Notice of project commencement due 15 days after commencement. This provides additional protections to the general contractor against potential lien claimants.
South Carolina Mechanics Lien Guide and FAQs
Quicklinks
“Levelset takes something that is pretty complex and makes it easy.”
Ready to file a lien in South Carolina?
Not sure? Calculate your deadline for free.
South Carolina lien law deadlines for:
Lien must be filed w/in 90 days after last labor or materials furnished.
In South Carolina, an action to enforce a mechanics lien must be initiated within 6 months from the claimant's last furnishing of labor and/or materials to the project. A notice of lis pendens must also be filed in South Carolina.
Note that, due to some case law, it may be best practice to initiate an action to enforce a lien before the earlier of either 6 months after the lien was filed or 6 months after the date of last furnishing, just to be safe.
If contracted with a party other than the property owner, potential claimant must serve the owner and GC with a Notice of Furnishing Labor or Materials.
Lien must be filed w/in 90 days after last labor or materials furnished.
In South Carolina, an action to enforce a mechanics lien must be initiated within 6 months from the claimant's last furnishing of labor and/or materials to the project. A notice of lis pendens must also be filed in South Carolina.
Note that, due to some case law, it may be best practice to initiate an action to enforce a lien before the earlier of either 6 months after the lien was filed or 6 months after the date of last furnishing, just to be safe.
If contracted with a party other than the property owner, potential claimant must serve the owner and GC with a Notice of Furnishing Labor or Materials.
Lien must be filed w/in 90 days after last labor or materials furnished.
In South Carolina, an action to enforce a mechanics lien must be initiated within 6 months from the claimant's last furnishing of labor and/or materials to the project.A notice of lis pendens must also be filed in South Carolina.
Note that, due to some case law, it may be best practice to initiate an action to enforce a lien before the earlier of either 6 months after the lien was filed or 6 months after the date of last furnishing, just to be safe.
South Carolina Mechanics Lien FAQs
Who can file a South Carolina mechanics lien?
In South Carolina, parties who furnish labor and/or materials used in the “erection, alteration, or repair of a building or structure” or “for the improvement of real property” are entitled to mechanics lien protection. Mechanics lien protection in South Carolina is fairly broad. Contractors, subcontractors, laborers, design professionals (architects and engineers), surveyors, and equipment lessors are all entitled to mechanics lien rights.
Further, South Carolina allows security guards at a site of real estate improvement to claim mechanics lien protection as a laborer. Also, parties who provide landscape services (as defined by statute) are entitled to a mechanics lien when the service exceeds $5000, and was pursuant to a written contract with the owner of the property.
Note that a contractor must be licensed or registered to file a mechanics lien if he is required by law to be licensed or registered to do the work he performs.
Is a written contract required to file a mechanics lien in South Carolina?
No, there is no specific requirement that construction contracts be in writing in order to be able to file a South Carolina mechanics lien. However, it’s always best practice to get your agreements in writing to avoid any confusion or complications.
• See: Can You File a Mechanics Lien Without a Written Contract?
Can an unlicensed contractor file a South Carolina mechanics lien?
No, not if you are required to be licensed by law. South Carolina requires that a contractor be licensed in order to file a mechanics lien if the contractor performs work for which he is required by law to be licensed or registered. Also, his license or registration number must be provided on the claim of lien itself.
• Learn how to get licensed: South Carolina Contractor Licensing Guide
When is the deadline to file a South Carolina mechanics lien?
In South Carolina, a claim of lien must be filed no later than 90 days after the last day on which the claimant furnished labor or materials to the project. Unlike many other states, South Carolina generally allows “call-back” or warranty work to extend the time period in which a lien may be filed. That is, if a party returns to do work pursuant to a warranty, or just to fix something, the 90-day period is generally counted starting from the date of that work. Note that some counties in South Carolina require a proof of service that the lien was served on the owner be provided prior to filing.
What information should be included in a South Carolina mechanics lien?
A South Carolina Notice of Mechanics Lien is governed by S.C. Code §29-5-90, and must contain all of the following information:
• Claimant’s information;
• Amount claimed, along with a verified statement of account;
• Property description;
• Owner’s information; &
• Contractor license number or registration number (if applicable).
→ Download free South Carolina Notice of Mechanics Lien forms here:
• South Carolina Mechanics Lien (Direct Contractors) form
• South Carolina Mechanics Lien (No Contract w/Owner) form
Does a South Carolina mechanics lien need to include a legal property description?
No. In South Carolina, a mechanics lien only requires a “description of the property intended to be covered by the lien sufficiently accurate for identification.” A full legal property description isn’t necessarily required.
Can attorney fees, collection costs, or other amounts be included in the lien amount?
Attorney’s fees and collection costs are not allowable in the lien amount itself, but the award of costs and attorney’s fees is mandatory to the prevailing party in an action on the lien (to either lien claimant or property owner, whoever prevails). The amount of costs and reasonable attorney’s fees may not exceed the amount of the lien.
Does a South Carolina mechanics lien need to be notarized?
Yes. South Carolina law requires that a mechanics lien must be notarized to be valid and accepted for recording.
• Learn more about notarizing construction payment documents
• Options for notarizing mechanics liens remotely
Where do I file and record a South Carolina mechanics lien?
South Carolina mechanic lien claims are documents recorded with the county clerk or court or register of deeds. For your mechanic’s lien to be valid, you must record it in the county where the job is physically located.
South Carolina counties each have their own unique rules and requirements. To help you, we’ve assembled all of the offices in South Carolina that record mechanics liens. These pages will walk you through the county’s specific formatting requirements, deadlines, and fees.
• Be prepared: Essential Questions to Ask The County Recorder Before Filing a Lien
How do I actually file a South Carolina mechanics lien?
There are a lot of questions answered on this page about who can file a South Carolina mechanics lien, when it must be filed, what types of rules apply, and more. But you may be wondering something much more practical: how do I actually get my mechanics lien recorded and filed in South Carolina?
• For this, you may want to consult our Step-by-Step Guide on How to File a South Carolina Mechanics Lien
Do I need to send notice that the mechanics lien was recorded in South Carolina?
Yes. Some counties in South Carolina require that a proof of service of the lien on the owner be provided prior to the recording of the lien. However, in any event, the property owner must be served with a copy of the lien within the same 90-day period in which the lien must be filed.
If the property owner cannot be found, the lien may be served on the person in possession of the property – and an affidavit of the sheriff stating that the owner could not be found must be filed. Note that service may not be accomplished by mail, or even by a private process server. South Carolina requires that the lien be served on the property owner (or person in possession, if the property owner cannot be found) by the sheriff.
When is the deadline to enforce a South Carolina mechanics lien, or, how long is my lien effective?
