I was helping my uncle who is the home owner with an agreement that if I remodeled the barn house he would pay me for my time and material I work and played for
The state of Nevada does not require a written contract in order to file a mechanics lien. Furthermore, there is typically a preliminary notice requirementto secure lien rights. But, if the claimant was hired directly by the owner, then a preliminary notice is not needed.
A Nevada mechanics lien needs to be filed within 90 days of either completion of the project, or the last date of furnishing labor or materials to the project; whichever is later. However, if the owner files a Notice of Completion, then the claimant will only have 40 days from the filing of the notice to file their mechanics lien claim.
For more information: How to File a Nevada Mechanics Lien
NOTE. The information presented here is for informational purposes only. It is not legal advice and should not be construed nor relied upon as such. Furthermore, this posting does not create an attorney-client relationship. If you need legal advice, seek the counsel of a licensed, local attorney.See More...See More...