Texas Mechanics Lien Questions

All Status
Mechanics Lien
Texas
I had a house built and my builder hired someone to build the fence. We signed an agreement that I would pay the builder after closing on the home based
on the estimate he provided. He wouldn't send a copy of the invoice or receipt of the job. I found out the contractor he said did the work, actually...Read More
...Read More
Anonymous Contractor
1 answerAdd commentApr 3, 2018
TexasConstruction ContractMechanics LienPayment Disputes
as a GC, do we even have to care of an owner files an Affidavit of Completion? To lien, we have to file by the 15th day of the 4th month following unpaid
draw, so January unpaid, means we file lien by May 15 and so on. Fund trapping notice (retention) is to be filed following completion, so we woul...Read More
...Read More
Anonymous Contractor
1 answerAdd commentApr 3, 2018
TexasMechanics LienRetainage
I am building a new house. I have a Builder that holds the Mechanic's Lien rights. I would like to contract directly with each tradesman instead of having those
contracts go through the Builder. Is that allowed? I plan to secure Lien Waivers from each tradesman. In this case, I'd be listed for both "the pers...Read More
...Read More
Anonymous Contractor
1 answerAdd commentApr 3, 2018
TexasConstruction ContractMechanics Lien
We are a equipment rental company. If we contracted directly with the property owner and they have stopped paying us and no notices have been sent. Do
we have lien rights regardless? The project was entered in Zlien and the equipment is still on their site.
...Read More
Anonymous Contractor
1 answerAdd commentMar 29, 2018
TexasMechanics LienPreliminary Notice
I am a contractor and I hired a sub contractor to perform a work for a house that I am remolding. the subcontractor did not finish the work in the time
agreed ( March 17, 2018) in writing. in the contract I have a penalty of $500 for every day after March 17, 2018. I have also a clause stating that ...Read More
...Read More
Anonymous Contractor
1 answerAdd commentMar 25, 2018
TexasConstruction ContractMechanics LienPayment Disputes
I'm in Texas trying to start small aerial construction company. Took a verbal agreement with company that stated: He would cover housing for two crews,
supply trucks fuel equipment and pay us per foot on install, footage price on tree trim and set price to move or make ready at set price. I have e...Read More
...Read More
Anonymous Contractor
1 answerAdd commentFeb 27, 2018
TexasConstruction ContractMechanics LienPayment Disputes
Water mitigation company that dried out two homes and performed labor and mitigation services....Read More
Anonymous Contractor
1 answerAdd commentFeb 15, 2018
TexasLien DeadlinesMechanics Lien
I ask this because the monthly notices are for select invoices, which do not reflect the entire balance due. If the customer did not pay us, would we only be
able to lien on the amount reflected in the monthly notice value? We, of course, would want to have the ability to lien on the entire balance unpaid.
...Read More
Anonymous Contractor
1 answerAdd commentFeb 9, 2018
TexasMechanics LienPreliminary Notice
We rented a machine for earthwork performed on a project. This machine broke down several times causing us downtime while they fixed the machine on
the jobsite. We cannot bill the customer for repairs not caused by operator error, but the equipment company is charging me and threatening to ...Read More
...Read More
Anonymous Contractor
1 answerAdd commentJan 31, 2018
TexasConstruction ContractMechanics Lien
Own a fire /water/mold restoration company. We rendered water mitigation service for a home owner that is insurance based, and we have received 6 of a
$12,000 bill. We have all documentation needed to prove service has been rendered. How much time do we have?
...Read More
Anonymous Subcontractor
1 answerAdd commentJan 29, 2018
TexasMechanics LienPreliminary Notice
I'm an equipment lessor in Texas. In your system, the lien claim deadline is triggered by "Date Labor or Materials Last Delivered". Is that the date that we first
deliver the equipment to the job site? Or do I use the date that the rental equipment is returned to us? Or some other date?
...Read More
Anonymous Contractor
1 answerAdd commentJan 25, 2018
TexasLien DeadlinesMechanics Lien
We gave the contractor foot print and ask for a bid. He redrew he own foot print just like the one we send him and gave us a bid to built . we rejected his bid
and send him a note that we went we someone else. He is threatening to put a lien on the property. Requesting $500.00 for the foot print.
...Read More
Anonymous Contractor
1 answerAdd commentJan 24, 2018
TexasMechanics Lien
We currently have a customer that owes us balances on a job in TX from Septemeber, October, and Nov. We did our letters for 2nd month and 3rd month but
January was 4th month from supply on the September invs. Did miss our lien rights on this job since we did not lien by 1/15?
...Read More
Anonymous Subcontractor
1 answerAdd commentJan 19, 2018
TexasLien DeadlinesMechanics LienPreliminary Notice
I have been in contact with the legal representative for Pumpco and he raised a concern that an individual was named on the lien. I need to know if this is
going to potentially create a bigger mess than the remedy. He certainly thinks so, but I have no idea because I am not a lawyer. Is naming g an in...Read More
...Read More
Anonymous Contractor
1 answerAdd commentJan 4, 2018
TexasMechanics Lien