In South Carolina, an action to enforce a mechanics lien must be initiated within 6 months from the last day on which the claimant furnished labor and/or materials to the project. Note that a lis pendens must also be filed in South Carolina.
Some case law suggests that an action to enforce a mechanics lien must be initiated within 6 months of the date on which the lien was filed. Because of this, it may be best practice to initiate an action to enforce a lien before the earlier of either 6 months after the lien was filed or 6 months after the date of last furnishing, just to be safe.
Can I collect the entire unpaid amount from the property owner if they already paid the general contractor in full in South Carolina?
No, South Carolina is considered an “unpaid balance lien state.” Meaning that a subcontractor or supplier’s lien claim will be limited to the amount still owed to the GC at the time of filing.
Learn more: Full Price vs. Unpaid Balance Lien States
Does a South Carolina lien have priority over pre-existing mortgages or other construction loans?
No. South Carolina generally applies a “first-in-time, first-in-right” rule between mechanics liens and other competing encumbrances.
As between competing mechanics liens, the time of filing is of no consequence. Competing mechanics liens (of the same class), if there are not enough funds to fully pay them all, share the funds on a pro-rata basis. Mechanics liens of subcontractors or more remote parties take priority over the lien of a general contractor.
• Dive deeper: Lien Priority | What Happens When Everybody Is Trying to Grab a Piece of the Same Pie?
Who cancels the South Carolina mechanics lien if/when I get paid?
South Carolina lien law provides that “when a debt secured by such a lien is fully paid, the creditor, at the expense of the debtor, shall enter on the margin of the registry where the statement is recorded a discharge of his lien or shall execute a release thereof, which may be recorded where the statement is recorded.” So, the lien claimant must release the lien, but the debtor must pay for the release.
People are asking South Carolina construction attorneys:
Not able to send Notice of Intent to Lien to the Site Optioner
Does my Mechanics Lien expire after 1 year?
What is the best way to dispute a baseless mechanics lien being filed against my home
Do I file a lien next?
Hello, and thank you for reaching out.
Your question may be too specific for an attorney to answer in this public forum. You may wish to consider consulting an attorney privately. Here are some attorneys from our directory in your area: https://www.levelset.com/payment-help/experts/construction-lawyer/south-carolina/
I hope this helps!
Is my lien affected by my lack of notice of commencement
Landscaper inflated mechanics lien
There are numerous variables that can influence the outcome of this kind of dispute including what is in writing (and what isn't) as well as the contractor's timing. I am happy to discuss this with you and to go over your options. Please feel free to contact me at your convenience.
What is my next step
Can I file a mechanics lien.
Provided your last labor and/or material was supplied in the last 90 days you probably have mechanic's lien rights which need to be perfected. There are a couple of other questions which would need to be answered regarding the type of work and amounts owed. Feel free to contact me to discuss.
Where do my lien rights stand with a change of ownership of the property I am currently doing work at?
Generally, mechanics lien rights stick with the project property. So, when the property is sold mid-job, the new owners should become responsible for any potential lien claims. Levelset discusses that in these article: What Happens If I Filed My Mechanics Lien After the Property Was Sold?
According to South Carolina's priority rules, a mechanics lien filed after the new owner's mortgage wouldn't take priority over the mortgage. However, a lien claim should certainly be an alarming development for a new commercial owner and could force some action on their part - whether that be them stepping in to resolve the matter, them contacting the prior owner and forcing them to deal with the matter, or some other resolution.
As for required notices - South Carolina general contractors don't have any mandatory preliminary notices, so there's no notice that becomes required simply due to the sale of the property. Note, though, that contacting the new owner to notify them about the payment situation would be wise.
To the extent it looks like a lien may be required to recover payment, it'd also be wise to send any payment reminders, demands, or Notices of Intent to both the original owner and the new owner - the more eyes on the issue, the better the chances that recovery. Plus, if all parties are brought to the discussion, that'd improve transparency on the payment communications and could lead to a quicker resolution. Not to mention, an original owner who's failed to make payment could run into even bigger issues surrounding the sale.
Can a homeowner be required to pay TWICE for materials/labor if the contractor files bankruptcy?
The answer is probably not. Under South Carolina law, Subcontractor and Supplier liens are to be pro-rated based on what you owed the Contractor at the time the liens were filed. It sounds like the Contractor did not finish the job so the $25,000 contract balance would be reduced by the amounts you actually spend to complete the work of the original contract and/or correct defects in that original work. If there is anything left of the $25,000.00 contract balance after that you would be obligated to pro-rate it among the lienors (and to pay them that pro-rated amount).
SECTION 29-5-60. Proration of payments among lienors.
(A) In the event the amount due the contractor by the owner is insufficient to pay all the lienors acquiring liens as herein provided it is the duty of the owner to prorate among all just claims the amount due the contractor.
(B) In the event the amount due a subcontractor by the contractor is insufficient to pay all the lienors acquiring liens under Section 29-5-20 as a result of supplying labor, materials, or services to that subcontractor, all just liens must be prorated by the contractor among sub-subcontractors and suppliers to that subcontractor.
Do you have to be a licensed contractor in order to file a mechanic lien
The short answer is Yes you usually do. The longer answer is that it depends on what type or work or what material you supplied to the project. If South Carolina LLR requires you to be licenesed or registered to do the work than you must have that license or registration in order to file a lien. However, if you aren't required to be licensed (an easy example would be a materials supplier, like tile or brick) then you can still file a lien without a licenese.
SECTION 29-5-15. Filing requirements; penalty for frivolous lien.
(A) To file a mechanics' lien, a contractor must provide the county clerk of court or register of deeds proof that he is licensed or registered if he is required by law to be licensed or registered. As proof of licensure or registration, the contractor must record his contractor license number or registration number on the lien document when the lien document is filed.
(B) A contractor who files a frivolous lien is subject to a fine up to five thousand dollars, the loss of his registration or contractor license, or both.
Can I still File the Lien if customer is in a lease?
When a tenant is the one commissioning the improvements, a lien may still be filed in most circumstances. But the question becomes whether the lien will attach to the property itself, or the tenant's leashold interest; which tends to be a fact-intensive discussion.
- For a deep dive on the subject: Construction Lien Rights When the Project is a Tenant Improvement
In South Carolina, there needs to be some specific consent or approval for the work granted from the owner to the tenant to allow claimants to file a lien against the property. Mere knowldege of the improvements isn't enough. It will ultimately depend on whether there was explicit consent; which given your question, might be applicable here. Furthermore, even if such consent is given, an owner in South Carolina may provide a Notice of Nonresponsibility to prevent liens from attaching to the property.
Lastly, notwithstanding the previous statements, a lien may still be filed against the tenant/lessor's leashold interest. Sending a Notice of Intent to Lien to both the tenant and the property owner may be theuseful step. That way both parties are made aware of the payment problem, and their responses could provide valuable intel on the arrangement between the two, and could end up resolving the dispute before having to actually file a claim.
