if I sign a lien waiver when I get paid do I have to provide lien waivers from every one I paid?

ColoradoLien Waivers

trying to get paid final payments

1 reply

Dec 14, 2018
That's a great question, and ultimately, whether lien waivers will be necessary is ultimately up to the highest tiers of the project. Meaning, if the property owner, developer, or GC demands that lien waivers be collected all the way down the chain, then they might withhold payments until all lien waivers are collected. In such a situation, collecting lien waivers from lower tiers could help to facilitate payments.