I am the owner of a new construction (completed Aug. 2021) home in GA that has a lien filed from painters in February of 2022. It is for $ owed from the builder (not the owner) for invoices not paid up until June of 2021. The work that the painters did in February 2022 is primarily punch list and repa...Read More...Read More
I sent the original proposal to Fortify Holdings, LLC. I did work on four hotels and our agreement was that I was to be paid for each property upon completion. They paid me for the first three hotels and a partial payment for the last one but they still owe me $3488.00 and it has been over a month since I...Read More...Read More
I was recently told that Home Improvement Contractors (i.e., kitchen remodel) are not allowed to provide a Time & Materials contract - that the contract must be a set price and any changes to the scope of work/price must be covered with a Change Order. I'm looking for the statute or ordinance t...Read More...Read More
I have a current scenario in which the Contractor provided me a time frame of 3-4 months to complete a job. It has been over a year and was still not completed. During that time frame (9 Months in) the ROC was contacted, opened a case and had an onsite review with ROC, and principals. Duri...Read More...Read More
Client is unhappy with their GC’s pace of work, the GC is still performing, but behind schedule . They want me to take over the job, but the GC has yet to be terminated. What kind of legal risks am I facing from the client AND the GC in this situation?...Read More
I am a contractor who did some work for an apartment complex back in March of this year. The maintenance supervisor at the time signed my contract which provides for arbitration as an option for nonpayment. I did not file a lien because I was in contact with the Manager who assured me that p...Read More...Read More
from The 5 Main Types of Contracts in Construction What are the construction contracts that obligate the contractor to own the money before signing the contract? , And what are the contracts that obligate the owner to own the money before signing the contract? I hope I formulated the question well...Read More
We have been in different phases of this project as we are a plumbing subcontractor. A pre-limb notice was not served within the first 20 days of starting project and it has taken a year. We have several projects with the same situation from the same contractor. However we have been on the proje...Read More...Read More