Change Orders Questions

All Status
Change Orders
All States
Can retentions be withheld on change orders? ...Read More
Anonymous Contractor
1 answerAdd commentSep 22, 2021
CaliforniaChange OrdersPay Applications
In California once a lien is filed on a property I have 90 days "after" recording the lien to file an action. So I have read it on several legal & law sites. It is my
understanding that the day has 24 hours, typically counted midnight to midnight. It is also my understanding that "after" in the English language ...Read More
...Read More
Robert Dorner
Waiting for answerAdd commentAug 30, 2021
CaliforniaChange OrdersConstruction ContractLawsuitLien ForeclosureLien ReleasesMechanics LienSlow PaymentSubstantial Completion
AFTER LEANING THE PROJECT I RECIVED A NOTICE OF CONTEST OF CLAIM OF LEAN ON THE LIEN LEVEL SET HELPED ME WITH IN REF TO BY THE SEA
RESORT AMPOUNT 122K HOW SHOULD I PROCEED I DIDNT RELIZE I ONLY HAD 60 DAYS WHICH WILL BE UP SEPT 7 2021
...Read More
Anonymous General Contractor
1 answerAdd commentAug 27, 2021
FloridaBack ChargesChange OrdersConstruction ContractRight to Lien
We signed a contract to install doors and hardware. But now they want us to install temporary doors not the originals from the contract. So basically a
change order. But have not received a changer order signed. So no they want us to install the doors as per contract even if they are temporary ones.
...Read More
Anonymous Subcontractor
2 answersAdd commentAug 25, 2021
TexasChange Orders
Hello. I agreed to paint two sides of a house and the home owner made up a contract for the work that I was doing. And after I approved the contract he
decided he wanted to change the colors up. Then preceded to take a small portion of the work off. And now he is trying to change his mind yet a...Read More
...Read More
Anonymous Contractor
Waiting for answerAdd commentAug 23, 2021
FloridaChange Orders
We are a subcontractor on a large industrial project. The last day we were on site was at the end of May 2021, however, we did not receive a final change
order until 08/10/21. We billed the job 100% including retainage when we received the change. I added the end date on the project as 05/30/21 w...Read More
...Read More
Anonymous Subcontractor
3 answersAdd commentAug 18, 2021
FloridaChange OrdersLien DeadlinesNotice of Intent to Lien
We hired a general contractor for a siding job. He is not listed through the BBB. In the original contract it only stipulates the removal and replacement of the
siding, fascia, soffit, gutters and garage door frame. There is nothing listed about change orders. Now he is coming to us with these changes that...Read More
...Read More
Anonymous Contractor
1 answerAdd commentJan 8, 2020
OhioChange Orders
Did not file an intent to file lien when job started just completed job about 3 weeks ago. Job is in Georgia. Appears that the GC did not file the commencement
notice. Do I still have lien rights? also we were supposed to wire a generator as a change order GC ha decided to use a different company for this...Read More
...Read More
mark durham
2 answersAdd commentJul 21, 2021
GeorgiaChange Orders
I hired a GC who specialized in repairing fire damage homes. The original scope of the job was to fix a drainage pipe under the concrete slab. Since then the
kitchen had to be torn out and tile floors removed etc... since there was going to be a delay on cabinets i asked if they could work ln the bathroo...Read More
...Read More
Anonymous Contractor
Waiting for answerAdd commentJul 21, 2021
CaliforniaChange OrdersConstruction ContractNotice of Termination
After sending the intent to lien for the 2000. 2000 is a discounted price to what the client owes. We were in process of a change order when customer was
agreeing in person only to renegotiate terms and accuse us of over charging her. The client has not paid even after receiving the intent to lien. H...Read More
...Read More
Anonymous General Contractor
1 answerAdd commentJul 3, 2021
MassachusettsChange OrdersConstruction ContractLien WaiversMechanics LienPay Applications
We have job where we filed a mechanics lien on June 1st , our 90 day deadline. Just today, we received a change order for additional billable work to be done
in the next month or so. How do I handle the current lien and preserve our right to file a lien again if we are not paid in full 90 days after comple...Read More
...Read More
Anonymous Subcontractor
2 answersAdd commentJun 28, 2021
FloridaChange OrdersLien DeadlinesLien ReleasesRight to Lien
I'm a GC on a small addition. The framing sub made some errors based on a failure to properly read the plans r take field measurements. After completing
the corrections he then issued a change order which was not approved. After explaining that these were his mistakes to correct and in any even...Read More
...Read More
Anonymous General Contractor
Waiting for answerAdd commentJun 21, 2021
CaliforniaChange OrdersPreliminary Notice
After a Change Order has been agreed, if it is later found that there were errors in its preparation (incorrect exchange rate applied, for example) or
impropriety on the part of the contractor in overstating the resources employed, or even discovering that the work the contractor is claiming as ...Read More
...Read More
Anonymous Contractor
Waiting for answerAdd commentJun 12, 2021
HawaiiChange Orders
I’m a sub contractor that hasn’t been paid for change orders or last contract payment. As soon as we requested payment For change orders the GC
requested us to leave the site before finished. Do we request payment for the full contract amount and change orders?
...Read More
Anonymous Subcontractor
Waiting for answerAdd commentJun 7, 2021
OregonChange OrdersConstruction Contract