AFTER LEANING THE PROJECT I RECIVED A NOTICE OF CONTEST OF CLAIM OF LEAN ON THE LIEN LEVEL SET HELPED ME WITH IN REF TO BY THE SEA RESORT AMPOUNT 122K HOW SHOULD I PROCEED I DIDNT RELIZE I ONLY HAD 60 DAYS WHICH WILL BE UP SEPT 7 2021

1 reply

Aug 27, 2021
If you do not file suit on or before the 60th day your lien will expire and nothing can be done to extend it. See a lawyer right away.