Can I still file lien if signed condition wiever
Typically the "conditional" part of a lien waiver is that the waiver is not valid unless and until they pay you the amount listed in the waiver. You should probably pursue your lien before time runs out.
When should a lien be filed in SC?
Generally, South Carolina mechanics liens should be served within the same 90-day period that the lien must be filed in, under § 29-5-90 of the state's lien statute. In fact, some South Carolina counties will actually require proof of service of the lien - otherwise, they won't record the mechanics lien filing. This isn't an explicit legal requirement set out by the lien statute. However, if the county refuses to record a lien without having proof of service, claimants won't really have much choice.
As for whether the lien's recording information must be included with served liens - generally, no, that's not required in order to have a valid mechanics lien. And, in the counties where the recorder won't file a lien until it's been served, that order of operations isn't really possible, anyway.
For further discussion on filing and serving South Carolina mechanics liens: (1) South Carolina Mechanics Lien Guide and FAQs; and (2) How to File a South Carolina Mechanics Lien – Step by Step Guide to Get You Paid.
29-5-90 SC law requires Statement of Account just and true, proper and just credits, what if only debt due stated
Generally, mechanics liens are only available to the extent that work has been performed but not paid for. A contractor cannot file a mechanics lien for the entire contract when they have only performed some small portion of the work. As you mention above, South Carolina seems to abide by this general rule: § 29-5-90 of South Carolina's mechanics lien statute calls for the amount that's due to the contractor, with just credits given.
With that in mind, if the contractor has only performed a small portion of the work but has filed a mechanics lien for the entire price of their contract, then there's probably a good chance that the lien is ovestated and rendered invalid or unenforceable as a result. Still - only a court can decide on the validity of a mechanics lien. Though, hiring a local South Carolina construction lawyer can help to review the validity of the claim, and they can advise you on the likelihood of success of challenging the lien. You can begin the search for a South Carolina lawyer here: Top South Carolina Construction Lawyers.
Finally, I think this article should be useful: A Mechanics Lien Was Filed on My Property – What Do I Do Now?
What happens if the contractor files a mechanics lien against my property?
First, it's worth noting that cleaning services, by themselves, are generally not lienable because they don't permanently improve, alter, or change the project property. More on that here: Can You File A Mechanics Lien for Cleaning Services?
As for how to respond to a mechanics lien or a threat of a lien claim, these two articles will be useful: (1) I Just Received a Notice of Intent to Lien – What Should I Do Now?; and (2) A Mechanics Lien Was Filed on My Property – What Do I Do Now?
With that being said, keep in mind that the cost of defending against a lien claim or having the lien removed could quickly exceed $1,000. So, even if you feel that full payment is not in order, it may be worthwhile to negotiate some lesser payment in exchange for a lien waiver. Plus, if you truly believe they have been stealing from you, you can always bring your own claims later on, if necessary.
How long is a mechanics lien valid in SC
Can We send a notice of non-payment or file a lien through this website?
Can they put a lien on my house?
How can I collect interest on the money owed me for over a year when a mechanics lien has been filed?
The ability to seek interest is very fact specific and, unfortunately, I don't have enough information about your claim to give you specific advice. If the contract sets an interest rate, you would be entitled to that rate. If the contract does not set a specific rate, you can seek interest statutorily through the demand letter statute, prompt pay act or through common law pre-judgment interest depending on the circumstances.
Can I collect interest on the money owed me for over a year?
Mechanics lien for service fee that was never stated?
How long is a mechanics lien valid?
Interest included on lien
The owner hired a sub to finish my job. Can I file a lien if I'm unlicensed in California?
How do I file a lien on a home we have done the remodel on
Lien rights for restoration contractors?
Can the owner force us to release lien if they paid contractor and we are not paid as a supplier?
How long can mechanic's lien stay on property? Can the owner force us to release it?
What happens when you send an NOI to a company and you later learned there is a HQ?
Best rated general contractors in South Carolina
5 essential things to know about a South Carolina mechanics lien
Contractors & suppliers have strong lien rights in South Carolina. If a contractor or supplier isn’t paid on an South Carolina job, they can turn to filing a lien to speed up payment and protect themselves. However, there are specific requirements and rules that must be followed. Here are 5 essential things you need to know about South Carolina’s mechanics lien law.
Licensed contractors have the right to lien
In South Carolina, any project participant that contributes labor or supplies to the erection, alteration or repair towards the improvement of a property has mechanics lien rights. This includes licensed contractors, subcontractors, laborers, design professionals (architects and engineers), surveyors, and equipment lessors.
An especially interesting fact about eligibility in South Carolina is that security guards at the site of labor as well as landscapers are also entitled to mechanics lien rights. The one condition for landscapers is that the amount of work is valued at over $5000.
Note, however, that notwithstanding the broad mechanics lien protection in South Carolina, a potential lien claimant must be licensed if performing work for which a license is required by South Carolina law, and the lien claimant’s license or registration number is required to be provided on the face of the lien claim itself.
The deadline to file a mechanics lien in South Carolina is unique
The deadline to file a mechanics lien in South Carolina is 90 days from the date that a project participant last provided services or materials for a project. However, unlike many other states, South Carolina has a “call-back” policy. A “call-back” generally means that although a project has been claimed “completed” a participant might be asked to perform additional services or last-minute materials. Normally these are not lienable. However, South Carolina allows a lien to be filed 90 days from the date “call-back” work was performed.
Preliminary notice is not required but may protect participant rights
It is always advisable to send a preliminary notice on any project in any state, but in South Carolina, it’s not necessarily required. A general contractor can file a Notice of Commencement within 15 days of a projects commencement to either the Clerk of Court or Register of Deeds in the property’s county. It is not mandatory, but filing this notice will better protect the rights of a general contractor. Sub-subcontractors and suppliers to subcontractors will only have rights equal to the amount that the general contractor owes to the subcontractor.
If sub-subcontractors and suppliers to subcontractors do their research, finding out that a Notice of Commencement has been filed, they may in turn file a Notice of Furnishing Labor and Materials that can be served to the general contractor via certified mail with return receipt requested further protecting their own rights.
Some counties require proof of service on owner prior to filing the lien
Notice the lien was filed must be provided to the property owner. Some counties in South Carolina require that a proof of service of the lien on the owner be provided prior to the recording of the lien. However, in any event, the property owner must be served with a copy of the lien within the same 90-day period in which the lien must be filed. If the property owner cannot be found, the lien may be served on the person in possession of the property — and an affidavit of the sheriff stating that the owner could not be found must be filed. Note that service may not be accomplished by mail, or even by a private process server, South Carolina requires that the lien be served on the property owner (or person in possession, if the property owner cannot be found) by the sheriff.
