiring Appellant to provide written evidence of receipt is contrary to a plain reading of the statute, when actual receipt is disputed by Appellees.”
A Notice of Furnishing served outside the 21-day deadline can still effectively secure lien rights. However, the amount of protection will be limited to the value of labor and/or materials furnished in the 21 days preceding the service of notice, and everything thereafter.
Ohio provides two avenues for recovery for non-payment on public projects. A claim against the payment bond, and a lien on contract funds. These notices can be combined into one form.
Bond Claims
All claimants without a direct contract with the general contractor (excluding wage laborers) must send a preliminary notice in order to preserve their lien rights, provided that the labor and/or materials furnished were more than $30,000.
Parties on highway construction projects aren’t required to provide notice, but it’s a good idea to send one anyways. Particularly if supplying more than $30,000 of labor and/or materials.
Liens on Contract Funds
All claimants without a direct contract with the general contractor (excluding wage laborers) must send a preliminary notice in order to preserve their lien rights.
Bond Claims
Notice must be served on the general contractor who posted the bond.
Liens on Contract Funds
Preliminary notice must be sent to the general contractor as well as the public authority who commissioned the project. The copy sent to the public entity must include a sworn statement as to the date when notice was given to the general contractor
Both preliminary notices must be served within 21 days after first furnishing labor and/or materials to the project. Sending notice before providing labor or materials will not be valid.
Also, when it comes to preliminary notices for liens on contract funds, there is no specific deadline to provide a copy of the notice to the public entity. However, it’s best practice to send the notice as soon as possible after delivering notice to the general contractor.
The Ohio public Notice of Furnishing must be in substantially the same form as provided under ORC §1311.261(B) and contain the following information:
• General contractor’s name & address
• Description of the labor and/or materials to be furnished
• Description of the property
• Date of first furnishing
• Notifying party’s name & address
→ Download a free Ohio public Notice of Furnishing form here
The preliminary notice must either be personally served by the county sheriff (or by other means as provided by Ohio law) or by certified mail, registered mail, overnight delivery, or hand delivery, provided that a written receipt is obtained.
If given by certified mail, the notice of furnishing is considered served on the date the notice is deposited in the mail. However, actual receipt is still required. If personally served, then upon receipt.
If the preliminary notice is sent after the 21-day deadline, the notice will still be effective to secure payment bond claim and lien on contract funds claims, however, it will only cover labor and/or materials provided in the 21 days preceding service of the notice, and everything furnished thereafter. If the notice is not given at all, the claimant’s rights to make a bond claim are extinguished.
Sending a Notice of Right to Lien in Oregon is a relatively common practice. This notice is required by law to be sent by subcontractors and suppliers on most residential projects to secure the right to file a lien; if and when a payment problem that arises on the project.
I agree that seeing the term "lien" on any legal document can be unsettling. But keep in mind that a preliminary notice is not any indication of any payment issues or perceived financial problems. Consider it a proactive means to ensure that the company is going to get paid on the project. Some companies generate them for every project, others send them only on projects over a predetermined dollar amount, and some don't send them at all. But as a property owner, there is no cause for concern when a preliminary notice is received.
In fact, besides securing the ability to file a lien if unpaid, it also offers valuable information and points of contact to property owners and general contractors about who is involved on the project, and what they are providing. That way both the owner and GC can ensure that they are getting paid, and requesting a lien waiver when they're paid to ensure that no claims are filed against the property.
Here are some other resources that may help:
Assuming this is a residential project, contractors hired directly by the property owner will need to provide an Information Notice to Owner if the project exceeds $2,000. That notice is given at the time the contract is signed. If the notice is not given, mechanics lien rights won't be available. For commercial jobs, contractors hired directly by the owner won't need to send preliminary notices in order to preserve the right to file a mechanics lien. You can learn the finer details of these notice requirements here: Oregon Preliminary Notice FAQs.
Still, even if mechanics lien rights aren't on the table, other options could lead to payment - like sending invoice reminders or demand letters. Further actions can be useful, too - like the ones discussed here: Can’t File a Lien? Here Are Some Other Options For Recovery.
Ohio is a state in which preliminary notice (also called Notice of Furnshing) requirements for sub-tier parties are specifically and directly tied to the actions of the parties higher up on the payment chain. Additionally, Ohio is one of the rare states that specifically limits the applicability of preliminary notices to projects other than residential projects. Ohio specifically does not require preliminary notices for projects on single or double family residences and condominiums, but, like always, it is generally advisable to give notice anyway.
Other than the residential projects mentioned above, Ohio is one of the few states that requires a Notice of Commencement to be filed. The Notice of Commencement must be filed by the owner or other party authorizing work on the property, and a copy must be posted in a conspicuous place at the job site. Further, a copy must be sent to the general contractor on the project. If the Notice of Commencement is not filed, if it is filed late, if the notice is deficient, or if a copy is requested but not given to a potential claimant, the time to file a lien may be extended and the otherwise required preliminary notice requirements may not apply.
If the Notice of Commencement is properly filed, as required, all project participants not directly in contact with the property owner (excluding wage laborers), must file a Notice of Furnishing. The notice must be sent via certified mail with return receipt requested within 21 days from the date the project participants first provided service or materials. If the property owner has not filed a Notice of Commencement, then preliminary notice is not specifically required, although it is still best practice to provide notice.
Ohio is interesting in that sending the Notice of Furnishing too soon renders it ineffective – even if the notice was received after labor or material was furnished. Unlike states like California, in which notice can never be sent too early and which specifically allow preliminary notice to be sent at any time, Ohio strictly requires that Notices of Furnishing must be sent after first furnishing labor or materials to the project.
The statute setting forth the Ohio’s Notice of Furnishing requirement (1311.05) states that a party required to give such notice: “shall serve a notice of furnishing . . . at any time after the recording of the notice of commencement or amended notice but within twenty-one days after performing the first labor or work or furnishing the first materials.”
The Ohio Twelfth Appellate District Court of Appeals interpreted this clause to specifically require that notice not be given until after the first furnishing of labor or materials. Since service is considered accomplished upon mailing, this means that the notice should not be put into the mail until the project participant supplying the notice has begun work.
Additionally, a property owner or other interested party may request a written notice of labor or materials provided. If requested, a project participant must provide this statement within 10 days in order to preserve lien rights.
First, read the guide for preliminary notices (notices of furnishing) in Ohio. There, you can find all the state requirements, including what information you need to include, the rules for delivery, and the deadline for completion.
The next step is to download the blank Ohio preliminary notice form. Ohio is strict regarding which information must be included and how the document should be formatted. Our free forms were created by construction attorneys to meet those state requirements.
Make sure you get everything right when filling out your Ohio preliminary notice! Making the slightest mistake could eliminate your right to file a mechanics lien down the line. Include all the required information and make sure it’s 100% accurate.
The last step is to deliver your Ohio preliminary notice. You have several options. You can send it via the sheriff’s office, registered mail, or certified mail, return receipt requested.
Select Preliminary Notice document.
Provide basic job information.
Levelset sends the document for you. Postage included!