Delaware does not require any construction parties to send a preliminary notice before filing a mechanics lien.
Delaware Mechanics Lien Guide and FAQs
Quicklinks
“Levelset takes something that is pretty complex and makes it easy.”
Ready to file a lien in Delaware?
Not sure? Calculate your deadline for free.
Delaware mechanics lien & notice deadlines for:
For contractors who have a direct contract with a Delaware property owner, the deadline to file a mechanics lien is within 180 days of completion of the project. See the FAQs for more detail on timing requirements.
An action to enforce a mechanics lien in Delaware is incorporated with the lien filing itself, and accordingly, the enforcement deadline for prime or direct contractors is the same 180 days.
Delaware does not require any construction parties to send a preliminary notice before filing a mechanics lien.
Construction parties who do not have a direct contract with the property owner must generally file a mechanics lien in Delaware within 120 days of their last date of furnishing labor or materials. See the FAQs for more detail on timing requirements.
An action to enforce a mechanics lien in Delaware is incorporated with the lien filing itself, and accordingly, the enforcement deadline is the same as the lien filing deadline.
Delaware Mechanics Lien FAQs
Who can file a Delaware mechanics lien?
Delaware law provides mechanics lien rights to any party that supplies:
“labor or material, or both, to an amount exceeding $ 25 in or for the erection, alteration or repair of any structure.” Liens may also be obtained for services or materials provided “in plumbing, gas fitting, paper hanging, paving, placing iron works and machinery of every kind in mills and factories, bridge building, the erection, construction and filling in of wharves, piers and docks and all improvements to land by drainage, dredging, filling in, irrigating and erecting banks and the services rendered and labor performed and materials furnished by architects.”
Rental equipment providers and suppliers to suppliers do not have mechanics lien rights in Delaware.
Also, if the mechanic’s lien rights are based solely on improvement to land, and not a structure thereon, strict requirements apply. In order for such a lien to be valid, “there must be a contract in writing, signed by the owner… setting forth the names of all parties to the contract and containing a description by the metes and bounds of the land to be affected and by a statement of the general character of the work to be done, and of the total amount to be paid thereunder, and the amounts of the partial payments, together with the time when such payments shall be due and payable.”
Is a written contract required to file a mechanics lien in Delaware?
Generally, no, a written contract isn’t required to secure lien rights in Delaware. Delaware lien law specifically states that parties who are entitled to lien rights are those who perform work or furnish materials “in pursuance of any contract, express or implied.”
However, if the improvements are made solely to the land, as opposed to a building or structure, the contract must be in writing.
• Learn more: Can Contractors File a Lien Without a Written Contract?
Can an unlicensed contractor file a Delaware mechanics lien?
Yes. Delaware does not impose any specific licensing requirement in order to file a valid mechanics lien claim. However, it is never a good idea to perform work for which a license is required without having the proper license.
• Learn how to get licensed: Delaware Contractor Licensing Guide
When is the deadline to file a Delaware mechanics lien?
The time period in which a lien claimant must file his Statement of Claim depends on whether the lien claimant has a direct contract with the owner of the property.
Direct contractors:
• The deadline to file is no later than 180 days after the completion of the structure. Although, Delaware law also notes that a Statement of Claim is filed timely if it is filed within 180 days of any of 9 separate dates outlined by 25 Del. C. § 2711(a)(2), some of which may not occur until well after the structure is completed.
All other claimants:
• The deadline to file is no later than 120 days of the date the lien claimant last supplied materials or performed labor. Although, Delaware law also notes that a Statement of Claim is filed timely if it is filed within 120 days of the date final payment is due to the lien claimant (including all retainage), or within 120 days of the date final payment is made to the general contractor who contracted directly with the owner and the lien claimant.
NOTE: Special care should be taken when a potential lien claimant contracts with the tenant of a property. Because that potential lien claimant has not contracted directly with the owner, the 120 day period applies.
What information should be included in a Delaware mechanics lien?
A Delaware lien statement and/or complaint is governed by Del. Code tit. 25 §2712, and must include all of the following information:
• Claimant’s information;
• Owner’s information;
• Hiring party’s information;
• Amount claimed and a copy of the contract (if written);
• Amount claimed to be due on each structure (if applicable);
• First and last dates of furnishing labor and/or materials;
• Property description; &
• Statement that the labor and/or materials were furnished on credit.
Does a Delaware mechanics lien need to include a legal property description?