Mechanics liens do not take priority over prior encumbrances
Mechanics liens do not generally take priority against prior encumbrances (mortgages etc.) in South Carolina. South Carolina generally applies the “first in time, first in right” rule, and priority is based solely on time. Generally, if there are not enough funds to pay all mechanics liens of the same class, competing liens must share funds on a pro rata basis. Subcontractors and 3rd tier parties take priority over general contractors.
How to file a Mechanics Lien in South Carolina (DIY)
Read the guide
In our step-by-step guide, we will walk you through each step required to qualify for and file a South Carolina mechanics lien. This guide explains the notices you need to send, the information required on the South Carolina mechanics lien form, and essential tips about delivering it to the county office for recording.
Get the right form
South Carolina has different claim of lien forms for direct claimants, indirect claimants, and 3rd tier parties. Follow the links to download the correct form. Our free forms were created by construction attorneys to meet the requirements in South Carolina mechanics lien laws. The state statutes are very specific about the language and formatting required in a lien claim document. We make it easy to get this part right.
Fill out the form
Make sure you get this part right. Filling out the form correctly requires attention to detail because mistakes could completely invalidate your lien claim. All of the information must be 100% accurate, including the legal names of each party, the property description, and the claim amount. Review every detail carefully.
Serve the lien on the owner
Some counties in South Carolina require you to notify the owner before the lien is filed. Also, South Carolina requires these notices to be delivered by the county sheriff in person. If the property owner cannot be found, the sheriff will submit the lien to the person in possession of the property.
File your lien with the register of deeds
File your completed form with the recorder’s office in the South Carolina county where the property is located, and pay the recording fee. View a full list of South Carolina register of deed’s offices to find contact information, fees, and filing requirements.
After you file
A South Carolina mechanics lien is only valid for six (6) months. Unless it is extended, you will need to enforce your lien claim within this deadline.
If you get paid, it’s a good idea to file a lien release form to discharge your lien claim.
South Carolina's Mechanics Lien Statutes
The provisions of the South Carolina statutes that permit the filing of mechanics liens and materialman’s liens on construction projects can be found in South Carolina’s Mechanics’ Lien Law, S.C. Code 1976 § 29-5-10 et. seq. The full text of the South Carolina Construction Lien Law is provided below. Updated as of May 2023.
§ 29-5-10. Lien of Person Furnishing Labor and Materials for Buildings or Structures; Offers of Settlement
(a) A person to whom a debt is due for labor performed or furnished or for materials furnished and actually used in the erection, alteration, or repair of a building or structure upon real estate or the boring and equipping of wells, by virtue of an agreement with, or by consent of, the owner of the building or structure, or a person having authority from, or rightfully acting for, the owner in procuring or furnishing the labor or materials shall have a lien upon the building or structure and upon the interest of the owner of the building or structure in the lot of land upon which it is situated to secure the payment of the debt due to him. The costs which may arise in enforcing or defending against the lien under this chapter, including a reasonable attorney’s fee, may be recovered by the prevailing party. The fee must be determined by the court in which the action is brought but the fee and the court costs may not exceed the amount of the lien. As used in this section, labor performed or furnished in the erection, alteration, or repair of any building or structure upon any real estate includes the preparation of plans, specifications, and design drawings and the work of making the real estate suitable as a site for the building or structure. The work is considered to include, but not be limited to, the grading, bulldozing, leveling, excavating, and filling of land (including the furnishing of fill soil), the grading and paving of curbs and sidewalks and all asphalt paving, the construction of ditches and other drainage facilities, and the laying of pipes and conduits for water, gas, electric, sewage, and drainage purposes, and the disposal of any construction and demolition debris, as defined in Section 44-96-40(6), including final disposal by a construction and demolition landfill. Any private security guard services provided by any person at the site of the building or structure during its erection, alteration, or repair is considered to be labor performed or furnished within the meaning of this section. As used in this section, materials furnished and actually used include tools, appliances, machinery, or equipment supplied for use on the building or structure to the extent of their reasonable rental value during their actual use. “Person” as used in this section means any individual, corporation, partnership, proprietorship, firm, enterprise, franchise, association, organization, or other entity. For purposes of this section, the term “materials” includes flooring, floor coverings, and wall coverings.
(b) Not less than fifteen days before the first term of court at which the trial is set, either party may file and serve on the other party an offer of settlement, and within ten days thereafter the party served may respond by filing and serving his offer of settlement. The offer shall state that it is made under this section and specify the amount, exclusive of interest and costs, which the party serving the offer is willing to agree constitutes a settlement of the lien. If the action is not reached for trial, then not less than fifteen days before the next term of court and subsequent terms of court at which the trial is set, either party may file and serve on the other party an offer of settlement or an amendment of a prior offer of settlement and, within ten days after that, the party served may respond by filing and serving his offer or amended offer of settlement. The offer or amended offer supersedes any offer previously made under this section by the same party.
An offer of settlement is considered rejected unless an acceptance in writing is filed and served on the party making the offer, five days before the commencement of the term.
If the offer is rejected, it may not be referred to for any purpose at the trial, but may be considered solely for the purpose of awarding costs and litigation expenses under this section.
For purposes of the award of attorney’s fees, the determination of the prevailing party is based on one verdict in the action. One verdict assumes some entitlement to the mechanic’s lien and the consideration of compulsory counterclaims. The party whose offer is closer to the verdict reached is considered the prevailing party in the action. If the difference between both offers and the verdict is equal, neither party is considered to be the prevailing party for purposes of determining the award of costs and attorney’s fees.
If the plaintiff makes no written offer of settlement, the amount prayed for in his complaint is considered to be his final offer of settlement.
If the defendant makes no written offer of settlement, the value of his counterclaim is considered to be his negative offer of settlement. If the defendant has not asserted a counterclaim, his offer of settlement is considered to be zero.
§ 29-5-15. Filing Requirements; Penalty for Frivolous Lien
(A) To file a mechanics’ lien, a contractor must provide the county clerk of court or register of deeds proof that he is licensed or registered if he is required by law to be licensed or registered. As proof of licensure or registration, the contractor must record his contractor license number or registration number on the lien document when the lien document is filed.
(B) A contractor who files a frivolous lien is subject to a fine up to five thousand dollars, the loss of his registration or contractor license, or both.
