I have an official AIA contract signed with the LLC entity and we designed a commercial building... but now near the building's completion the building has been sold according to the county recorder on 12-21-2018. A call to the general contractor reveals the closing will be early next week....Read More
My girlfriend took her car to one of her friend's house to get some work done on it they didn't sign a written agreement next thing you know he says it's 2,000 more than what it was nice trying to get a lien on it...Read More
The contractor company did not complete the project in the right way and even did not finish the job,but i received the notice of lien.What should i do ?...Read More
I am filling out this form and am not sure if on the second page is where the owner of the company who is going to file the lien signs as the Agent of Claimant or if it has to be a third party....Read More
Since I first entered a project in zlien, boundary line modifications have been done that changed some of the APN numbers. We have a recorded lien on the old APN's, do we need to do anything since the APN's have changed?...Read More
A mechanics lien was filed on a commercial property, now the property owner is requesting a copy of the contract agreement between our company (Architectural & Civil Engineering Firm) and the General Contractor (our client). Legally what documentation are we required to provide the prop...Read More...Read More
I was told they were going through a change of C.E.O. and this would be resolved and then they money would be paid. I was told this several times over the past Three weeks, but I have a lot of trouble contacting them to get updates....Read More
Roofer messed up the painter's finished work(paid and gone). I informed the roofer and I held back $200 till the paint was repaired. Roofer said it was cosmetic and did nothing but lien me! Lien says...Contract amount: $3,180...payments of $3,004 Amount of lien after offsets and payments $200...Read More...Read More
When sending out prelien notices, is it okay if I sign as the Claimant as I'm in charge of collecting monies owed. Or does the President of our company need to be the signature on the prelien notice?...Read More
We have several GC's who delay payment, or say they won't pay Retention until the project is complete. Our part of the job is done months before the project is complete due to the nature our our work. Do our lien rights stay in place until the project is complete? (Nevada)...Read More
We are seeking clarification of when lien rights are lost in Nevada. 90 days after we worked on the site or 90 days after the last invoice date. ...Read More
Our prime contractor filed a lien against our property for monies owed for work done on the property. There are so many issues, errors and failures to comply with statutory requirements with filing a mechanics lien that there is just no way the lien could b found valid after challenging it. Because...Read More...Read More
I am a subcontractor to a company working for a GC at a State owned property in Nevada. Do I have lien rights? If so, what form do I use and who do i send them to?...Read More