Home>Levelset Community>Legal Help>Maine-subcontractor has 90 days to file but prime contractor has 120 so can prime file lien after 90 days if sub did wk
Maine-subcontractor has 90 days to file but prime contractor has 120 so can prime file lien after 90 days if sub did wk
prime contractor filed lien within 120 days but it was really a subcontractor doing work
so if prime contractor last day was more than 120 days but subcontractor was within 120 days but past 90 days
is this invalid
The information presented here is not legal advice and should not be construed as such. Rather, this content is provided for informational purposes. Do not act on this information as if it is advice. Further, this post does not create any attorney-client relationship. If you do need legal advice, seek the helSee More...See More...