Menu
Home>Levelset Community>Legal Help>Is it true that a sub that doesn’t file a preliminary notice cannot lien the property (it’s residential)?

Is it true that a sub that doesn’t file a preliminary notice cannot lien the property (it’s residential)?

CaliforniaLien DeadlinesPreliminary Notice

20 day prelim notice

3 replies

Jun 30, 2020
Yes, that's true. You still have contract rights against the GC. Good luck. Carlton & Alberola and/or Andrew Carlton have not been retained by the recipient of the above comment and, moreover, the above comment does not create an attorney-client relationship. The above is general commentary based on limited and insufficient information. If you wish to obtain legal advice, please contact Andrew Carlton at 949-954-6666 x101, or by email at andrew@cnalawfirm.com.
0 people found this helpful
Helpful
Jun 30, 2020
Yes. Very true.
0 people found this helpful
Helpful
Jun 30, 2020
Yes, under California mechanics lien laws anyone who didn't contract directly with the property owner must provide a preliminary notice within 20 days of first furnishing labor or materials to the project. Failure to provide this 20-day prelim is fatal to your mechanics lien rights. However, if you missed the 20-day deadline, there is still an opportunity to secure some lien rights. This notice can be sent later than 20 days after the first furnishing date. However, this late notice will only secure lien rights for the value of labor or materials provided in the 20 days prior to the notice, and the remainder of the project. It can be better to secure some lien rights, instead of none at all. If the project has already completed, then you will be unable to file a mechanics lien to secure payment. But that doesn't mean you are completely out of options. You can still file a lawsuit against the party who hired you under claims such as breach of contract. Also, depending on the amount in dispute, these claims can be brought up in California Small Claims Courts. Good luck!  
0 people found this helpful
Helpful