So we supplied material to a job in Oregon. The job is with the Hood River Co. School District. I sent out a preliminary notice when we sent the material. The
job was billed on 7-18-17. I call the Contractor that we are supplying to and they said that they haven't been paid yet by the school district. Shou...Read More
...Read More
Anonymous Contractor
1 answerAdd commentSep 21, 2017
OregonBond ClaimsLien DeadlinesMechanics Lien
I hope this question isn't confusing. We have a client that we have worked for for years and they are having financial difficulty. We have about 4 open
projects we are currently working on for them. Can I file a lien for the total amount due now even though some of the work will be performed in ...Read More
...Read More
Anonymous Contractor
1 answerAdd commentSep 21, 2017
TexasBankruptcyLien DeadlinesMechanics LienPayment Disputes
We have a job where the customer has unpaid balances outside of the contract amount. Can I file separate pre liens for those items? If I send out a pre lien
at one amount, and it changes, how can I update a pre lien?
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 20, 2017
CaliforniaLien DeadlinesPreliminary Notice
Transpacific Recycling LLC incurred charges for equipment to clean up the yard of tire debris. They're attorney is iclaiming I have no right to file a lien
because I am not a licensed contractor, a landscape architect, nor a licensed design professional. I was contracted by the President of the comp...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 19, 2017
CaliforniaLawsuitMechanics LienPayment DisputesRecovery Options
I have a client that I have provided a home plan for. Have a contract and finished the job, in which he paid my retainer and that is all. I have an outstanding
invoice which he has fail to pay. I have made numerous calls and emails with no success. He was going to purchase some acreage to put his n...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 19, 2017
MissouriLawsuitMechanics LienPayment DisputesRecovery Options
Our company's corporate office is located in Las Vegas but we have an office in AZ. If we were to file a lien in AZ and needed to provide the license number,
would we provide the branch or state number?
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 18, 2017
ArizonaMechanics Lien
I am a senior citizen and have a grant from my USDA mortgage holder to get some capital improvements in my home. The heating contractor was aware of
this before the work was done to replace to rusted out baseboard heaters in my basement. At the time of work completion; namely 6pm on a Fri...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 18, 2017
New YorkConstruction ContractLawsuitPayment Disputes
60 days ago, we drew for 50% retention on a project that was closer to 80% done. They paid the material and labor draw but refused the retention draw
saying they'd pay it all at the end. The contract is now 100% complete with no complaints. Our contract does state they have 60 days for final re...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 15, 2017
GeorgiaRetainage
Thank you for the previous response. I do not see where the attorney made any missteps so far as far as timelines and notifications and all of that. I was
hoping you could tell me, just based upon the facts that I gave you, if the lien was invalid, and if so, how I can demand that it be removed. I sent ...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 15, 2017
CaliforniaConstruction ContractPayment Disputes
Probably not a question you can answer, but we had a contractor take material from a job site, and use it on another job, that he was not authorized to use it
on. Then he started buying product for the new job, and we would like to file a notice of furnishings on it. We are well within the 21 days to file th...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 14, 2017
OhioLien DeadlinesPreliminary Notice
My question is this: we have a lien against a client that did not pay for work completed. I filled out and filed the paperwork, and, the sheriff went to serve him
the paperwork. Letter received from sheriff states that he went to the house twice, once left a card and the other time no one was there. So, wh...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 14, 2017
South CarolinaMechanics Lien
We are involved in a situation where it looks like a foreclosure sale is imminent on a property with several outstanding liens (mechanics and mortgage). Our
mechanics' lien was recorded after several other mechanics' liens. We are wondering whether the fact that our lien was recorded after other lie...Read More
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 14, 2017
ColoradoLien PriorityMechanics Lien
Delivery of equipment was on a Friday, began work on following Tuesday and completed the job 20 days after work began or would it be 24 days from
equipment delivery. I did not file a NTO, and GC is not paying me for work performed. Can I still file a NTO?
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 14, 2017
FloridaLien DeadlinesPreliminary Notice