Washington Preliminary Notice Guide and FAQs

Ready? Build Your Free Washington
Preliminary Notice Now

Send A Notice Now
Washington Preliminary Notice FAQs

About Washington Preliminary Notice

Washington Preliminary Notice Rules
At a Glance


  • Private Jobs
  • Public Jobs
  • Top Links
Icon_Form_Required
Preliminary Notices Are Required

Preliminary notice is required, but the type depends on the project and participant role.


0
DAYS
GCs Must Send Notice

Under some circumstances, Notice to Owner required before commencing work. Model Disclosure Statement due before work begins on all residential projects of over $1,000; and commercial projects between $1,000 and $60,000.


60
DAYS
Subcontractors Must Send Notice

Notice of Right to Claim Lien within 60 days from first delivering labor or materials.

NOTE, that on the new construction of a single-family home, the Notice to Owner should be delivered within 10 days of first providing labor or materials to the project.


60
DAYS
Suppliers Must Send Notice

Notice of Right to Claim Lien within 60 days from first delivering labor or materials.

NOTE, that on the new construction of a single-family home, the Notice to Owner should be delivered within 10 days of first providing labor or materials to the project.


icon-can
Notice Can Generally be Sent Late

A late notice in all commercial cases, and on a remodel, alteration, or repair of an owner-occupied single-family residence will protect your lien rights for 60 days prior to the date the Notice was delivered. In the case of a new construction of a single-family home, a late notice will protect your lien rights for the 10 days preceding the delivery of the notice.


Icon_SearchContractor
Send to Owner and GC

Preliminary notice on Washington should always be given to the property owner. Notice form project participants that did not contract directly with the property owner must also be delivered to the GC.

Icon_Form_Required
Preliminary Notice Required

Washington requires any party furnishing materials, supplies, or provisions to any subcontractor to send preliminary notice to the general contractor to preserve the right to prosecute a bond claim.


X
N/A

On public jobs, any claims for non-payment are made against the general contractor's bond. Since GCs will not make a claim against their own bond for non-payment, they do not have bond claim rights, and have no preliminary notice requirement.


10
DAYS
Subs Must Send Notice

Subs must deliver Notice to Contractor to the prime contractor within 10 days if contracted with a sub or sub-sub.


10 or 60
DAYS
Suppliers Must Send Notice

Suppliers must deliver Notice to Contractor to the prime contractor within 10 days if contracted with a sub or sub-sub.


icon-can't waive lien rights
Notice Cannot be Sent Late

When required, failure to give the preliminary notice timely is fatal to a bond claim in Washington.


Icon_SearchContractor
Send to GC

The preliminary notice, when required, must be delivered to the general contractor.

Preliminary notice is required, but the particular notice required depends on the project type and participant role in Washington.

Parties that did not contract directly with the property owner are required to provide the owner with a “Notice to Owner.”

Project participants who did contract directly with the property owner are required to provide the owner a “Model Disclosure Statement” when the work:

  1. involves the repairing, altering or building of 4 or fewer residential units on residential property and the bid price is $1,000 or more, or
  2. when the work to be done is on a commercial building and the bid price is between $1,000 – 60,000.

A detailed discussion of this is found in the article, “Deliver the Model Disclosure Statement or Else.

Note that parties who only furnishing labor, are not specifically required to send a Washington preliminary notice (though a Model Disclosure statement will still be required for those parties contracting directly with the owner).

This “labor only” exception is a bit less known, which is that it protects at least some work performed by subcontractors who should have sent off a preliminary notice, but didn’t. So, here is the deal:

1)  If you furnish only labor to a project, you do not need to deliver preliminary notice in Washington state.

2) If you furnish only materials to a project, you always need to deliver preliminary notice in Washington state, and if you don’t deliver this notice, you’ll have no lien rights whatsoever.

3) If you furnish labor and materials to a project, you are supposed to deliver preliminary notice in Washington state, but if you don’t deliver this notice, you’ll have a right to file a mechanics lien related to your labor only.

However, if there is any material component to the contract or furnishing, preliminary notice is required to protect the ability to later file a mechanics lien if one becomes necessary. In a circumstance in which project participant is providing labor and materials, it may be possible to file a lien for the labor portion of the work (and exclude the materials cost) without a preliminary notice… however, it is a best practice to avoid this need.

As you can see, there are a few nuances associated with the preliminary notice requirements in Washington. More information can be found in the article Is Notice Required Before Filing A Construction Lien? Washington Law.

Preliminary Notice Frequently Asked Questions

There are a lot of things that you need to know if you're sending preliminary notices in Washington, and it's important to get all the details right. If you're receiving prelims, it's important to know what you're looking at and know what to do in followup. Since prelims are subject to a lot of complex rules and requirements, this can be a difficult and tedious task. Here are some frequently asked questions (and their answers) about the Washington preliminary notice process.

Prelim FAQs on Private Projects

Do I Need to Send a Washington Preliminary Notice?

If you did not contract directly with the owner, you are required to provide the owner with a “Notice to Owner.”

If you contracted directly with the owner, you are required to provide the owner a “Model Disclosure Statement” when your work involves the repairing, altering or building of 4 or fewer residential units on residential property and the bid price is $1,000 or more, or when the work to be done is on a commercial building and the bid price is between $1,000 – 60,000. A detailed discussion of this is found in the article, “Deliver the Model Disclosure Statement or Else.

