We have a project that began in December of 2018 and just finished on the 12th of this month that we have retainage on. We are the sub and did the fire sprinkler install. What would be the best document to send on this project?
Accordingly, if there is money due for work performed or labor furnished in the previous months 2 or 3 months, a "monthly" or "fund-trapping" notice should be sent to retain lien rights.
“not later than the earlier of:
(1) the 30th day after the date the claimant’s agreement providing for retainage is completed, terminated, or abandoned; or
(2) the 30th day after the date the original contract is terminated or abandoned.