Menu

Georgia Mechanics Lien Questions

All Status
Mechanics Lien
Georgia
I've recently filed a mechanics lien on a property and I would like to know what the next steps will be to ensure we get paid promptly? On our contract with
them we would get paid 90% of final amount and then 10% once the property was sold. Since they haven't paid us the 90% is it my right to dema...Read More
...Read More
Ramiro Neto
1 answerAdd commentJan 19, 2023
GeorgiaConstruction ContractMechanics Lien
HI, My question is does my contractor have the right to file a mechanics lien on my house, if unlicensed. The total job was $55k. we have paid him $32500. He
also has added $10k of extra work we never approved. Bottom line, there have been many, many mistakes discovered with inspections, etc. We ...Read More
...Read More
Anonymous Contractor
1 answerAdd commentDec 19, 2022
GeorgiaMechanics Lien
I am a contractor in ga. that was assited by legvelset to place a lien on a customer back in august of 2020 i was just notified that leveset is not a legal firm
and is unable to asist in this matter
...Read More
Larry Birdsong
1 answerAdd commentJan 11, 2023
GeorgiaMechanics Lien
Contractor told us they were licensed, gave us fake licenses. Did a horrible job. Walked off. Now want payment on an unfinished job. 90% of project was
paid.
...Read More
Anonymous Contractor
1 answerAdd commentJan 9, 2023
GeorgiaMechanics Lien
I installed removed all old flooring and base trim, door trim and shoe molding along with an island in the kitchen in preparation for a new floor install. I then
installed the new flooring, reinstalled the baseboard and shoe molding, door trim, kitchen island, and custom cut the flooring during the install. R...Read More
...Read More
undefined undefined
1 answerAdd commentDec 27, 2022
GeorgiaMechanics Lien
I am a kitchen and bath contractor that provides material and the labor to homeowners and the contractors. One of my builders that i know him since 2016
recently had some issues and it’s been keep delaying the payment on a project that we have completed on August 4th. I’ve been waiting on him ...Read More
...Read More
Emre Yurdakul
1 answerAdd commentDec 22, 2022
GeorgiaMechanics Lien
I have a Lien against an ex clients property. The Lien is for failing to make good on work that was done on his property. I hava a lien claim number 441141361
filed by Levelset on my behalf, Apalachee Painting and Construction.
...Read More
Anonymous General Contractor
4 answersAdd commentOct 5, 2020
GeorgiaMechanics LienPayment Disputes
I have a lien on a residential property the customer filed a contest of lien. What do I have to do now and how long do I have to do it before the lien is no
longer any good? Can I file a suit in small claims court?
...Read More
Anonymous Contractor
1 answerAdd commentAug 5, 2020
GeorgiaMechanics Lien
My company is the HOA and one of our owners has an outstanding balance of $690 for dues. My boss has requested me to file a Mechanics Lien on the
property for the amount of the current balance. Is this the correct process when trying to collect HOA Dues?
...Read More
Anonymous Contractor
1 answerAdd commentAug 19, 2020
GeorgiaLien on FundsMechanics Lien
I missed filing a Mechanics Lien with in the 90 days. What is the next step I need to take to try and recover my payment?...Read More
Anonymous Contractor
1 answerAdd commentOct 27, 2022
GeorgiaLien DeadlinesMechanics LienRecovery OptionsRight to Lien
I'm a subcontractor in who was hired to install cabinets in a new house in the state of Georgia. I did the majority of the installation in December 2021, with
the intent to return after countertops and tile had been installed. Before these installations took place, the contractor declared bankruptcy and I ...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 14, 2022
GeorgiaMechanics Lien
I am the owner of a new construction (completed Aug. 2021) home in GA that has a lien filed from painters in February of 2022. It is for $ owed from the
builder (not the owner) for invoices not paid up until June of 2021. The work that the painters did in February 2022 is primarily punch list and repa...Read More
...Read More
Anonymous Contractor
Waiting for answerAdd commentAug 11, 2022
GeorgiaConstruction ContractMechanics Lien
I did a garage door replacement that this customer begged me to do even after suggesting to get other estimates ect. (Initial conversation about the job
November 2021, Door ordered March 2022, Received and installed by May 13th 2022) when the door finally arrived, the very next day we were o...Read More
...Read More
Ronnie Lee
Waiting for answerAdd commentSep 5, 2022
GeorgiaMechanics Lien