Note that if you are only furnishing labor, you need not send a Washington preliminary notice (though a Model Disclosure statement will still be required if you contracted directly with the owner). However, if there is any material component to the contract or furnishing, preliminary notice is required to protect your full mechanics lien rights. In the circumstance when you are providing labor and materials, it may be possible to file a lien for the labor portion of the work (and exclude the materials cost) without a preliminary notice…however, it is a best practice to avoid this need.  For more, see:  You Don’t Need Preliminary Notice in Washington for Labor Portion of Work.

As you can see, there are a few nuances associated with the preliminary notice requirements in Washington. We published this helpful article way back in 2007 (!), yet it is still useful in evaluating all of these nuances and helping you understand if notice is required on a Washington project:  Is Notice Required Before Filing A Construction Lien? Washington Law.

When do I Need to Send a Washington Preliminary Notice?

If you did not contract directly with the owner, the “Notice to Owner” can be sent at any time, but it only protects your rights to claim a lien for a limited period of time prior to delivery of the notice. To fully preserve your lien rights, the Notice to Owner must be delivered within 60 days of the date labor or materials were first furnished to the property for all commercial cases, and on a remodel, alteration, or repair of an owner-occupied single-family residence. If your work was the new construction of a single-family home, the Notice to Owner should be delivered within 10 days of first providing labor or materials to the project.

If you contracted directly with the Owner, the “Model Disclosure Statement” must be delivered prior to the initiation of work. The statement must be signed by the Owner, and you must retain a copy of the signed document for at least three years.

What if I Send the Washington Preliminary Notice Late?

If you miss the required date and deliver the Notice to Owner late, all is not necessarily lost.

A late notice in all commercial cases, and on a remodel, alteration, or repair of an owner-occupied single-family residence will protect your lien rights for 60 days prior to the date the Notice was delivered.

In the case of new construction of a single-family home, a late notice will protect your lien rights for the 10 days preceding the delivery of the notice.

How Should the Washington Preliminary Notice be Sent?

If you contracted directly with the owner, the “Model Disclosure Statement” must be delivered to, and signed by, the owner.

If you are delivering a “Notice to Owner”, it may either be sent to the owner via certified or registered mail, or personally delivered to, or served on, the owner. If the notice is personally delivered or served to the owner, a signed receipt from the owner or an affidavit of service is required.

Do I Have to Send the Washington Preliminary Notice to Someone Other than the Owner?

If you did not contract directly with the prime contractor, notice must also be given to the prime contractor.

An interesting situation arises when working on condominium projects in Washington state. At the start of a condo project, it’s possible that the entire facility is owned by a single development company. However, this may not be the case, and if work is being performed on common elements after the units have already been sold, the condominium project may be owned by an assortment of different parties. This creates a complicated legal question about who must receive the preliminary notice. This head scratcher is discussed in more detail to help you determine which parties should and should not receive notice in the article “Who Gets Preliminary Notice When Working On A Condominium Complex in Washington?”

Is the Washington Preliminary Notice Requirement met when sent or delivered?

If sent by registered or certified mail, the notice is considered delivered three days after mailing, excluding Saturdays, Sundays, and legal holidays.

Prelim FAQs on Public Projects

Do I Need to Send a Washington Preliminary Notice?

It depends. Washington requires any party furnishing materials, supplies, or provisions to any subcontractor to send preliminary notice to the general contractor to preserve the right to prosecute a bond claim.

When do I Need to Send a Washington Preliminary Notice?

When required, the preliminary notice must be delivered or mailed to the general contractor no later than 10 days from the date of claimant’s first furnishing of labor and/or materials to the project.

What if I Send the Washington Preliminary Notice Late?

When required, failure to give the preliminary notice timely is fatal to a bond claim in Washington.

How Should the Washington Preliminary Notice be Sent?

Washington statutes provide no concrete answer to how the preliminary notice must be sent. However, it appears that actual receipt is necessary. It is likely advisable to send the notice via certified or registered mail, or have it served personally.

To Whom Must the Washington Preliminary Notice be Given?

The preliminary notice, when required, must be delivered to the general contractor.

Need More Help with Washington Preliminary Notices?

Ask an Expert for Free

Check Out Our Payment Experts

Recent Questions & Answers
About Washington Preliminary Notices

Is a mechanics lien the right thing to file when a customer fails to claim upholstery work

I restore antique textiles. A customer commissioned to restore an antique textile. The customer blocks my calls and doesn't respond too my emails. The customer...

I signed a waiver of lien for regions bank there is a balance of 12,600.00 owed to me I spoke with the insurance company

Today and they told me that the claim had been paid in full so that means that regions name did not get put on the...

Do I need to ensure that subcontractors are paid before releasing final payment to the GC?

As a public entity, do I need to ensure that the subs are paid by the GC?

Washington Preliminary Notice Form Template

The Washington preliminary notice forms are regulated by statute. This doesn’t mean that the form has to look a certain way, but it does mean that the document must contain certain required information. The forms provided here for free by Levelset are compliant with the Washington rules. You can download them for free, or use our system to send or request them easily.

Washington Model Disclosure Statement Form - free from

Washington Model Disclosure Statement Form

This disclosure statement is given to the consumer (customer) from the contractor showing they are registered in the state of Washington. The consumer (customer) signs...

Get Form Now

Washington Notice to Owner (Preliminary Notice) Form - free from

Washington Notice to Owner (Preliminary Notice) Form

The Washington Notice to Owner — also known as a Notice of Right to Claim Lien — is a type of preliminary notice. Washington state...

Get Form Now

Washington Notice to Contractor Form - free from

Washington Notice to Contractor Form

On a Washington Public Works Project, a notice must be sent to preserve your claim against the bond, and against the retainage. The notice must...

Get Form Now

Helping Thousands of Contractors Like You
With Washington Preliminary Notices