No. Delaware law only requires a description of the location of the structure being liened “sufficient to identify the same, ” a full legal property description is not required.
Can attorney fees, collection costs, or other amounts be included in the lien amount?
Generally, no. Attorney’s fees and consequential damages are not allowed as part of a lien claim in Delaware. However, if there is an agreement between the parties that attorney’s fees can be recovered, they might be allowed.
• Dive deeper: Mechanics Lien Amounts | What can be included in each state?
Does a Delaware mechanics lien need to be notarized?
Delaware mechanics liens must be accompanied by an affidavit of the lien claimant stating that the information contained therein is true and correct. The affidavit must be verified, but not necessarily notarized. It is not sufficient for this purpose to claim that the information is true and correct “upon information and belief” or “to the best of knowledge.”
Where do I file and record a Delaware mechanics lien?
Delaware mechanics lien claims are documents recorded with the prothonotary office of the superior court. For your mechanics lien to be valid, you must record it in the county where the job is physically located. Delaware counties each have their own unique rules and requirements.
To help you, here are all the offices in Delaware that record mechanics liens: New Castle County, Kent County, and Sussex County.
• Learn more: Essential Questions to Ask The County Recorder Before Filing a Lien
How do I actually file a Delaware mechanics lien?
There are a lot of questions on this page about who can file a Delaware mechanics lien, when it must be filed, what types of rules apply, and more. But you may be wondering something much more practical: how do I actually get my mechanics lien recorded and filed?
• For a full breakdown of the process, you may want to consult: How to File a Delaware Mechanics Lien: A Step-by-Step Guide
Do I need to send notice that the mechanics lien was recorded in Delaware?
Yes. Delaware law requires that notice must be sent when a Statement of Claim is filed. A lien claimant is required to send a Notice to Lien Holders to everyone who holds a lien on the property subject to the action, as well as to any tenants holding a leasehold interest.
This notice must be sent by certified mail return receipt requested. Further, a lien claimant is required to furnish a Writ of Scire Facias. If the lien is on an occupied residence, a copy of the Writ must be left with a person residing in the residence. If the structure is not an occupied residence, the sheriff will affix a copy of the Writ to the door or other front part of the structure.
When is the deadline to enforce a Delaware mechanics lien, or, how long is my lien effective?
In Delaware, the action to enforce the lien is generally incorporated with the filing of the Statement of Claim itself. Due to this, claimants should consult an attorney to help guide them through this process.
Can I collect the entire unpaid amount from the property owner if they already paid the general contractor in full in Delaware?
No, Delaware is considered an “unpaid balance” lien state, meaning that a claimant’s amount is limited to the remaining contract price due to the general contractor at the time the claim is filed.
• Learn more: Full Price v. Unpaid Balance Lien States
Does a Delaware lien have priority over pre-existing mortgages or other construction loans?
No. In Delaware the lien relates back to the later of two dates, either the day when labor first began, or immediately following the time of recording of a first mortgage upon the structure provided at least 50% of the loan proceeds are used for the payment of labor or materials, or both, for the structure. Pre-existing liens have priority over mechanics liens, and any first mortgage from which at least 50% of the loan proceeds financed construction is automatically a pre-existing lien.
• Dive deeper: Lien Priority | What Happens When Everybody Is Trying to Grab a Piece of the Same Pie?
Who cancels the Delaware mechanics lien if/when I get paid?
There is no specific provision in Delaware law that outlines who must cancel a mechanics lien after payment. However, since a mechanics lien in Delaware is generally incorporated with an action to enforce, the court outlines the procedure after the lien is paid.
People are asking Delaware construction attorneys:
Should I file a mechanics lien?
What lawyer do i need?
You should speak with an attorney familiar with construction disputes. They might be able to assist in convincing the contractor to finish the work to your satisfaction. And, they can assist if the contractor files suit.
One word of caution, these disputes can become very expensive very quickly, in terms of legal fees and expenses. You may want to contact the Attorney General’s Consumer Fraud Division as I believe they are setting up a mediation program for disputes such as yours. That might be a less costly way to resolve the dispute, and you might not need an attorney to participate in mediation. It still would be a good idea to meet with an attorney to get prepared for mediation, but having them “in the room” might not be necessary.
Mechanic lien in Delaware
Best rated general contractors in Delaware
Do It Yourself: Steps to file a mechanics lien in Delaware
Read the step-by-step guide
In our step-by-step guide, we will walk you through each step required to qualify for and file a Delaware mechanics lien. This guide explains the information required on the Delaware mechanics lien form, the extra steps required, and essential tips about delivering it to the county office for recording.
