How should we position our deductive change order on a commercial project in Hawaii?

HawaiiChange Orders
Anonymous Contractor

I am in a state contract on a commercial building and our original bid had GL Insurance as a line item Client elected to do insurance direct and we need to do a deductive CO to them Should they get just the amount listed on the breakdown under GL Insurance or should they get credit for General conditions and or Overhead & profit

1 reply

Levelset Admin at Levelset
| 1,005 reviews
Apr 10, 2020
I'm not sure I totally understand the situation. But, if the contract originally called for general liability insurance and that no longer has to be secured - then whatever amount was originally included in the bid to cover the GL policy should probably just be deleted as an item on the bid. If you're still unsure, it could be useful to consult with an attorney on the matter to have them read the relevant documentation and make sure that's the best way for proceeding.
The information presented here is not legal advice and should not be construed as such. Rather, this content is provided for informational purposes. Do not
act on this information as if it is advice. Further, this post does not create any attorney-client relationship. If you do need legal advice, seek the helSee More...