My documents are being mailed today/tomorrow to all parties. The customers lawyer reached out today and sent a copy of our check and is requesring we bring the final lien waiver and collect the check. Do we try to have the lien released now or let it go thru and then have it removed (assuming the...Read More...Read More
when a subcontractor files a pre lien, and the GC wants us to provide a Lien release, do you go back to the same date the prelien was filed ? or before ?...Read More
I sent a lien for our project called RCloud. Since I sent the lien, the GC has made one progress payment. We are still owed $218,602.80 which includes unbilled retention. The GC is asking if I've updated the lien amount to reflect the new balance since they made a payment. Is this something I n...Read More...Read More
Great. I'm trying to figure out something. We're a concrete service business(Sub). We mainly estimate our projects with materials and concrete costs. However, we started a project where we only did the labor work and the contractor was responsible to pay for materials and concrete cost. How...Read More...Read More
As the GC, we paid a subcontractor for an invoice, in full, and subsequently terminated their contract, but we have never received an "Unconditional Waiver" from them. What do we do if one is never sent?...Read More
Hi, I'm new to the flooring Sub contracting industry and I don't know the exact difference between a conditional and unconditional waiver? I think I'm just not fully grasping the concept for some reason. If our GC's require vendor waivers for the previous month, to be summitted during the current mont...Read More...Read More
We have a GC that is holding payment until we provide them with executed contracts from our subcontractors. We have already provided them with notarized lien wiavers from our subs stating they are paid through the date of our pay app and we dont owe them anything. Are we obligated to ...Read More...Read More
This company is trying to sell this location but can't because there is a lien still on file. we had signed an unconditional waiver for the amount they had paid of 19k leaving a balance of 47k. Since we signed the waiver when picking up the first check, does that mean we don't have lien rights If we decide t...Read More...Read More
What is the Minnesota statue that addresses the following: Minnesota specifically forbids the waiving of the right to file a mechanics lien or make a claim against a payment bond prior to the actual receipt of payment. Any such waiver is void and unenforceable. However, the statute specifically not...Read More...Read More
I filed a Texas bond claim for the amount of $20,996.00 for payment application #3. The GC reached out to me and offered me a check for $5,000.00 for PA#3 and for me to sign a conditional lien waiver on progress payment to release the check to us and once we deposit the check the GC wants a...Read More...Read More
We get various lien waivers from our general contractors. Some have the invoice # listed on lien waiver for which the payment is being made. Even though the project may not be complete (we may do additional work and bill for that work), the payment is "in full" for the referenced invoice(s). In that ...Read More...Read More
Hi -- One of the contractors we do work with is asking us to revise a Conditional Waiver on Progress Payment. Specifically what they are asking is that in the Exceptions section, the date indicated be the through date of the invoice associated with the waiver issued, not the date that the waiver was issu...Read More...Read More
Who is the subcontractor? K&B HOME AND LAND PRESERVATION. I'm the owner . Who is the general contractor or the contractor above them? A company out of Florida. (SOUTHERNCAT IS ABOVE THEM). Which company are you with? K&B HOME AND LAND PRESERVATION (SUB CONTRACTOR FOR th...Read More...Read More