§ 29-5-20. Lien of Laborer, Mechanic, Subcontractor or Materialman; Limits on Aggregate Amount of Lien Filed by Subcontractor or Supplier; Limits on Total Aggregate Amount of Liens; Exceptions; Settlement of Actions to Enforce Lien
(A) Every laborer, mechanic, subcontractor, or person furnishing material for the improvement of real estate when the improvement has been authorized by the owner has a lien thereon, subject to existing liens of which he has actual or constructive notice, to the value of the labor or material so furnished, including the costs of the action and a reasonable attorney’s fee which must be determined by the court in which the action is brought but only if the party seeking to enforce the lien prevails. If the party defending against the lien prevails, the defending party must be awarded costs of the action and a reasonable attorney’s fee as determined by the court. The fee and the court costs may not exceed the amount of the lien. The lien may be enforced as herein provided.
(B) In no event shall the aggregate amount of any liens filed by a sub-subcontractor or supplier exceed the amount due by the contractor to the subcontractor to whom the sub-subcontractor or supplier has supplied labor, material, or services unless the sub-subcontractor or supplier has provided notice of furnishing labor or materials by certified or registered mail to the contractor. Such notice of furnishing labor or materials shall include:
(1) the name of the sub-subcontractor or supplier who claims payment;
(2) the name of the person with whom the claimant contracted or by whom he was employed;
(3) a description of the labor, services, or materials furnished and the contract price or value thereof. Materials specially fabricated by a person other than the one giving notice and the contract price or value thereof shall be separately stated in the notice;
(4) a description of the project where labor, services, or materials were used sufficient for identification;
(5) the date when the first and the last item of labor or service or materials was actually furnished or scheduled to be furnished; and
(6) the amount claimed to be due, if any.
After receiving such notice, no payment by the contractor to the subcontractor will lessen the amount recoverable by the person so giving notice. However, in no event shall the total aggregate amount of liens on the improvement exceed the amount due by the owner.
(C) Not less than fifteen days before the first term of court at which the trial is set, either party may file and serve on the other party an offer of settlement, and within ten days thereafter the party served may respond by filing and serving his offer of settlement. The offer shall state that it is made under this section and specify the amount, exclusive of interest and costs, which the party serving the offer is willing to agree constitutes a settlement of the lien. If the action is not reached for trial, then not less than fifteen days before the next term of court and subsequent terms of court at which the trial is set, either party may file and serve on the other party an offer of settlement or an amendment of a prior offer of settlement and, within ten days after that, the party served may respond by filing and serving his offer or amended offer of settlement. The offer supersedes any offer previously made under this section by the same party.
An offer of settlement is considered rejected unless an acceptance in writing is filed and served on the party making the offer five days before the commencement of the term.
If the offer or amended offer is rejected, it may not be referred to for any purpose at the trial but may be considered solely for the purpose of awarding costs and litigation expenses under this section.
For purposes of the award of attorney’s fees, the determination of the prevailing party is based on one verdict in the action. One verdict assumes some entitlement to the mechanic’s lien and the consideration of compulsory counterclaims. The party whose offer of settlement is closer to the verdict reached is considered the prevailing party in the action. If the difference between both offers and the verdict is equal, neither party is considered to be the prevailing party for purposes of determining the award of costs and attorney’s fees. If the plaintiff makes no written offer of settlement, the amount prayed for in his complaint is considered to be his final offer of settlement.
If the defendant makes no written offer of settlement, the value of his counterclaim is considered to be his negative offer of settlement. If the defendant has not asserted a counterclaim, his offer of settlement is considered to be zero.
(D) Subsection (B) does not apply to individual laborers when the amount of their lien is less than two thousand dollars.
§ 29-5-21. Services of Surveyor and Real Estate Licensee as Improving Real Estate; Real Estate Licensee's Liens
(A) A surveyor who surveys real estate by virtue of an agreement with the owner of such real estate has furnished material for the improvement of real estate within the meaning of Section 29-5-20.
(B)
(1) A real estate licensee who, by virtue of a written agreement with the owner, performs professional services for which he is licensed under Title 40 incident to marketing, developing, or improving commercial real estate preparatory to or as a part of a commercial real estate lease or rental transaction involving the commercial real estate, has furnished labor or material for the improvement of commercial real estate within the meaning of Section 29-5-20.
(2) A real estate licensee shall not acquire a lien under this subsection unless:
(a) the owner of the commercial real estate or the owner’s authorized agent authorizes the real estate licensee, under the terms of a written agreement, to lease an interest in the commercial real estate; and
(b) the real estate licensee or the real estate licensee’s affiliated licensees provide licensed services that result, during the term of a written agreement described in item (1) of this subsection, in the procuring of a person or entity that rents or leases the commercial real estate or rents or leases an interest in the commercial real estate upon terms contained in a written agreement described in item (1) of this subsection.
(3) A real estate licensee shall not acquire a lien under this subsection upon residential real estate.
(4) Prior recorded liens shall have priority over a real estate licensee’s lien. A prior recorded lien shall include, without limitation:
(i) a valid mechanic’s lien claim that is recorded subsequent to the real estate licensee’s lien notice of lien but which relates back to a date prior to the recording date of the real estate licensee’s lien notice of lien; and
(ii) prior recorded liens securing revolving credit and future advance of construction loans as described in Section 29-3-50.
§ 29-5-22. Reasonable Rental Value of Tools, Appliances, Machinery, and Equipment
A person who supplies tools, appliances, machinery, or equipment used as provided in Section 29-5-10(a) is considered to have furnished material for the improvement of real estate within the meaning of Sections 29-5-20 and 29-5-40 to the extent of the reasonable rental value of the tools, appliances, machinery, or equipment for the period of actual use.
§ 29-5-23. Notice of Project Commencement; Location Notice; Failure to File Notice
Any person entering into a direct agreement with, or with the consent of, an owner for the improvement of real property may file with the clerk of court or register of deeds in the county or counties where the real property is situate a notice of project commencement. The notice of project commencement shall contain the following information:
(1) the name and address of the person filing the notice of commencement;
(2) the name and address of the owner or developer;
(3) a general description of the improvement; and
(4) the location of the project.
The notice must be filed within fifteen days of the commencement of work and must be accompanied by a filing fee of fifteen dollars to be deposited in that county’s general fund. The name and address of the contractor must be posted at the job site. A location notice also must be posted at the job site. The location notice must contain the following statement: “The contractor on the project has filed a notice of project commencement at the county courthouse. Sub-subcontractors and suppliers to subcontractors shall comply with Section 29-5-20 when filing liens in connection with this project.” The failure to file a notice of project commencement shall render the provisions of Sections 29-5-20(B) and 29-5-60(B) inapplicable. The failure to file a notice of project commencement shall also render the provisions of Sections 29-5-440, 11-35-3030(2)(c), 57-5-1660(b), and 11-1-120, relating to the requirement of a notice of providing labor, materials, or rental equipment inapplicable for a claim against a payment bond furnished by a contractor holding a direct contractual agreement with an owner. The filing of a notice of project commencement shall not constitute a cloud, lien, or encumbrance upon, or defect to, the title of the real property described in the notice, nor shall it alter the aggregate amounts of liens allowable under Section 29-5-40, nor shall it affect the priority of any mortgage filed before or after the notice, nor shall it affect any future advances under any mortgage. The clerk of court or register of deeds in each county shall maintain a separate book and index of all notices of project commencements.
