Im a subcontractor on a state project. We were working directly with the prime contractor. The project is installing signal lights at 9 locations. At the project onset, there were no addresses assigned to the locations. Part of the work we haven’t been paid for was acquiring those addresses. What address should be listed on our notices regarding bond claims? Do we need to put “see attached” in the space provided & attach a list of all of the newly acquired addresses or is there a more appropriate way to deal with this issue? Also would like clarification/confirmation that a sub contracted with the prime on a Texas state project only needs to file a 3 month notice by the 15th of the 3rd month like it says on your website. An answer to my previous question said 2 month, but that conflicts with the info on your site as well as other info I’ve received. Thanks so much!