GC has had extensive delays on job. I’m a framing contractor (rough framing) my contract includes installation of siding and providing the material. Framing started in August of 2018 and didn’t complete until August of 2019 due to design changes, foundations not poured on a guest house and other GC delays. Siding material was changed by GC from plans and specifications at beginning of framing and to date GC has not decided on material to use and is holding contract money including retainage. What recourse do I have if any due to the GC delays. Also he is now threatening me with back charges for straight edging the walls which I have done twice since I completed framing because it has sat unfinished by GC. Contractor has not covered exposed wood framing in the 6 months since I finished. Wood shrinks and twists if not properly covered which I have pointed out...at any rate I believe GC is not going to pay and refuses to provide the information to complete my contract work.