§ 29-5-25. Private Security Guard Services at Site of Real Estate Improvement
Any person providing private security guard services at the site of the real estate during its improvement shall be deemed to be a laborer within the meaning of Sections 29-5-20 and 29-5-40. “Person” as used in this section shall mean any individual, corporation, partnership, proprietorship, firm, enterprise, franchise, association, organization or other such entity.
§ 29-5-26. Landscape Services
(A) A person who provides a landscape service on a parcel of real estate, which service exceeds five thousand dollars, by virtue of a written agreement with the owner of the real estate and to whom a debt is due for his performance of the landscaping service has a mechanics’ lien on the real estate to secure payment of debt due to him as provided by Section 29-5-10 and Section 29-5-20. The lien attaches to the land and a building, structure, or other improvement on the land.
(B) As used in this chapter, a landscape service includes:
(1) land clearing, grading, filling, plant removal, natural obstruction removal, or other preparation of land;
(2) provision or installation, or both of them, of a landscaping item including plant material, mulch, paving, walkway, swimming pool, fountain, retaining wall, bulkhead, deck, patio, lightscaping system, irrigation system, drainage structure, drainage system, underground utility, or other feature incidental and necessary to a landscape plan or site design; or
(3) both.
(C) A landscaping service does not depend on whether the service is related to the construction, erection, alteration, or repair of a building or other structure.
§ 29-5-27. Laborer and Person Defined
Any person providing construction and demolition debris disposal services, as defined in Section 44-96-40(6), including, but not limited to, final disposal services provided by a construction and demolition landfill, is a laborer within the meaning of Sections 29-5-20 and 29-5-40. “Person” as used in this section means any individual, corporation, partnership, proprietorship, firm, enterprise, franchise, association, organization, or another entity.
§ 29-5-30. Lien Against Debtor with Life Estate or Whose Estate is Less than Fee Simple
If the person for whom the work is done or materials are furnished has an estate for life or any other estate less than a fee simple in the land or if the property, at the time of recording the statement, is mortgaged or under any other encumbrance, the lien before provided for shall bind his whole estate and interest therein in like manner as a mortgage would have done and the creditor may cause the right of redemption or whatever other right or estate the owner had in the property to be sold and applied to the discharge of his debt, according to the provisions of this chapter.
§ 29-5-40. Notice to Owner Before Lien Attaches When Laborer was Employed by Someone Other than Owner
Whenever work is done or material is furnished for the improvement of real estate upon the employment of a contractor or some other person than the owner and such laborer, mechanic, contractor or materialman shall in writing notify the owner of the furnishing of such labor or material and the amount or value thereof, the lien given by Section 29-5-20 shall attach upon the real estate improved as against the true owner for the amount of the work done or material furnished. But in no event shall the aggregate amount of liens set up hereby exceed the amount due by the owner on the contract price of the improvement made.
§ 29-5-50. Lienor's Preference Over Contractor
Any person claiming a lien under the provisions of this chapter who shall have given the notice provided for herein shall be entitled to be paid in preference to the contractor at whose instance the labor was performed or material furnished and no payment by the owner to the contractor thereafter shall operate to lessen the amount recoverable by the person so giving the notice.
§ 29-5-60. Proration of Payments Among Lienors
(A) In the event the amount due the contractor by the owner is insufficient to pay all the lienors acquiring liens as herein provided it is the duty of the owner to prorate among all just claims the amount due the contractor.
(B) In the event the amount due a subcontractor by the contractor is insufficient to pay all the lienors acquiring liens under Section 29-5-20 as a result of supplying labor, materials, or services to that subcontractor, all just liens must be prorated by the contractor among sub-subcontractors and suppliers to that subcontractor.
§ 29-5-70. Force of Lien Against Existing Recorded Mortgage
Except as otherwise provided in Section 29-3-50, a lien claimed by any mechanic or materialman furnishing labor, services, or material is not enforceable against any mortgage recorded before the filing of the notice pursuant to Section 29-5-90 setting forth the statement of account upon which the lien is based.
§ 29-5-80. Notice of Nonresponsibility by Owner of Building or Structure
The owner of any such building or structure in process of erection or being altered or repaired, other than the person by whom or in whose behalf a contract for labor or materials has been made, may prevent the attaching of any lien for labor thereon not at the time performed or materials not then furnished by giving notice, in writing, to the person performing or furnishing such labor or furnishing such materials that he will not be responsible therefor.
§ 29-5-90. Dissolution of Lien for Failure to Serve and File Statement; Contents of Statement
Such a lien shall be dissolved unless the person desiring to avail himself thereof, within ninety days after he ceases to labor on or furnish labor or materials for such building or structure, serves upon the owner or, in the event the owner cannot be found, upon the person in possession and files in the office of the register of deeds or clerk of court of the county in which the building or structure is situated a statement of a just and true account of the amount due him, with all just credits given, together with a description of the property intended to be covered by the lien sufficiently accurate for identification, with the name of the owner of the property, if known, which certificate shall be subscribed and sworn to by the person claiming the lien or by someone in his behalf and shall be recorded in a book kept for the purpose by the register or clerk who shall be entitled to the same fees therefor as for recording mortgages of equal length. Provided, that in the event neither the owner nor the person in possession can be located after diligent search, and this fact is verified by affidavit of the sheriff or his deputy, the lien may be preserved by filing the statement together with the affidavit. The delivery on the register or clerk for filing, as provided in this section, shall be and constitute the delivery contemplated with regard to such liens in Title 30 of this Code.
§ 29-5-100. Proceedings not Invalidated by Inaccuracy of Statement of Account
No inaccuracy in such statement relating to the property to be covered by the lien, if the property can be reasonably recognized, or in stating the amount due for labor or materials shall invalidate the proceedings, unless it appear that the person filing the certificate has wilfully and knowingly claimed more than is his due.
§ 29-5-110. Release of Lien upon Filing Written Undertaking and Security
At any time after service and filing of the statement required under Section 29-5-90 the owner or any other person having an interest in or lien upon the property involved may secure the discharge of such property from such lien by filing in the office of clerk of court or register of deeds where such lien is filed his written undertaking, in an amount equal to one and one-third times the amount claimed in such statement, secured by the pledge of United States or State of South Carolina securities, by cash or by a surety bond executed by a surety company licensed to do business in this State, and upon the filing of such undertaking so secured the lien shall be discharged and the cash, securities or surety bond deposited shall take the place of the property upon which the lien existed and shall be subject to the lien. In the event of judgment for the person filing such statement in a suit brought pursuant to the provisions of this chapter, such judgment shall be paid out of the cash deposited or, in event of pledge of securities, it shall be paid from the proceeds of a sale of so much of the pledged securities as shall be necessary to satisfy such judgment or, in event of the filing of a surety bond, the surety company issuing such bond shall pay such amount found due, not to exceed the amount of the bond. Unless suit for enforcement of the lien is commenced as required by Section 29-5-120, the undertaking herein required shall be null and void and the principal therein shall have the right to have it canceled and such cash or securities deposited or pledged or surety bond filed shall be released from the lien herein provided.
