An owner/management company requested a lien waiver from my subcontractor after the project was complete and the sub was already paid. It was an
unconditional lien waiver and signed by the sub, as I interpret, relinquishing lien rights no matter what the value stated. It was returned to me by ...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 12, 2017
IllinoisLien Waivers
Do I need to file a mechanics lien? Or do I need to do some other kind of contract agreement. I did some construction work on my friends house a couple
years ago and he was going to pay me when he was able to get the money to do so. He has decided to sell his house and I want to make sure t...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 12, 2017
TexasConstruction ContractLawsuitMechanics LienPayment Disputes
Due to the fact that Oregon has the shortest preliminary notice deadline in the country, it causes issues on the time necessary to complete the processing of
shipment/invoicing and then give enough time to enter the project, allow for research, and file a preliminary notice. I keep seeing that to "be safe...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 12, 2017
OregonLien DeadlinesMechanics LienPreliminary Notice
A notice of Mechanics Lien Claim came in the mail, but it was for only $300. Pennsylvania states liens can only be placed that exceed $500. How do I get it
removed using this knowledge?
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 11, 2017
PennsylvaniaLien ReleasesMechanics Lien
I have sent a notice of intent to lien to all parties as required by Illinois law. What I didn't do, was send the 60 day preliminary notice for an owner occupied
project (which this was). My question is do I still have to/ or should I send the 60 day preliminary notice even though I have a ready sent a notice of intent ?
...Read More
Anonymous Contractor
1 answerAdd commentSep 11, 2017
IllinoisLien DeadlinesPreliminary Notice
I recently placed an order for a NOI to lien. When I was hired as a sub-contractor the house was completely gutted(so no one lived there). Would I still need to
do a 60 day preliminary notice when the owners moved out temporarily while construction was going on and only moved back in when the certifi...Read More
...Read More
Anonymous Contractor
2 answersAdd commentSep 8, 2017
IllinoisLien DeadlinesPreliminary Notice
Client owes for three months work, and has not paid. I have a contractors license in California...Read More
Anonymous Contractor
1 answerAdd commentSep 9, 2017
CaliforniaMechanics Lien
STATE OF NEW YORK- Worked on a State Project, GC got paid for my work. Can I file a Mechanics lien on the property in addition to a Bond Claim? Thank you...Read More
Anonymous Subcontractor
1 answerAdd commentSep 8, 2017
New YorkBond ClaimsMechanics Lien
We have multiple jobs where we file a 2nd, then 3rd, then its time for the 4th. We currently do not aggregate all outstanding debt for that job to the fourth
month notice we file the fourth, and then any subsequent filings for the additional 2nd and 3rd months notices as required. Our concern is what ...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 7, 2017
TexasLien DeadlinesMechanics LienPreliminary Notice
I have an LLC in MO and contracted with a large General Contractor also in Missouri to complete a half done project in Louisville, KY. The owner of the
Louisville property pre-funded my payroll and materials with cash which was to be paid back as my invoives were paid through the monthly draw...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 7, 2017
KentuckyLien DeadlinesMechanics LienPayment DisputesPreliminary Notice