Prepare the lien form
Prepare a Statement of Claim according to the information required by Delaware’s statute, along with an affidavit stating that the facts in the claim are “true and correct.”
Record the lien
A Delaware mechanics lien must be recorded with the Prothonotary (i.e. County Clerk) of the Superior Court.
Serve notice
Delaware requires lien claimants to serve a copy of the recorded lien upon the property owner after filing. In addition, the claimant must furnish a writ of scire facias.
After you file
Delaware's Mechanics Lien Statutes
The provisions of the Delaware statutes that permit the filing of mechanics liens and materialmen’s liens can be found at Delaware Code 25 Del.C. § 2701 et. seq. The full text of the Delaware Mechanics Lien Law is provided below. Updated as of May 2023.
§ 2701. Definitions
As used in this chapter, unless the context requires a different meaning.
(1) “Construction management services” includes services performed pursuant to a contract with an owner of a structure, or with the agent of such owner, for the management of the erection, alteration or repair of such structure, where the person or entity providing such services does not perform or furnish labor or material for such erection, alteration or repair.
(2) “Labor” includes work.
(3) “Structure” includes a building or house.
§ 2702. Persons entitled to obtain lien
(a) It shall be lawful for any person having performed or furnished labor or material, or both, to an amount exceeding $25 in or for the erection, alteration or repair of any structure, in pursuance of any contract, express or implied, with the owners of such structure or with the agent of such owner or with any contractor who has contracted for the erection, alteration or repair of the same and for the furnishing of the whole or any part of the materials therefor, including any person who has performed or furnished labor or material, or both, for or at such structure under a contract with or order from any subcontractor to obtain a lien upon such structure and upon the ground upon which the same may be situated or erected.
(b) Liens may also be obtained in connection with: labor performed and materials furnished in plumbing, gas fitting, paper hanging, paving, placing iron works and machinery of every kind in mills and factories, bridge building, the erection, construction and filling in of wharves, piers and docks and all improvements to land by drainage, dredging, filling in, irrigating and erecting banks and the services rendered and labor performed and materials furnished by architects.
§ 2703. Contract requirements to obtain lien based solely on improvement to land
No lien shall attach in case the improvements are to the land alone, unless a contract in writing, signed by the owner or owners thereof, setting forth the names of all parties to the contract and containing a description by the metes and bounds of the land to be affected and by a statement of the general character of the work to be done, and of the total amount to be paid thereunder, and the amounts of the partial payments, together with the time when such payments shall be due and payable.
§ 2704. Liens effective for or against corporations
Liens may be filed for or against corporations or individuals.
§ 2705. Duty of contractor to provide list of persons furnishing labor and material; effect of failure to provide list
The owner of any structure built, repaired or altered by any contractor or subcontractor may require such contractor or subcontractor from time to time to furnish and submit to the owner complete and accurate list in writing of all persons who have furnished labor or material, or both, in connection therewith, and who may be entitled to avail themselves of the provisions of this chapter. Should any such contractor or subcontractor fail to furnish such list for 10 days after demand made therefor by such owner, the contractor or subcontractor shall be entitled to receive no further payments from the owner until such list be furnished and shall not be entitled to avail himself or herself of any of the provisions of this chapter.
§ 2706. Waiver of lien
(a) Persons entitled to avail themselves of the lien provided for in this chapter shall not be considered as waiving the same by granting a credit or receiving notes or other securities, unless the same be received as payment or the lien expressly waived, but the sole effect thereof shall be to prevent such persons from availing themselves of the liens provided for in this chapter until the expiration of the time agreed upon.
(b) Notwithstanding the provisions of any other law, except as provided in this subsection: Any contract, any agreement or understanding whereby the right to file or enforce any lien created under this chapter is waived, shall be void as against public policy and wholly unenforceable. This section shall not preclude a requirement for a written waiver of the right to file a mechanics’ lien executed and delivered by a contractor, subcontractor, material supplier or laborer simultaneously with or after payment for the labor performed or the materials supplied has been made to such contractor, subcontractor, material supplier or laborer nor shall this section be applicable to a written agreement to subordinate, release or satisfy all or part of such lien made after a statement of claim has been filed under this chapter. Nothing in this subsection shall amend, exempt, limit or qualify the provisions of § 2707 of this title.
