Thank you for answering my previous question. Does that train of thought that you detailed also apply to other states, such as Texas? What about Puerto Rico? Thanks Again...Read More
We have a project that began in December of 2018 and just finished on the 12th of this month that we have retainage on. We are the sub and did the fire sprinkler install. What would be the best document to send on this project? ...Read More
We are a supplier right now, but will also be a subcontractor in Texas soon. I am getting pushback from our sales group on filing preliens in Texas. They don't like having the contract amount on the initial notice. I want to make sure we retain our lien rights. My questions are Do we have to send the initi...Read More...Read More
Can a Texas Preliminary Notice be sent even prior to being onsite…basically anytime after the contract is signed? If you have a very short duration project, let’s say it’s a one or two day project, do you still have until the 15th of the second month after your first day onsite to send the Preliminary Notice?...Read More
Commercial Mechanics Lien - last day labor performed was in Oct.2018 but we did not invoice until Dec.2018 - what date are we working from to schedule notices etc.?...Read More
We have a project with a single contract and a single invoice for work we are doing on a few different lots. Would we only need to send one monthly notice for this since theres only one contract/invoice? Or would we need to send separate monthly notices for each property even though it's for the same invoice?...Read More
I am a GC with a contract in hand with HO. The project was done through an insurance company and funds were already released to homeowner but the company was not paid, with the exception of the deductible plus $2000 after finishing the job. We need to perfect the lien and the chain of notice...Read More...Read More
Im a subcontractor on a state project. We were working directly with the prime contractor. The project is installing signal lights at 9 locations. At the project onset, there were no addresses assigned to the locations. Part of the work we haven’t been paid for was acquiring those addresses. What addres...Read More...Read More
We need to begin moving forward on a claim on a payment bond in the state of Texas. We are a sub-contractor hired by the prime contractor. The project was federally funded but the property/land was (I believe) state owned. The state of Texas is named on the bond, so I assume we are using state ...Read More...Read More
Hi there, We are a supplier of construction products. I sent a separate question re: a lien in Florida. We have almost identical situations happening in these states. We were to supply a residential project in Texas, the subcontractor sent us a PO, confirmed our order, we made the material, sent one tr...Read More...Read More
We have projects that contain multiple job sites at times. Now I know if there are multiple job sites that means you need to track separately because you have to send a notice for each site address to preserve lien rights. For instance if we had 1 project and under it 5 jobs that had different job side ...Read More...Read More
Subcontractor send POs to our rep. Rep then sends us a PO. We send quote to rep and they mark it up and invoice the subcontractor. They receive payment from the subcontractor....Read More