I want to know what the minimum is for lien waivers. Do I legally have to use all 4? Conditional progress, unconditional progress, conditional final and unconditional final? I want us to be covered but don't want any unnecessary work :)...Read More
Anonymous General Contractor
1 answerAdd commentOct 14, 2022
Nevada
We have a contract with a gc on a private commercial building. I am having trouble collecting information on the owner to file our preliminary notice but our contract mentions a bond (I also have not been given information on the bond company) do I still need to file a preliminary notice? How do I go about getting the information I need? What if they don't give me the information within the 20 days of starting work?...Read More
Anonymous Contractor
1 answerAdd commentJul 23, 2018
NevadaBonding Off LienMechanics LienPreliminary Notice
Hi There, We would like to be able to download your online forms in our account. Is there a way to save this under our documents or templates file? ...Read More
Anonymous Subcontractor
1 answerAdd commentMar 19, 2020
Nevada
I was working in the ac company and when i was olmost finish the job i no recieve a payment and i buy somematerial but the contractor that i work he no claim the money for a general so im in the air can i claim togeneral...Read More
Anonymous Contractor
1 answerAdd commentSep 9, 2017
NevadaMechanics LienPayment DisputesRecovery Options
a general contractor on a private project owes our company $60,000 from may 2022. They are in a lawsuit with the owner. We filed a lein, what else can we do to get payment?...Read More
Anonymous Subcontractor
Waiting for answerAdd commentJan 30, 2023
NevadaPrompt PaymentSlow Payment
I'm a contractor, we had issues with a job so we ended up filing a lien and the the owners took us to the Contractors board, so we do have to fix the issues in the shower(tile) but do we keep the lien on the property or do we remove it and see if they pay us after we fix the issues?...Read More
Susan Rodriguez
3 answersAdd commentJan 24, 2023
Nevada
Hello, Have a customer where 31 day intent to liens were mailed with only the Subcontractor information, do I still have lien rights? Customer has not paid their bill and they are approaching the 90 day deadline from last shipment date. ...Read More
Anonymous Material Supplier
2 answersAdd commentJan 23, 2023
NevadaMechanics Lien
Filed a lien through Levelset though it didn't get recorded until Nov. 8th and the property was sold to a new buyer on October 24th. New buyer doesn't want to pay it. Can we enforce it with the new buyer?...Read More
Anonymous Subcontractor
1 answerAdd commentJan 25, 2023
Nevada
i have not been paid from my last 3 invoices sent on Nov. 1st. 2020...Read More
Anonymous Subcontractor
Waiting for answerAdd commentJan 25, 2023
NevadaMechanics Lien
We were selected to be on a reality renovation show in Nevada and after reveal discovered they used cheap materials, completed horrible work, and caught their workers stealing on camera, visiting the home after hours with their family, smoking in home, and discovered work on the SOW was not completed. We paid almost $200K upfront and now they are disputing what they will repair/fix as part of the punch list. Please help!...Read More
Anonymous Contractor
1 answerAdd commentJan 23, 2023
NevadaConstruction Contract
We are doing geological surveys and we need to monitor a certain radius. This can only be done from the air or by aircraft. But it is too expensive to rent a helicopter and it would be more difficult to fly there....Read More
Karl Williams
2 answersAdd commentJan 15, 2023
NevadaProfessional Development
We filed for a notice of intent to be sent as well as a lien, but they sent them out of sequence. The lien has been sent to the recorder and the notice of intent has yet to be sent to the customer. If I understand correctly, it is mandatory that the notice of intent is received first....Read More
Nicholas Tilley
1 answerAdd commentDec 20, 2022
NevadaMechanics Lien
I work for a contractor and we finished a job and the guy will not pay so i filed a lien what do i do next?...Read More
Anonymous General Contractor
1 answerAdd commentDec 14, 2022
Nevada
Hi Alex I read your very helpful guidance on Mechanics Lien on the Levelset website and would like your help if we go ahead but first I have a question on eligibility. We supplied lights to the value of $700,000 to a company in Las Vegas. The company has paid half the purchase price but is trying to delay payment of the remaining $350,000. The lights will be installed in the event space of one of the big hotels on the strip but at the moment they are in our client's warehouse. Here's the question: our client will lease the lights to the hotel on a long lease so the hotel will not own them. Can we claim that these lights constitute a permanent improvement to the hotel and register a lien on them? Best wishes Joe Ruston Director Remote Controlled Lighting Ltd London, UK...Read More
Anonymous Contractor
2 answersAdd commentSep 3, 2020
NevadaMechanics Lien
Consulted with a new nightclub at the Rio casino Las Vegas and myself and all of my subcontractors have not been paid. Final invoice was delivered oct 27....Read More
Anonymous Contractor
2 answersAdd commentNov 15, 2018
NevadaRight to Lien