§ 2707. Payment of contractor by owner of residence as a defense; certification of payment for labor and materials or release of liens by contractor
No lien shall be obtained under this chapter upon the lands, structure, or both, of any owner which is used solely as a residence of said owner when the owner has made either full or final payment to the contractor, in good faith, with whom he contracted for the construction, erection, building, improvement, alteration or repair thereof. Prior to or simultaneous with the receipt of any full or final payment by the contractor, the contractor must provide the owner either:
(1) A notarized, verified written certification that the contractor has paid in full for all labor performed and materials furnished to the date of such full or final payment in or for such construction, erection, building, improvement, alteration or repair or
(2) A written release of mechanics’ liens signed by all persons who would otherwise be entitled to avail themselves of the provisions of this chapter, containing a notarized, verified certification signed by the contractor that all of the persons signing the release constitute all of the persons who have furnished materials and performed labor in and for the construction, erection, building, improvement, alteration and repair to the date of the release and who would be entitled otherwise to file mechanics’ liens claims.
Failure of the contractor to provide the owner a written certification or a release of mechanics’ liens at such time shall constitute sufficient cause for the immediate suspension, revocation or cancellation of the contractor’s occupational and business licenses. If the owner has not made full payment in good faith to such contractor, the lien may be obtained in accordance with this chapter, but it shall be a lien only to the extent of the balance of the payment due such contractor, which balance or portion shall be payable pro rata among the claimants who perfect liens. Payments made to the contractor by the owner after service of process, as provided in § 2715 of this title, shall not be deemed to be “in good faith.”
§ 2708. Fringe benefits
A mechanics’ lien may be used to secure payment of any unpaid amounts due under contract from the contractor arising from a subcontractor’s labor including payment of fringe benefit items. As used in this section, the phrase “fringe benefit items” shall have the same meaning as the phrase “benefits or wage supplements” defined in § 1109(b) of Title 19.
§ 2711. Time for filing of statement of claim
(a)
(1) A contractor who:
a. Has made that contractor’s contract directly with the owner or reputed owner of any structure; and
b. Has furnished both labor and material in and for such structure, or has provided construction management services in connection with the furnishing of such labor and material, in order to avail himself or herself of the benefits of this subchapter, shall file that contractor’s statement of claim within 180 days after the completion of such structure.
(2) For purposes of this subsection, and without limitation, a statement of claim shall be deemed timely if it is filed within 180 days of any of the following:
a. The date of purported completion of all the work called for by the contract as provided by the contract if such date has been agreed to in the contract itself;
b. The date when the statute of limitations commences to run in relation to the particular phase or segment of work performed pursuant to the contract, to which phase or segment of work the statement of claim relates, where such date for such phase or segment has been specifically provided for in the contract itself;
c. The date when the statute of limitations commences to run in relation to the contract itself where such date has been specifically provided for in the contract itself;
d. The date when payment of 90% of the contract price, including the value of any work done pursuant to contract modifications or change orders, has been received by the contractor;
e. The date when the contractor submits that contractor’s own final invoice to the owner or reputed owner of such structure;
f. With respect to a structure for which a certificate of occupancy must be issued, the date when such certificate is issued;
g. The date when the structure has been accepted, as provided in the contract, by the owner or reputed owner;
h. The date when the engineer or architect retained by the owner or reputed owner, or such other representative designated by the owner or reputed owner for this purpose, issues a certificate of completion; or
i. The date when permanent financing for the structure is completed.
(b) All other persons embraced within this chapter and entitled to avail themselves of the liens herein provided shall file a statement of their respective claims within 120 days from the date from the completion of the labor performed or from the last delivery of materials furnished by them respectively. For purposes of this subsection, and without limitation, a statement of claim on behalf of such person shall be deemed timely if it is filed within 120 days of either of the following:
(1) The date final payment, including all retainage, is due to such person; or
(2) The date final payment is made to the contractor:
a. Who has contracted directly with the owner or reputed owner of any structure for the erection, alteration or repair of same; and
b. With whom such person has a contract, express or implied, for the furnishing of labor or materials, or both, in connection with such erection, alteration or repair.
§ 2712. Requirements of complaint or statement of claim
(a) Every person entitled to the benefits conferred by this chapter and desiring to avail himself or herself of the lien provided for in this chapter, shall, within the time specified in this chapter, file a statement of claim, which may also serve as a complaint when so denominated, in the office of the Prothonotary of the Superior Court in and for the county wherein such structure is situated.
