I am a home owner in Indiana. I have signed a contingency contract with roofing company. Roofing company never return signed contract back to me and they helped to process the claim with an insurance company. Insurance company not approved 100% estimate provided by roofing company. Th...Read More...Read More
Hello I am having a home built by a developer in Monroe county. I will have no involvement with the developers sub contractors nor make any direct or joint payments to them. Since I am not involved with the subs at any level do the subs have any legal rights to file a lien against the property after we ...Read More...Read More
Hi, i worked for 2/3 years at this place installing perfect epoxy floor/wall systems. every job they gave me i gave great deals with the highest of quality possible. They had a very large project that they could not find any one capable of doing after 4 years of searching. I was there and i told them...Read More...Read More
I hired a contractor to put in two basements for me. There is no contract but he gave me a bid of around $66k on one basement and $43k on the 2nd one. He was to have the work done in approximately 3 to 4 weeks. He had multiple no-shows and 1/2 days and etc. so we are into week 9 plus. He sen...Read More...Read More
I was a renter to the home I am living in now. But come to find out the person who gave me an my wife a fake contract. Say she was the home owner. We was buying the home on land contract. We gave $5,000 down. The home was not liveable at all. We put another $13,000 in to it with than a 2 ...Read More...Read More
What happens after 1 year if they never pay ? IS a lien actually worth the time and money WE have to pay on top of not being paid, if it only lasts 1 year? What if they don't sell their house? We just continue to go unpaid, and on top of that now we've paid for the lien as well. ...Read More
The state of Indiana. I provided architectural services to a contractor for work at a residential home. The contractor paid me my $1,000 retainer. This project started in August of 2021. I provide preliminary sketches to the contractor. After modifications, we made final drawings which were provided to t...Read More...Read More
A contractor hired to perform tile work did an extremely poor job. The tiles are not installed correctly and look like garbage. And they didn’t complete all the work that they were hired to do. We got fed up and told them to leave the job. They sent an invoice for the total amount due if they completed th...Read More...Read More
Contractor wants me to sign a lien waver in order to get a check for payment for labor and materials on a job we have not been paid for yet. Will not give me the check until I sign the lien waver....Read More
My contractor left jobs undone, done poorly, damaged property in my home, and rarely quoted the cost of a job. I paid him immediately each time he produced an invoice. When he presented the last invoice, I did not pay it. He has now said he will be filing a lien on my home. How should I proceed?...Read More
I know this is municipality based, but if I plan to start a masonry restoration company on residential/possibly some commercial jobs, would I need a license?...Read More
The roof was replaced through an insurance claim on a home we're buying. We are supposed to close on the home this week but it has been disclosed that the insurance hasn't fully paid for the roof yet and we know the seller is financially broke. The insurance check will be going to the seller. If the se...Read More...Read More
We have submitted a pencil bill (preliminary bill) to the customer for approval. This is our step to gain agreement from the customer before posting the actual bill in our ERP. The GC has not been very responsive in their approval causing a delay in billing and ultimately causing delay in payment. Ca...Read More...Read More
Please recommend some Indiana attorney's that can assist with this public project. We are in a contract / scope of work dispute with the GC and the situation is escalating fast. Thank you!...Read More