We send out our preliminary notices for all jobs we wish to have a claim on retention for, but do we need to also send the monthly notices for the invoices billing that retention? A customer was under the impression that we have no claim on retention and therefore cannot send the monthly notices, however I am pretty sure we can issue notices for retention. I wanted to confirm with you and possibly gain some insight as to reasoning and rules.

2 replies

Levelset Admin at Levelset
| 1,003 reviews
Aug 22, 2019
Texas monthly notices include the unpaid balance between the party sending the notice and their customer. Because retainage represents amounts that the construction business has earned but has not been paid for, including retainage amounts in a monthly notice is acceptable. In fact, under § 53-057(a) of the Texas property code (which creates the Notice for Contractual Retainage requirement), the right to recover retainage amounts can be preserved by monthly notice, by sending a Notice for Contractual Retainage, or by sending both. It makes logical sense that monthly notices can include retainage. Even if retainage isn't expected until some later date, it is an amount that's been earned but remains unpaid. And, unless that amount was shown through a monthly notice or through a retainage notice, the right to ultimately file a mechanics lien on that retainage amount, if necessary, would not be available. So, Texas construction businesses can preserve their right to claim a mechanics lien on retainage amounts by including retainage in monthly notices, by sending a Notice for Contractual Retainage, or by doing both. I hope this was helpful! For more background on Texas lien claims, notices, and retainage requirements: Texas Lien Construction Payment Resources.
The information presented here is not legal advice and should not be construed as such. Rather, this content is provided for informational purposes. Do not
act on this information as if it is advice. Further, this post does not create any attorney-client relationship. If you do need legal advice, seek the helSee More...
See More...
0 people found this helpful
Helpful
Managing Partner at Miller, Ross, & Goldman
| 18 reviews
Mar 5, 2020

I wanted to follow-up and confirm you’ve been paid all your company's retainage on these project matters.

If I can further assist your company with any unpaid invoices, please feel free to call or email. My firm can collect for you even when lien rights have expired or were never pursued.

Mike Ross Miller, Ross & Goldman mross@mrgpartners.com (512)275-6412 Direct https://www.mrgpartners.com/levelset
0 people found this helpful
Helpful