(b) The complaint and/or statement of claim shall set forth:
(1) The name of the plaintiff or claimant;
(2) The name of the owner or reputed owner of the structure;
(3) The name of the contractor and whether the contract of the plaintiff-claimant was made with such owner or his agent or with such contractor;
(4) The amount claimed to be due, and, if the amount is not fixed by the contract, a statement of the nature and kind of the labor done or materials furnished with a bill of particulars annexed, showing the kind and amount of labor done or materials furnished or construction management services provided; provided, that if the amount claimed to be due is fixed by the contract, then a true and correct copy of such contract, including all modifications or amendments thereto, shall be annexed;
(5) The time when the doing of the labor or the furnishing of the materials was commenced;
(6) The time when the doing of the labor or the furnishing of the material or the providing of the construction management services was finished, except that:
a. With respect to claims on behalf of contractors covered by § 2711(a) of this title, the date of the completion of the structure, including a specification of the act or event upon which the contractor relies for such date, and
b. With respect to claims on behalf of other persons covered by § 2711(b) of this title, the date of completion of the labor performed or of the last delivery of materials furnished, or both, as the case may be, or a specification of such other act or event upon which such person relies for such date.
(7) The location of the structure with such description as may be sufficient to identify the same;
(8) That the labor was done or the materials were furnished or the construction management services were provided on the credit of the structure;
(9) The amount of plaintiff’s claim (which must be in excess of $25) and that neither this amount nor any part thereof has been paid to plaintiff; and
(10) The amount which plaintiff claims to be due him on each structure.
(11) The time of recording of a first mortgage, or a conveyance in the nature of a first mortgage, upon such structure which is granted to secure an existing indebtedness or future advances provided at least 50% of the loan proceeds are used for the payment of labor or materials, or both, for such structure.
(c) The complaint and/or statement of claim shall be supported by the affidavit of the plaintiff-claimant that the facts therein are true and correct.
§ 2713. Claims against 2 or more structures owned by same person
In every case in which 1 claim for labor or materials is filed by the same person against 2 or more structures owned by the same person for building, altering or repairing 2 or more structures owned by the same person, the claimant shall, at the time of filing such joint claim, designate the amount which the claimant claims to be due to that claimant on each of such structures.
§ 2714. Proceedings by scire facias; form
(a) The proceedings to recover the amount of any claim shall be by writ of scire facias.
(b) The writ of scire facias used under the provisions of this chapter shall be in the form prescribed by the Superior Court.
§ 2715. Issuance and service of scire facias
The writ shall be issued, returnable and served in the same manner as other writs of scire facias upon the defendant therein named, if he can be found within the county. A copy of the writ shall be left with some person residing in the structure to which the labor was done or for which the materials were furnished, if occupied as a place of residence, but if not so occupied, the sheriff shall affix a copy of such writ upon the door or other front part of such structure.
§ 2716. Default judgment; affidavit of defense
Judgment by default may be entered for the plaintiff at such time and in the manner prescribed by the rules of the Superior Court, unless the defendant has previously filed in the cause an affidavit that the defendant verily believes there is a legal defense to the whole or part of such cause of action and setting forth the nature and character of the defense. If the defense is to a part only, then the defendant shall specify the sum really due, and judgment may be entered for the plaintiff at the plaintiff’s own election for the sum acknowledged to be due. If judgment is not so entered by default, then like proceedings shall be had as in other cases of scire facias.
§ 2717. Proof of work done or materials furnished as prima facie evidence of extension of credit on structure
Proof by the claimant that labor or materials, or both, was performed or furnished upon or to any structure, or immediately adjacent thereto, or that construction management services were provided in connection with the performance or furnishing of such labor or materials, shall be prima facie evidence that the same was performed or furnished or provided for and on the credit of such structure.
§ 2718. Lien of judgment
(a) Any judgment obtained under a claim made in accordance with this subchapter shall become a lien upon such structure and upon the ground upon which the same is situated, erected or constructed and shall relate back to the day upon which the labor was begun or the furnishing of material was commenced, or the time immediately following the time of recording of a first mortgage, or a conveyance in the nature of a first mortgage, upon such structure which is granted to secure an existing indebtedness or future advances provided at least 50% of the loan proceeds are used for the payment of labor or materials, or both, for such structure, whichever shall last occur.
(b) In the case of the erection, construction and filling in of wharves, piers and docks and improvements to land, the liens shall extend to the lots or lands in front of which improvements are made.
