Iowa Retainage Requirements
- Private Jobs
- Public Jobs
- Top Links
Retainage Limit
Not Regulated by State Law
Pay Period
Not Regulated by State Law
There's No Process to Recover
N/A
Not Held In Escrow
In Iowa, contractors and owners do not need to hold retainage funds in a separate escrow account.
5 Percent
Retainage cannot exceed 5% of the estimated labor/material furnished.
30 Day Pay Period
Funds shall be released within 30 days of when payment to contractor becomes due. Payment to a subcontractor must be made no later than (1) 7 days after the contractor receives payment; or (2) "A reasonable time after the contractor could have received payment for subcontractor’s work, if the reason for nonpayment is not the subcontractor's fault."
There is a Process to Recover
Claim must be filed with public entity within 30 days of final acceptance - period can be extended if full contract price unpaiud.
Retainage, also called “retention,” is an amount of money “held back” from a contractor or subcontractor during the course of a construction project. In general, retainage serves two main purposes:
- To provide an incentive to the contractor or subcontractor to complete the project; &
- To give the owner some protection against problems like liens, contractual defaults, delays, and more.
In most states, laws exist to regulate how the parties use the retainage concept, mostly protecting some parties against abuse of the tool from others. The following are resources, legal information, and answers to frequently asked questions about Iowa’s retainage requirements.
Iowa’s retainage limits & deadlines
Iowa does not regulate retainage practices on private projects, so the amount withheld and the timing of its release will be determined by the terms of the contract between the parties.
On public projects, the maximum amount of retainage that can be withheld is no more than 5% of each progress payment. Upon 30 days of completion and acceptance of the project, if no claims have been made against the retained funds, the public entity must release retention to the GC. Once received, retainage must be released to subs and suppliers within 7 days.
Also, once a portion or all of the improvement has reached substantial completion, the contractor may submits a request for early release of retainage. If no claims have been made against the retained funds, and no more labor and/or materials need to be provided to the project, the retainage funds should be released.