We completed a change order. To submit it with our month requisition for payment, I see it can be on it's own separate continuation sheet instead of changing the SOV for every CO. Is that correct and Is it subject to retainage as well?

MassachusettsChange OrdersSchedule of Values
Anonymous Contractor

We are a small electrical contractor on a large commercial job. It looks like there will be several Change Orders going forward. I don't have much experience with Change orders.

1 reply

Levelset Admin at Levelset
| 997 reviews
Aug 8, 2019
That's a great question. Regarding updating the schedule of values with change orders - if the specifics on billing change orders aren't set out in the contract, it might be helpful to ask the customer how they should be billed. While the customer's word might not be gospel, if they have a preferred method that makes logical sense and doesn't negatively impact your rights, that might be the best way to determine how to proceed considering that one of the common reasons for a payment application being rejected is the organization of the application, itself.

Generally, though - change orders are reflected both by updating the schedule of values and the continuation sheet. And, amounts owed for change orders will generally be treated like other billable amounts, and as a result, retainage will typically apply.
The information presented here is not legal advice and should not be construed as such. Rather, this content is provided for informational purposes. Do not
act on this information as if it is advice. Further, this post does not create any attorney-client relationship. If you do need legal advice, seek the helSee More...
See More...
0 people found this helpful
Helpful