The state of Nevada does not require a Notice of Commencement to be filed on either public or private projects. For GC's working in Nevada, the only time a notice is "required" is when working on a residential project. This is a Notice of Intent to Lien, which must be sent at least 15 days before filing a mechanics lien.
For more information, you may find these resources helpful:
NOTE. The information presented here is for informational purposes only. It is not legal advice and should not be construed nor relied upon as such. Furthermore, this posting does not create an attorney-client relationship. If you need legal advice, seek the counsel of a licensed, local attorney.See More...See More...