North Dakota Preliminary Notice Guide and FAQs

Ready? Build Your Free North Dakota
Preliminary Notice Now

Send A Notice Now
North Dakota Preliminary Notice FAQs

About North Dakota Preliminary 20-Day Notices

North Dakota Preliminary Notice Rules
At a Glance


  • Private Jobs
  • Public Jobs
  • Top Links
Icon_Form_Required
Notices Are Required

Notice is not required at the beginning of work, but generally a notice must be provided prior to claiming a lien. Additionally, a separate notice may be both beneficial or required to claim a unique type of mechanics lien.


10
DAYS
Best Practice to Send Notice

It is unclear whether direct contractors must provide a pre-lien notice of intent. While it appears that GCs are not technically required to provide the notice, it may be beneficial to do so anyway.


10
DAYS
Subcontractors Must Send Notice

Parties without a contract with the property owner are clearly and specifically required to provide a notice at least 10 days prior to filing a lien claim in North Dakota.


10
DAYS
Suppliers Must Send Notice

Parties without a contract with the property owner are clearly and specifically required to provide a notice at least 10 days prior to filing a lien claim in North Dakota.


icon-can
Notice Can be Sent Late

The required pre-lien notice in North Dakota may be filed after the 80-day deadline (10 days prior to the 90-day deadline in which to claim a lien) but a claimant must wait at least 10 days before filing the lien claim. Filing a lien late in North Dakota does not invalidate the lien, but does have an effect on the lien's priority.

The other notices are not required, so cannot be sent late. However, if the optional notice for a lien on solely the structure is not delivered to the owner at the time of delivering materials, the lien claimant is not allowed to claim only that particular type of lien.


Icon_SearchContractor
Send to Owner

All preliminary notices in North Dakota only need to be provided to the property owner.

Preliminary notice not required in WV
Preliminary Notice Not Required

North Dakota does not impose any preliminary notice requirements for parties furnishing labor or materials to a public project in order to retain the ability to make a claim agains the payment bond secured for the project. It is generally a good idea, however, to provide preliminary notice even when not required to promote project visibility, open channels for communication, and streamline payment.


X
N/A

On public jobs, any claims for non-payment are made against the general contractor's bond. Since GCs will not make a claim against their own bond for non-payment, they do not have bond claim rights, and have no preliminary notice requirement.


X
Notice Not Required from Subs

North Dakota does not impose any preliminary notice requirements for parties furnishing labor or materials to a public project in order to retain the ability to make a claim agains the payment bond secured for the project. It is generally a good idea, however, to provide preliminary notice even when not required to promote project visibility, open channels for communication, and streamline payment.


X
Notice Not Required from Suppliers

North Dakota does not impose any preliminary notice requirements for parties furnishing labor or materials to a public project in order to retain the ability to make a claim agains the payment bond secured for the project. It is generally a good idea, however, to provide preliminary notice even when not required to promote project visibility, open channels for communication, and streamline payment.

North Dakota has interesting preliminary notice requirements and possibilities. While notice prior to claiming a lien in North Dakota is required, there are also multiple non-required but impactful preliminary notices that may be sent on certain projects.

The specific required pre-lien notice in North Dakota is set forth by North Dakota’s construction Lien Law § 35-27-02, and is more akin to a notice of intent than a traditional preliminary notice. That section states that any person performing work or furnishing labor pursuant to “a contract with any agent, trustee, contractor, or subcontractor of the owner” must provide written notice that a lien will be claimed by certified mail at least 10 days prior to recording the lien. It appears that this requirement only extends to parties other than those who contract directly with the GC, but this appearance is based on paragraph formatting and not completely specific and clear text. Accordingly, it may be best practice for a direct contractor to provide the notice, as well.

North Dakota law also contemplates a couple optional notices that may be provided to the owner by a potential lien claimant other than a primary contractor. While not required, and not influential on the ability of a claimant to file a general mechanics lien, if the need arises, the optional notices do have actual tangible impacts on a project participant’s rights. Depending on the type of optional notice provided, there are two distinct potential benefits.

The first optional notice, provides notification to the owner to (potentially) withhold funds from the GC and pay the noticing party directly. North Dakota law states that “[a]ny such person having a lien under the contractor in accordance with section 35-27-02 may serve upon the owner at any time a notice of that person’s claim.” For the purposes of identifying the claim amount the owner may withhold from the GC. The wording of the statute is a bit confusing, however, as it is unclear whether this is a notice divorced from the lien or only a notice of a specific lien claim already made. It appears that this is a separate notice and can be provided to give information regarding the amount due if the participant has a lien right even if unperfected, however.

The second potential optional notice relates to an interesting aspect of North Dakota lien law. It is possible, in North Dakota, for a laborer or material supplier to claim a lien on only a structure (without affecting the underlying property) provided that the project is the construction of a complete, independent, and original new structure. In order to claim this type of lien, a specific optional notice must be provided to the property owner.

