South Dakota Bond Claim Overview

South Dakota

Preliminary Notice Deadlines
None / not applicable.

South Dakota

Bond Claim Deadlines
Prime contractors cannot file a claim against their own bond.

South Dakota

Preliminary Notice Deadlines
None / not applicable.

South Dakota

Bond Claim Deadlines
120 Days

Must file lien claim within 120 days from completion and final acceptance of the project, but best practice (for maximum protection) is to send claim within 20 days of last furnishing. Lawsuit to enforce due 1 year from final completion and acceptance of the project.

South Dakota

Preliminary Notice Deadlines
None / not applicable.

South Dakota

Bond Claim Deadlines
120 Days

Must file lien claim within 120 days from completion and final acceptance of the project, but best practice (for maximum protection) is to send claim within 20 days of last furnishing. Lawsuit to enforce due 1 year from final completion and acceptance of the project.

South Dakota Bond Claim FAQs

Claim FAQs

Who is protected under South Dakota Bond Claim Laws?

In South Dakota, all parties who furnish labor and/or materials to the general, or to first-tier subcontractors, are entitled to make a bond claim. It is unclear whether parties more remote than those contracting with a first-tier sub are entitled to protection.

When is the deadline to file a South Dakota Bond Claim?

Contract Funds: The claim must be filed within 20 days of the claimant’s last furnishing or labor and/or materials to be fully protected. If the 20-day deadline is missed, the claim will generally be limited to the amount due to the general contractor at the time the claim is made. However, if the claimant a “settlement and statement of account” from the general contractor, signed and verified by the contractor, the full amount of the claim may be protected even if the 20-day period is missed. Finally, if the general contractor files a notice to file claims, all claims are due within 120 days of the publishing of that notice.

Bond Claim: The bond claim must be received more than 6 months, but less than 1 year after completion and final settlement of the contract. Note, however, that specific requirements of the bond will be held to control, so obtaining a copy of the bond is generally best practice.

Who should receive the South Dakota Bond Claim?

Contract Funds: The claim must be provided to both the officer of the contracting public entity, and the general contractor.

Bond Claim: The bond claim must only be given to the contracting public entity.

When is the deadline to initiate suit, or, how long is my South Dakota Bond Claim effective?

Contract Funds: Generally suit must be filed within 30 days of acceptance of claimant’s work, but if the contractor publishes a notice to file claim, suit must be initiated within 120 days of publication of the notice.

Bond Claim: Suit must be initiated more than 6 months, but less than 1 year after completion of the project. However, if any other party has already initiated a suit – the claimant must join that suit as an intervener within 1 year of final acceptance of the project.

What must the South Dakota Bond Claim include?

Contract Funds: The only information specifically required to make a claim on the contract funds is a verified statement of account due after allowing credits.

Bond Claim: A bond claim in South Dakota must include an affidavit stating that materials for the prosecution of work were supplied by the claimant, that claimant has not been paid. After receipt, the public body must send a copy of the bond to the claimant.

For both claims, it may be advisable to also include a description of the labor and/or materials supplied, and to identify the project and the hiring party.

How must the South Dakota Bond Claim be sent?

Contract Funds: Must be filed with the public entity, and delivered to the general contractor.

Bond Claim: Must be furnished to the contracting public entity. This is generally held to mean delivered by either certified or registered mail, or by personal service.

South Dakota Public, State and County Project Preliminary Notice FAQs

Need More Help with South Dakota Bond Claims? We're Here.

Ask an Expert for Free

Check Out Our Payment Experts
Construction attorneys: Courtney Stricklen, Christopher Ng, Andrea Goldman, and Peter Ryan

Recent Questions & Answers About South Dakota Claims

what can we do now?

Contractor was doing unsatisfactory work and it was one delay after another. I found while checking L and I that the contractors license had been...

What legal action do I have for a Municipal Project completed in Newington, CT?

I'm a subcontractor of a sub contractor who is contracted directly with the General Contractor. We've completed the project and were paid a partial amount....

Can a sub contractor file to collect a payment from our Bond – we are behind in paying after COvid 19

We are the GC.. In this Covid 19 we are behind on paying a roofing subcontractor He has filed a claim against our Bond We...

How to file a lien in South Dakota

Need to file a South Dakota mechanics lien? File your mechanics lien with Levelset, the lien experts quickly and easily. Or you can follow the 3 steps below to file a lien yourself with Levelset's free information.
File with the Mechanics Lien Experts
We’re the Mechanics Lien experts. With us it’s fast, easy, affordable, and done right!
File Now

South Dakota Bond Claim Free Forms

Notice of Intent to Make Bond Claim Form - free from

Notice of Intent to Make Bond Claim Form

A Notice of Intent to Make Bond Claim is not a required document, but it can be a powerful one. By sending this notice, a...

Get Form Now

Helping Thousands of South Dakota Contractors Like You
With Bond Claims & Getting Paid