§ 2719. Execution by levari facias; form
The execution of every judgment under the foregoing provisions shall be by writ of levari facias in the following form:
“………………. . County, ss.:
The State of Delaware.
To the Sheriff of said County, greeting:
We command you that without any other writ from us of the following described building and lot of ground, to wit (describing the same according to the record), in your bailiwick, you cause to be levied as well a certain debt of……….. . which……….. . lately in our Superior Court for the County aforesaid, before the Judges thereof, recovered against……….. . to be levied of the said building and lot of ground, as also the interest thereon from the……….. . day of……….. ., A. D.,……….. . and also the sum of……….. . for the cost which accrued thereon, according to the form and effect of an act of the General Assembly in such cases made and provided, and have you there moneys before our Judges at……….. . at our Superior Court in and for the County of……….. . there to be held on the………… day of……….. . next to render unto the said……….. . for his debt, interest and costs aforesaid, and have you then there this writ.”
Witness (as in similar writs).
§ 2720. Division of proceeds
If the proceeds received from any sale under the writ of levari facias is not sufficient to pay in full all liens, such proceeds shall be ratably divided among the persons who have availed themselves of the provisions of this chapter without priority or preference of 1 over the other.
§ 2721. Savings provision for personal actions
(a) Nothing contained in this subchapter shall be construed to impair or otherwise affect the right of any person to whom any debt may be due for labor done or materials furnished to maintain any personal action against the owner or contractor of such structure to recover the amount of such debt.
(b) Nothing contained in this subchapter shall be construed to impair or otherwise affect the right of any person to whom any debt may be due for labor done or materials furnished in the erection, alteration or repair of any structure, or for any construction management services provided in connection with such labor done or materials furnished, to maintain any personal action against the owner or reputed owner of the structure or against any contractor or against the same and other contracting parties for the same or for any greater or less demand before, concurrently with or after the proceedings for obtaining the lien upon the structure as provided in this chapter, and the judgment whether for the plaintiff or defendant or any of the defendants in such personal action shall in no wise impair, alter or affect the lien or the proceedings or judgment or execution provided for in this chapter.
§ 2722. Lien where labor is done or materials furnished at instance of lessee or tenant
Nothing contained in this subchapter shall be construed to render property liable to liens under this chapter for repairs, alterations or additions, when such property has been altered, added to or repaired by or at the instance of any lessee or tenant without the prior written consent of the owner or his duly authorized agent.
§ 2723. Rights of owner where lien or judgment is obtained by a subcontractor
The owner of any structure built, repaired or altered by any contractor who has contracted to build, erect, alter or repair the same and furnish the materials therefor may, in case any liens are entered under this chapter upon the structure, upon any claim for materials which by the terms of his contract the contractor was bound to furnish, by any person or persons other than such contractor, retain and withhold from such contractor so much of the moneys to be paid to him in pursuance of the contract made with such contractor as may be necessary to liquidate and discharge such liens; and, in case judgment is recovered by such lien creditors, the owner may apply the moneys or such part thereof as may be necessary to satisfy the judgment to the payment and satisfaction thereof. Such payment shall be considered and treated as a payment pro tanto to the contractor towards the moneys provided to be paid by the contractor.
§ 2724. Entries in Mechanics' Lien Docket
The prothonotary in each county of this State shall procure and keep a docket, to be called “The Mechanics’ Lien Docket,” in which the prothonotary shall make an entry of each claim filed, setting down therein the names of the parties, plaintiff and defendant, the amount claimed, the day upon which the claim is filed and of the issuing of the scire facias, a description of the property against which the claim is sought to be charged, amount for which judgment is rendered, the day on which the same is rendered, the party for and against whom it is rendered and, in case of judgment for the plaintiff, the time to which the judgment relates back as a lien and other entries necessary and proper to a full understanding of the case. The time to which the judgment relates back as a lien shall be ascertained in the same manner as the amount of the judgment is ascertained.
§ 2725. Procedure where claimant institutes personal action and also proceeds under this chapter
(a) When the claimant proceeds under this chapter for availing himself or herself of that claimant’s lien and institutes any personal action for the same demand or any part thereof or for a demand of which the amount for which the claimant claims a lien is a part, it shall be no objection in either suit that some of the parties defendant in the 1 suit are not also parties defendant in the other suit. In any such personal action or in the suit to avail himself or herself of the lien, whichever is last docketed, the plaintiff shall file an affidavit setting out the demand in each of the suits and stating to what extent the respective demands are identical. The judgment in either of the actions shall not be pleaded as a bar in the other action.
