Yes, there is a deadline to file to enforce the mechanic's lien. Generally, per Virginia's Mechanic's Lien Law, any suit to enforce must be filed within 6 months from recording the lien. If the project is still ongoing, that time frame will continue until 60 days from the completion or termination of the project.
Disclaimer: This communication does not constitute legal advice, is not an engagement for the provision of legal services, is not a consultation, and does not form an attorney-client relationship between Katz Law, LLC and yourself or any other person or entity. In all cases, any particular outcome or resSee More...See More...
1 person found this helpful
Helpful
Anonymous General Contractor
Question Author
Apr 27, 2020
Thank you! The amount is fairly small, so a law suit may not be ideal. If we do not enforce the lien, and the house will be placed for sale a couple of years from now, will the lien stand?