I was hired to do work on a house when it was halfway finished, they brought someone else in to finish it, When I talked to them about it, I got a response that no work was finished, How does one get paid for work that was performed. I did talk with the home owners, he said he hired one company to d...Read More...Read More
We bought a house on a tax sale and it has a Mechanic's lien on it. The lien has not been renewed for years and we would like to sell the home, however the lien is still on it. My understanding is that the lien must be renewed every 6 months to be considered active so we should be able to get it remov...Read More...Read More
Our client only owes us retainage / retention left for a project in which we agreed to allow the General Contractor to withhold this retainage. We only have 4 days left to file a mechanic's lien before the deadline for Missouri. Are we able to file a lien for retainage? Can you file a lien prior to the state's li...Read More...Read More
I'm confused about the following; "In Missouri, according to RSMo § 429.080, a mechanics lien must be filed within 6 months “after the indebtedness shall have accrued”. Missouri courts have interpreted the time the indebtedness accrued to be the date of the claimant’s last furnishing labor and/or ...Read More...Read More
We are a material and labor subcontractor in Missouri. The majority of our materials are pre-engineered building systems (specially fabricated materials). In some instances, our customers (general contractors or end-use owners) hire us to provide materials only because of our ability to procure and cl...Read More...Read More
we worked on a project at 45th & summit and billed it as one invoice but there were four buildings- 4500, 4502, 4504, & 4506. Do i have to do a notice of intent and mechanics lien per bldg or can i include them all on one?...Read More
I am renting to own a property and she is getting it appraised to take a loan out on it after I have invested 30k dollars. I want to put a lein on it so she can't do that and chance losing it through her defaultin on the loann...Read More
Lien is expiring soon and I need to know what to do next. I have not received any monies due me. And I want to know if my property manager who is in Callaway County, Missouri can continue precedings as my Agent. This would be different than original County of filling....Read More
Subcontractor has filed a lien against a private project that we are the GC on. This claim is in dispute, but we would like to release the lien from the property via a bond. Wasn't sure of the law in MO and if it allowed for such....Read More
I've already paid them 90% of what is owed, very early and then immediately when invoiced. The remaining is only because they did not include an additional invoice at the time. Now, they damaged my floors and are reimbursing me, but they will not give me the check until I've paid them...and today th...Read More...Read More
I have a client that I have provided a home plan for. Have a contract and finished the job, in which he paid my retainer and that is all. I have an outstanding invoice which he has fail to pay. I have made numerous calls and emails with no success. He was going to purchase some acreage to put his n...Read More...Read More