§ 29-5-120. Time for Bringing Suit to Enforce Lien; Dissolution and Release of Lien
(A) Unless a suit for enforcing the lien is commenced and notice of pendency of the action is filed within six months after the person desiring to avail himself of it ceases to labor on or furnish labor or material for the building or structure, the lien must be dissolved.
(B) A mechanics’ lien and associated bonds may be released by a court order, a written affidavit of the bond holder’s attorney, or by a written affidavit from the defendant’s attorney stating:
(1) six months has passed since the lien was attached and no suit or notice of pendency has been filed; or
(2) the failure of the filing party to take some other timely action required by this chapter. This affidavit must be in the form approved by the appropriate local office where the mechanics’ lien was filed and must reference the lien’s recording information.
§ 29-5-130. Enforcement of Certain Liens Before Magistrate's Court
When the amount of the claim does not exceed one hundred dollars the lien may be enforced by a petition to a magistrate. And such magistrate shall have like power and authority within his jurisdiction as herein conferred upon the court of common pleas, with like rights of appeal to the parties as exist in other civil cases.
§ 29-5-140. Enforcement of Lien by Petition to Court of Common Pleas
The lien may be enforced by petition to the court of common pleas for the county in which the building or structure is situated. The petition may be filed in term or in the clerk’s office in vacation and the date of the filing shall be deemed the commencement of the suit.
§ 29-5-150. Service of Petition
The petition may be served with the summons or filed with the clerk and shall be returned and entered as other civil cases.
§ 29-5-160. Contents of Petition
The petition shall contain a brief statement of the contract on which it is founded and of the amount due thereon, with a description of the premises subject to the lien and all other material facts and circumstances, and shall pray that the premises may be sold and the proceeds of the sale applied to the discharge of the demand.
§ 29-5-170. Petition Filed by Multiple Lienors
Any number of persons who have actually performed labor or furnished labor or materials on one or more buildings or structures upon different lots of land, when the labor was performed for the same owner, contractor or other person, may join in the same petition for their respective liens and the same proceedings shall be had in regard to the rights of each petitioner and the respondent may defend as to each petitioner in the same manner as if he had severally petitioned for his individual lien.
§ 29-5-180. Amendments of Pleadings
The court may at any time allow either party to amend his pleadings as in other civil actions.
§ 29-5-190. Notice to Owner and Other Creditors
The court in which the petition is entered shall order notice to be given to the owner of the building or structure, that he may appear and answer thereto at a certain day in the same term or at the next term, by serving him with an attested copy of the petition, with the order of the court thereon, fourteen days at least before the time assigned for the hearing. And the court shall also order notice of the filing of the petition to be given to all other creditors who have a lien of the same kind upon the same estate by serving them with a copy of the last-mentioned order in like manner.
§ 29-5-200. Notice by Publication or Other than Personal Service
If it appears to the court that any of the parties entitled to notice are absent or that they cannot probably be found or be served with the notice, the court may, instead of the personal notice before mentioned or in addition thereto, order notice given to all persons interested by publishing in some newspaper the substance of the petition with the order of the court thereon assigning the time and place for a hearing or may order such other notice to be given as may, under the circumstances of the case, be considered most proper and effectual.
§ 29-5-210. Further Notice of Suit
If at the time assigned for the hearing it appears to the court that any of the persons interested had not had a sufficient notice of the suit, the court may order further notice to them in such manner as may be considered most proper and effectual.
§ 29-5-220. Hearing on Claims of Lienors
At the time assigned for the hearing, or within such further time as the court allows for that purpose, every creditor having a lien of the kind before mentioned upon the same property may appear and prove his claim and the owner and each of the creditors may contest the several claims of every other creditor and the court shall hear and determine them in a summary manner, either with or without a jury, as the case may require.
§ 29-5-230. Questions for Jury
Every material question of fact arising in the case shall be submitted to a jury, if required by either party or deemed proper by the court, and the trial shall be had upon a question stated or an issue framed or otherwise, as the court may order. A jury shall be had before a magistrate only as in other civil cases.
§ 29-5-240. Determination of Claims Due but Not Yet Payable
The court shall ascertain and determine the amount due to each creditor who has a lien of the kind before mentioned upon the property in question and every such claim due, absolutely and without any condition, although not then payable, shall be allowed with a rebate of interest to the time when it would become payable.
§ 29-5-250. Recovery for Part Performance
When the owner fails to perform his part of the contract and by reason thereof the other party, without his own default, is prevented from completely performing his part, he shall be entitled to a reasonable compensation for as much as he has performed in proportion to the price stipulated for the whole and the court shall adjust his claim accordingly.
§ 29-5-260. Sale of Premises if Lien Established
If the lien is established in favor of any of the creditors whose claims are presented the court shall order a sale of the property to be made by such officer as may be authorized by law to make sales of property.
§ 29-5-270. Sale of Part of Property
If part of the property can be separated from the residue and sold without damage to the whole and if the value thereof is sufficient to satisfy all debts proved in the case, the court may order a sale of that part, if it appears to be most for the interest of all parties concerned.
§ 29-5-280. Notice of Sale
The officer who makes the sale shall give notice of the time and place in the manner prescribed in relation to the sale of mortgaged lands under foreclosure, unless the court orders a different notice to be given.
§ 29-5-290. Distribution of Proceeds of Sale
If all the claims against the property covered by the lien are ascertained at the time of ordering the sale, the court may order the officer to pay over and distribute the proceeds of the sale, after deducting all lawful charges and expenses, to and among the several creditors to the amount of their respective debts, if there is sufficient therefor, and if there is not sufficient, then to divide and distribute such proceeds among the creditors in proportion to the amount due to each of them.
§ 29-5-300. Distribution of Proceeds by Court
If all the claims are not ascertained when the sale is ordered or if for any other reason the court finds it necessary or proper to postpone the order of distribution, it may direct the officer to bring the proceeds of the sale into court, there to be disposed of according to the decree of the court, and if, by reason of the claims of attaching creditors or for any other cause, the whole cannot be conveniently distributed at once the court may make two or more successive orders of distribution, as the circumstances may require.