Preliminary Notice Frequently Asked Questions

Sending preliminary notice in North Dakota can be tricky, so it's important to get all the details right. Understanding what notice is required, when to send it, and what effect it may have are complex questions. And, if you're receiving prelims, it's important to know what you're looking at and know what to do in followup. This can be a difficult and tedious process for everyone involved. Here are some frequently asked questions (and answers) about the North Dakota preliminary notice process.

Prelim FAQs on Private Projects

Do I Need to Send a North Dakota Preliminary Notice?

Yes. North Dakota imposes mandatory notice requirements for a valid mechanics lien claim, as well as providing for optional notices that may be provided to the owner by a potential lien claimant other than a primary contractor.

An optional notice may be provided to the property owner by a potential lien claimant other than a prime contractor for two purposes, and in two situations. The first potential reason is to give notice to the owner to withhold funds from the prime contractor in an amount necessary to cover the claimant’s lien, and to pay them directly.

The second potential reason is to retain the ability to claim a lien against solely the structure separate from the underlying property. It is possible for a laborer or material supplier to claim a lien on only a structure (without affecting the underlying property) provided that the project is the construction of a complete, independent, and original new structure. In order to claim this type of lien, a specific optional notice must be provided to the property owner.

When do I Need to Send a North Dakota Preliminary Notice?

The optional preliminary notice for lien on both land and structure may be provided at any time prior to the lien itself (perhaps prior to the mandatory notices, as well.)

The optional preliminary notice for lien on solely the structure must be received by the owner at the time of delivery of the materials.

The mandatory notice prior to filing a lien must be served on the property owner at least 10 days prior to the lien claimant recording the lien. This means that for a timely lien claim, the notice must be provided no later than 80 days after the date of last furnishing of labor and/or materials.

What if I Send the North Dakota Preliminary Notice Late?

The optional notices are not required to be filed, so they cannot technically be filed late. Further, the optional notice for a lien on both the land and structure may be given at any time prior to the filing of the lien.

If the optional notice for a lien on solely the structure is not delivered to the owner at the time of delivering materials, the lien claimant is not allowed to claim only that particular type of lien.

How Should the North Dakota Preliminary Notice be Sent?

The optional notices to owner must be “served” or “delivered” to the owner. This requirement is likely best met by sending the notice to the owner by certified mail, or certified mail, return receipt requested. However, since these notices are not required, any type of delivery is sufficient if actually delivered to the owner; sending by a method that allows delivery tracking provides this information.

The mandatory notice to owner prior to filing the lien (“Notice of Intent to Lien”) must be sent to the property owner by certified mail. Sending by certified mail, return receipt requested, should also satisfy this requirement if the lien claimant wishes.

Do I Have to Send the North Dakota Preliminary Notice to Someone Other than the Owner?

No. All notices in North Dakota are only required to be sent to the property owner – no other notices are required to be sent.

Is the North Dakota Preliminary Notice Requirement met when sent or delivered?

Notices of Intent to Lien are considered delivered when mailed by certified mail. It is unclear whether the mailing of the optional notices meets the requirements for service or delivery if not actually received.

Prelim FAQs on Public Projects

Do I Need to Send a North Dakota Preliminary Notice?

No. North Dakota does not require preliminary notice to be sent to preserve the right to make a claim on the contractor’s bond on a public project if the claimant is otherwise entitled to make a bond claim. However, any party may send notice if they so desire.

When do I Need to Send a North Dakota Preliminary Notice?

N/A

What if I Send the North Dakota Preliminary Notice Late?

N/A

How Should the North Dakota Preliminary Notice be Sent?

N/A

To Whom Must the North Dakota Preliminary Notice be Given?

N/A

Need More Help with North Dakota Preliminary Notices or Construction Payment?

Ask an Expert for Free

Check Out Our Payment Experts

Recent Questions & Answers
About North Dakota Notices and Payment Issues

Is it legal (or enforceable) for a customer to ask us to waive our lien rights in North Dakota?

We are reviewing a contract with a customer in ND. The contract says we waive our right to lien. I've heard this is illegal in...

What should i do?

Hi, I am in the process of selling my home. An ex employer from 6 yrs ago just popped up claiming that I owe him...

Lien Deadlines failure to provide notice

I ordered a lien through Levelset and was very pleased that the lien was filed within the 90 day deadline of the last day of...

How to file a lien in North Dakota

Need to file a North Dakota mechanics lien? File your mechanics lien with Levelset, the lien experts quickly and easily. Or you can follow the 3 steps below to file a lien yourself with Levelset's free information.
File with the Mechanics Lien Experts
We’re the Mechanics Lien experts. With us it’s fast, easy, affordable, and done right!
File Now

North Dakota Preliminary Notice Form Template

The North Dakota preliminary notice forms are subject to some statutory regulation. While the information or formal requirements for the North Dakota notice templates aren’t as strict or comprehensive as they are in some other states, that doesn’t mean that any notice will work in any situation. The forms provided here for free by Levelset are compliant with the North Dakota rules, and drafted to be effective and helpful. You can download them for free, or use our system to send or request them easily.

Helping Thousands of Contractors Like You
With North Dakota Preliminary Notices