(b) Whenever any moneys are applied on the judgment on either of the demands pursuant to the execution thereof or pursuant to any other execution proceedings, the Superior Court may order all or any part to be credited on the judgment in the other of the demands according to the equity of the matter as the equity appears to the Court.
§ 2726. Mechanics' lien on ship or vessel; time for filing claim; procedure
This subchapter shall also extend to labor or materials performed or furnished in the construction, alteration, furnishing, rigging, launching or repairing of any ship or vessel within this State. No bill of particulars and affidavit shall be filed more than 1 year after such ship or vessel has been launched, rigged, furnished and ready for sea or after such repairs have been completed and shall contain the name of the ship or vessel or a description thereof sufficient for identification. Upon filing the bill of particulars and affidavit under the provisions of this section, the Prothonotary may issue a writ of attachment, directed to the sheriff of the county in which the ship or vessel may be, commanding the sheriff to attach the defendant by such ship or vessel, together with the tackle, apparel and furniture, wheresoever the same may be found in his bailiwick, so that he appears at the next term of the Superior Court to answer the plaintiff’s demands. The sheriff shall, under such writ, seize and take possession of the ship or vessel and have the same inventoried and appraised and shall be answerable therefor. If the defendant in the attachment at any time before judgment appears and enters into recognizance to the plaintiff in the writ of attachment in a reasonable penalty and with surety to be approved by the Prothonotary with condition to pay the condemnation money and all costs or otherwise abide the judgment of the Superior Court in the case and if he fails to make good his plea, the attachment shall be dissolved, the ship or vessel shall be discharged, and the case shall proceed as in other cases of assumpsit for work and labor or materials furnished.
§ 2727. Auditors; powers and duties; report to Court; exceptions to report
On the return of the writ of attachment or summons the Court may, upon petition of any person claiming to have performed or furnished labor or materials at the request of the plaintiff or plaintiffs in the attachment, appoint 3 suitable persons to audit and determine the claim of the plaintiff and also the claim of the petitioner, who shall adjust and ascertain all the demands, including that of the plaintiff in the writ. The auditors shall severally be sworn or affirmed to perform their duties according to the best of their skill and knowledge. They shall give 10 days’ notice to the parties of the time and place of their first meeting by advertisement, posted at the courthouse door and at least 5 other public places in the county. Their subsequent sittings shall be by adjournment duly made and publicly announced. They may investigate any claim presented in any form they judge best and may examine any of the parties upon oath or affirmation. On receipt of the proceeds of the sale of the property attached or against which judgment is obtained or any part thereof, the auditors shall calculate and settle the proportions and dividends due the several parties and shall make report to the next term of the Court after such appointment and, upon confirmation of the report, pay over to the several parties their respective share of the proceeds according to such appointment. The Court may hear exceptions to and correct such account and report, either in the calculations, dividends, apportionment, or otherwise.
§ 2728. Judgment on attachment; sale and distribution; suit for deficiency; return of surplus; title under sale
If the attachment has not been dissolved, as provided in this subchapter, judgment may be given for the plaintiff in the attachment at the second term after issuing the writ as in other cases of attachment, and thereupon the Court may order that the sheriff shall sell the property attached, on due notice, and pay the proceeds, deducting legal costs and charges, to auditors for distribution. Any balance remaining due from the defendant in the attachment to any of the parties after such distribution of the proceeds may be collected as other debts, and any surplus after paying costs shall be returned to the defendant or the defendant’s executors, administrators or assigns. All sales made under this subchapter shall be good against the defendant, the defendant’s executors, administrators or assigns.
§ 2729. Discharge of lien on payment into Court or entry of security
(a) Cash deposit. — Any claim filed hereunder shall, upon petition of the owner or any party in interest, be discharged as a lien against the property whenever a sum equal to the amount of the claim shall have been deposited with the Court in said proceedings for application to the payment of the amount finally determined to be due. Said petition shall include an affidavit by the owner or party in interest setting forth which parts of the claim filed hereunder are disputed and which parts are not disputed. The nondisputed part of the claim shall be paid to the claimant before the lien against the property is discharged. If it is finally determined by the Court that the disputed portion of the claim has been grossly overstated by the affiant, the Court may, in its discretion, award damages to the claimant against the affiant in an amount up to twice the figure stated by the affiant to be disputed.
(b) Refund of excess. — Any excess of funds paid into Court as aforesaid, over the amount of the claim or claims determined and paid therefrom, shall be refunded to the owner or party depositing same upon application.