§ 29-5-310. Distribution of Surplus
If there remain any surplus of the proceeds of the sale, after making all the payments before mentioned, it shall be forthwith paid over to the owner of the property, but such surplus, before it is so paid over, shall be liable to be attached or taken on execution in like manner as if it proceeded from a sale made by the officer on an execution.
§ 29-5-320. Prior Attaching Creditor is Preferred
If the interest of the owner in the building, structure or land is under attachment at the time of filing and recording the statement of the account, the attaching creditor shall be preferred to the extent of the value of the buildings and land as they were when the statement was recorded and the court shall ascertain, by a jury or otherwise as the case may require, what proportion of the proceeds of the sale shall be held subject to the attachment as derived from the value of the property when the statement was recorded.
§ 29-5-330. Distribution of Proceeds Where There is Attaching Creditor
If the attaching creditor recovers judgment he shall be entitled to receive on his execution the proportion of the proceeds held subject to his attachment, or so much thereof as may be necessary to satisfy his execution, and the residue of the proceeds shall be applied in the same manner as if there had been no such attachment.
§ 29-5-340. Subsequent Attachments
If the interest of the owner of the property is attached after the recording of the statement, the proceeds, after discharging all prior liens and claims, shall be applied to satisfy the execution of such attaching creditor.
§ 29-5-350. Attachments Intervening Between Two Liens
If an attachment is made after the recording of such statement and if, after the attachment, another like statement is recorded, the creditor in the latter statement shall be entitled to be paid only out of the residue of the proceeds remaining after paying all that is due on the demand a statement of which was recorded before the attachment and satisfying the attaching creditor.
§ 29-5-360. Rights of Creditors Among Themselves
When there are several attaching creditors, they shall, as between themselves, be entitled to be paid according to the order of their attachments. But when several creditors who are entitled to the lien provided for in this chapter have equal rights as between themselves and the fund is insufficient to pay the whole, they shall share it equally in proportion to their respective debts.
§ 29-5-370. Person Against Whom Lien may be Enforced When Debtor Dies or Conveys His Interest
If the person indebted dies or conveys away his estate or interest before the commencement of a suit on the contract, the suit may be commenced and prosecuted against his heirs or whoever holds the estate or interest which he had in the premises at the time the labor or materials were performed or furnished. Or, if a suit is commenced in his lifetime, it may be prosecuted against his executors, administrators, heirs or assigns in like manner as if the estate or interest had been mortgaged to secure the debt.
§ 29-5-380. Executor or Administrator May Enforce Creditor's Lien
If a creditor dies before the commencement of the suit, the suit may be commenced and prosecuted by his executor or administrator or, if commenced in his lifetime, it may be prosecuted by them as it might have been by the deceased, if living.
§ 29-5-390. Suits Begun by One Creditor may be Prosecuted by Another
If it appears in any stage of the proceedings that the suit was commenced by the petitioning creditor before his right of action accrued or after it was barred or if he becomes nonsuited or fails to establish his claims the suit may be prosecuted by any other creditor having such lien in the same manner as if it had been originally commenced by him, if the circumstances of the case are such that he might then or at any time after the commencement of the original suit have commenced a like suit on his own claim.
§ 29-5-400. Allowance of Claim and Costs of Petitioning Creditor
If the suit is commenced by the petitioning creditor before his right of action accrues, his claim may nevertheless be allowed if the suit is carried on by any other creditor, as provided in Section 29-5-390, but he shall not in such case be entitled to costs and he may be required to pay the costs incurred by the debtor or such part thereof as the court may deem reasonable.
§ 29-5-410. Costs
The costs, in all other respects, shall be subject to the discretion of the court and shall be paid from the proceeds of the sale or by any of the parties to the suit, as justice and equity require.
§ 29-5-420. Civil Action not Barred
Nothing contained in this chapter shall be construed to prevent a creditor in such contract from maintaining an action thereon in like manner as if he had no such lien for the security of his debt.
§ 29-5-430. Recording Discharge or Release of Lien
When a debt secured by such a lien is fully paid, the creditor, at the expense of the debtor, shall enter on the margin of the registry where the statement is recorded a discharge of his lien or shall execute a release thereof, which may be recorded where the statement is recorded.
§ 29-5-440. Suit on Payment Bond
Every person who has furnished labor, material, or rental equipment to a bonded contractor or its subcontractors in the prosecution of work provided for in any contract for construction, and who has not been paid in full therefor before the expiration of a period of ninety days after the day on which the last of the labor was done or performed by him or material or rental equipment was furnished or supplied by him for which such claim is made, shall have the right to sue on the payment bond for the amount, or the balance thereof, unpaid at the time of the institution of such suit and to prosecute such action to final execution and judgment for the sum or sums justly due him.
A remote claimant shall have a right of action on the payment bond only upon giving written notice by certified or registered mail to the bonded contractor within ninety days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material or rental equipment upon which such claim is made. However, in no event shall the aggregate amount of any claim against such payment bond by a remote claimant exceed the amount due by the bonded contractor to the person to whom the remote claimant has supplied labor, materials, rental equipment, or services, unless the remote claimant has provided notice of furnishing labor, materials, or rental equipment to the bonded contractor. Such written notice to the bonded contractor must generally conform to the requirements of Section 29-5-20(B) and sent by certified or registered mail to the bonded contractor at any place the bonded contractor maintains a permanent office for the conduct of its business, or at the current address as shown on the records of the Department of Labor, Licensing and Regulation. After receiving the notice of furnishing labor, materials, or rental equipment, no payment by the bonded contractor shall lessen the amount recoverable by the remote claimant. However, in no event shall the aggregate amount of claims on the payment bond exceed the penal sum of the bond.
No suit under this section shall be commenced after the expiration of one year after the last date of furnishing or providing labor, services, materials, or rental equipment.
For purposes of this section, “bonded contractor” means a contractor or subcontractor furnishing a payment bond, and “remote claimant” means a person having a direct contractual relationship with a subcontractor or supplier of a bonded contractor, but no contractual relationship expressed or implied with the bonded contractor. Any payment bond surety for the bonded contractor must have the same rights and defenses of the bonded contractor as provided in this section.
This section shall apply to any payment bond, whether statutory, public, common law, or private in nature, that is issued in connection with a construction project or other improvements to real property within South Carolina when such payment bonds are not otherwise required or governed by any other applicable section of the South Carolina Code of Laws.
For the purposes of this section:
(1) “Statutory bonds” or “public bonds” means bonds that are either:
(a) provided because required by statute and in accordance with the minimum guidelines set forth in this section; or
(b) contain either express or implied reference to the provisions of this section.
(2) “Common law bonds” or “private bonds” means bonds that are either:
(a) not required by statute, such as a bond voluntarily provided to meet a contractual agreement between parties; or
(b) required by statute but that specifically deviates from the statutory requirements to provide broader protection.