I filed a lien on a project and it was recorded on 10/12/2018. Another company that has gone unpaid has filed a lien on 8/24/2018 and filed for a foreclosure on this claim. Being that they filed a lien claim before us would they get paid first?...Read More
started interior plumbing on a house and was fired, as was the original plumber. No reason given. I understand that he can file a complaint with the state but I'm not worried about that, I wouldjust like to get the money owed me for doing half the job....Read More
Association began balcony reconstruction project but home owners have to hire contractor. Contractor made his proposal, customer signed it, association approved it and village gave permit for construction. After construction is dun, village inspector made final report confirming that everything is pr...Read More...Read More
American Industrial Werks was contracted to disassemble and reassemble a clean room in IL. The customer transported the equipment once it was packed and stored it in a location in IL. The warehouse was next door to the location that it would be rebuilt. AIW rebuilt the clean room at the new loc...Read More...Read More
We built a house and closed on the property with a punch list three years ago. The builder still has work he needs to complete. The painter came and finished most of his part of the punch list. That was over a year ago. Today, the Painter sent an email to list of owners he did work for and copie...Read More...Read More
We received a lien notice almost 2 years ago (Illinois). We didn't respond to it because we believed the contractor would not perfect it and didn't want to contest it. The appendix A is important because according to the contract all additions had to approved of in writing and I don't know if what is re...Read More...Read More
I did concrete slab for a storage facility. The owner used to be my landlord and he requested the work to be done. He asked for a cost in and I gave the price based on the square footage he told me ($10K). Once, at the job site, the square footage turned to be more than what he said so he verbally agr...Read More...Read More
We need to file a Service Affidavit, with our Circuit Clerk of DuPage county office, for work done on a Construction Vehicle. We performed the work. The owner did not pay so we filed a Mechanics Lien. The owner has since gone out of business and moved out of country. We are needing to title the ...Read More...Read More
Draw #6 appears to be a final draw with my contract-previous paid-this payment=0 but I know a Change Order is going to be issued for Draw #7 that will increase my contract. Am I okay to issue a Final Waiver for Draw #6 and a second Final waiver for Draw #7 as long as my contract value increas...Read More...Read More
U was hired by an out of town owner to sealcoat a commercial parking lot. I emailed a detailed bid and he called me to discuss it further. He explained that he just wanted to dress it up . I told him what I could do and how much it would cost to go that route. He sent me a down payment and was happ...Read More...Read More
We hand laid 2125 sq ft of asphalt for a company and when we finished the job they complained about the asphalt not meeting up with the top of the concrete. They never stated that was how they wanted it and its not written in the contract that way....Read More
We filed a lien with Zlien and the customer hired an atty to write us a letter to drop it or else. He said that we were beyond the date of being able to file a lien. Contract is dated 1/28/17 and we filed the lien 7/2/18, nineteen months later. NO WORK WAS DONE ON THIS CONTRACT, BUT WE ORDERED THE ...Read More...Read More
We are a prime contractor in IL and filed a lien on a customer who signed a contract on 1/28/2017 for custom / specially fabricated bath materials. Our contract gives the customer 3 days to cancel the job, but if they cancel past the 3 days, we will file a lien. This customer requested we hold off un...Read More...Read More