(c) Security in lieu of cash. — In lieu of the deposit of any such sum or sums in cash, approved security may be entered in such proceedings in an amount which the Court shall approve, which, however, shall in no event be less than the full amount of such required deposit; and the entry of such security shall entitle the owner to have such liens discharged to the same effect as though the required sums have been deposited in Court as aforesaid.
(d) Authority of Court. — The Court, upon petition filed by any party, and after notice and hearing, may upon cause shown:
(1) Require the increase or decrease of any deposit or security;
(2) Strike off security improperly filed;
(3) Permit the substitution of security and enter an exoneration of security already given.
§ 2731. Lien for less than $100
Any person having performed any labor to any amount less than $100 in or for the erection, alteration or repair of any structure or bridge, in pursuance of any contract, expressed or implied, with the owner or reputed owner of such structure or bridge or with any contractor who has contracted for the erection, alteration or repair of any structure or bridge, or any part thereof, may obtain a lien upon such structure or bridge and upon the ground upon which the same may be situated or erected in the manner provided in this subchapter.
§ 2732. Time for Filing Statement of Claim; Place
No person having done or performed any labor in or about the erection, alteration or repair of any structure or bridge shall be allowed to file any statement of that person’s claim before a justice of the peace until after the expiration of 20 days from the time of the last labor done or performed by that person, but, in order to avail himself or herself of the benefits of this subchapter, the person shall file that person’s claim within 10 days after the expiration of the 20 days aforesaid. Any person entitled to the benefits of this subchapter shall file that person’s claim under oath, within the time above specified, with any justice of the peace of the county wherein such structure or bridge is situated.
§ 2733. Requirements of statement of claim
The statement of claim shall set forth the names of the party claimant, the owner or reputed owner of the structure or bridge, the contractor and the kind of labor done and whether the contract was with the owner or the owner’s agent or with the contractor, the sum claimed to be due, the time when the labor was commenced and finished, the location of such structure or bridge, the ground upon which the same is situated, and a description sufficient to identify the same.
§ 2734. Summons; judgment; transcript
Immediately upon the filing of any claim under this subchapter, the justice of the peace with whom the claim is filed shall issue a summons, as in other civil cases, to the owner and contractor, directed to any constable of the county. The time for the defendant’s appearance shall not be more than 3 days from the date of the summons, and not more than 2 adjournments shall be had and then only from day to day. If the defendant fails to appear at the time appointed or if after a hearing the justice is satisfied of the correctness of the claim, the justice shall give judgment as in other cases and, upon the payment of cost and a demand for the transcript, he shall furnish such transcript.
§ 2735. Entry of transcript and judgment in Superior Court; effect; costs; contractor to give security to owner
The transcript and judgment may be entered in the Superior Court of the county in which the structure is situated and, when so entered, if within 2 days from the date of the judgment, shall become a lien on such structure or bridge and upon the ground upon which the same is erected and shall relate back to the day when the labor was commenced and shall take priority accordingly. Any and all transcripts taken and entered in the Superior Court under this subchapter shall contain a description of the property upon which it is to become a lien and shall conform to the description set forth in the plaintiff’s statement. All costs and charges shall follow the judgment and shall be the same as are authorized by law in civil cases before justices of the peace. Every contractor, when so required, shall give ample security to the owner of any structure being altered, erected or repaired by him to save such owner harmless from the provisions of this subchapter.
§ 2736. Execution by levari facias; form
The execution of every judgment entered in the Superior Court upon transcript under the provisions of this subchapter shall be by writ of levari facias in the following form:
“………………. . County, ss.:
The State of Delaware.
To the Sheriff of said County, Greeting:
We command you that without any other writ from us, of the following described building and lot of ground, to wit (describing the same according to the record) in your bailiwick, you cause to be levied as well a certain debt of……….. ., which……….. . lately before one of the justices of the peace for the County aforesaid recovered against……….. . to be levied of the said building and lot of ground, as also the interest thereon from the……….. . day of……….. . A.D………… ., and also the sum of……….. . for the costs which accrued thereon according to the form and effect of an Act of the General Assembly in such cases made and provided, and have you there the moneys before our Judges at……….. ., at our Superior Court in and for the County of……….. ., there to be held on the……….. . day of……….. . next, to render unto the said……….. . for his debt, interest and costs aforesaid and have you then there this writ.”
Witness (as in similar writs).