Im a tile subcontractor for a larger corp we have not worked for them over 12 months at this point. We are told after 12 months they will release our escrow
ck that was 3/29/19 so technically due today .I just want to know the legality in what they owe as far as interest for last 12 months plus what the l...Read More
...Read More
Anonymous Contractor
1 answerAdd commentApr 3, 2020
New YorkBack ChargesRecovery OptionsRetainage
I am working for a unlicensed contractor who I thought at the time I started was licensed since he gave me a card with company name on it so I can
purchase material. I haven't been paid in over 3 weeks and am getting behind on bills.I have no idea what to do and I have documented every ho...Read More
...Read More
Anonymous Contractor
1 answerAdd commentMar 23, 2020
CaliforniaBack Charges
Hi there, When a subcontractor provides some Goods to the main contractor, can the subcontractor still use the terminology as "back charge" or is there any
other? Thank you
...Read More
Anonymous Contractor
1 answerAdd commentMar 17, 2020
ArkansasBack ChargesChange Orders
We provided landscaping services for a customer that did not pay. Can we file a lien on property...Read More
Anonymous Contractor
1 answerAdd commentMar 10, 2020
NevadaBack Charges
We’ve been working with a painter and agreed to pay him $6500 to paint the interior of our home. The night prior to him finishing up the project he sends
over a handwritten list of “back charges” for $7,000. Keep in mind the entire project was supposed to cost $6500- so this new charge took the int...Read More
...Read More
Anonymous Contractor
1 answerAdd commentMar 10, 2020
KentuckyBack ChargesChange OrdersConstruction ContractMechanics LienPayment Disputes
We’ve been working with a painter and agreed to pay him $6500 to paint the interior of our home. The night prior to him finishing up the project he sends
over a handwritten list of “back charges” for $7,000. Keep in mind the entire project was supposed to cost $6500- so this new charge took the int...Read More
...Read More
Anonymous Contractor
1 answerAdd commentMar 10, 2020
KentuckyBack ChargesChange OrdersConstruction ContractMechanics LienPayment Disputes
so for a while now the contractor has been changing my invoices with no explanation they never gave me a price sheet to follow or go by. nor have they ever
had me sign a contract. every job is different so pricing fluctuates but I never have over charged. but how would I know if I over charged if there ...Read More
...Read More
Anonymous Contractor
1 answerAdd commentMar 9, 2020
VirginiaBack ChargesConstruction Contract
We are a GC licensed to do work in Washington State, Oregon,Idaho, Texas, Arizona & California. This situation applies mostly to our Washington State &
Oregon jobs and subcontractors we have had perform work on jobs in those states. As of the last week or 2 we have received a considerable a...Read More
...Read More
Anonymous Contractor
1 answerAdd commentMar 5, 2020
WashingtonBack ChargesConstruction Accounting
It is the practice of many GC's to back charge the same amount to multiple subs. We perform new construction cleaning of multi-family apartments. We
generally are requested to re-clean an area, a building, or an apartment through a change order. For example, the change order to complete th...Read More
...Read More
Anonymous Contractor
1 answerAdd commentMar 3, 2020
GeorgiaBack ChargesConstruction Accounting
Good Afternoon, I have a few questions: We are a landscape company and our clients are Apartment Communities. All our clients are under a written
contract for monthly service. Under the documents, which notice can i send for past due and unpaid balances from our clients. We service Dallas...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentMar 6, 2020
TexasBack ChargesCollections
I'm a contractor and I paid other contractor in full 11/5/2019 and he asking for more money. Even he don't do a work what he asking money for. Can he put a
lien on property? We never have any contracts between us.
...Read More
Anonymous Contractor
Waiting for answerAdd commentMar 6, 2020
FloridaBack Charges
GC has had extensive delays on job. I’m a framing contractor (rough framing) my contract includes installation of siding and providing the material. Framing
started in August of 2018 and didn’t complete until August of 2019 due to design changes, foundations not poured on a guest house and other G...Read More
...Read More
Anonymous Contractor
1 answerAdd commentFeb 27, 2020
CaliforniaBack ChargesConstruction ContractPayment Disputes
Ref.: to a property for which Bruce Allan Drezner was the sole beneficiary of the Ruth Drezner Living Trust, owner of the property at 348 Fairway Circle,
Weston, FL 33326 The property was in unhealthy and in an unsellable condition. Back in 30th of January 2015, Jack Beckerman, a Builder, agree...Read More
...Read More
Anonymous Contractor
1 answerAdd commentFeb 25, 2020
FloridaBack Charges
We did renovations for an apartment complex for 3 years. We tried to raise prices last year, so they found someone cheaper. We did not have a contract,
but renovated over 200 units. I sent them an invoice for materials on cancelled units, and complex specific materials ordered for this job. The ...Read More
...Read More
Anonymous Contractor
1 answerAdd commentFeb 24, 2020
CaliforniaBack ChargesCollectionsConstruction Contract
We are working out credits to a contract with a sub, they are threatening to lien the project. I do not have a copy of a notice of furnishing. They finished
contract work in Nov. and were on the jobsite a couple of weeks ago performing warranty work. Do they have any rights to lien?
...Read More
Anonymous General Contractor
1 answerAdd commentFeb 20, 2020
MichiganBack ChargesLien Deadlines