Illinois Notice of Intent to Lien Questions

All Status
Notice of Intent to Lien
Illinois
I sold kitchen cabinets to McDowell of St Charles a General Contractor. I did not recieve payment in full. Since then they sold, new owners McDowell
Acquistion said they only bought the assets not the liabilty and I should go after McDowell of St. Charles. Is this correct? Thank you
...Read More
Anonymous Subcontractor
1 answerAdd commentMar 4, 2020
IllinoisNotice of Intent to Lien
We have a client that is not paying for work completed so we just want to supply an intent to lien subcontractors supplying materials for Illinois...Read More
Anonymous Contractor
1 answerAdd commentFeb 10, 2020
IllinoisNotice of Intent to Lien
Hello, I own & operate a very new landscaping company. Do I need to give a lien to clients in IL that I am doing landscaping work at their home? What is the
benefit of a lien, what does it cost, and how exactly does it work & protect me? Thank you very much
...Read More
Anonymous General Contractor
1 answerAdd commentJan 26, 2020
IllinoisMechanics LienNotice of Intent to LienPreliminary NoticeRecovery OptionsRight to Lien
Am I required to file an intent to lien in ILLINOIS? Thank you...Read More
Anonymous Contractor
1 answerAdd commentJan 3, 2020
IllinoisNotice of Intent to Lien
I was awarded a judgement in Cook County Civil Court for $3000.00 as a ProSe litigant. The Defendant performed sub-standard renovations in my condo,
which have been corrected. Defendant has not paid after 30 business days. Prior acts of not responding to calls, Demand Letter, appearances f...Read More
...Read More
Anonymous Contractor
1 answerAdd commentDec 19, 2019
IllinoisNotice of Intent to Lien
We have performed work on a commercial building in Lake County< IL. 1. Notice of lien rights was not served upon beginning work. 2. Additional work was
performed more than 4 months after the original contract work was completed, but less than 90 days of completion. 3. Are we still within the 90-...Read More
...Read More
Anonymous Contractor
1 answerAdd commentOct 8, 2019
IllinoisConstruction ContractLien DeadlinesMechanics LienNotice of CompletionNotice of Intent to LienRight to Lien
We repaired floors at a food processing plant in Morton MS and the general contractor on the job has my invoice on hold and will not take our calls. The
owner in Mississippi was very please with our work and we did not hear of any issues.
...Read More
Anonymous Subcontractor
1 answerAdd commentSep 19, 2019
IllinoisMechanics LienNotice of Intent to LienPayment Disputes
After I retired, someone asked me to remodel a building. Basement, First and Second Floor. The amount I requested when finished is extremely low. Even
so, I was paid part of it. Mechanics Lien has been filed for over $8000.00. They offer half the amount. I don't want to accept. My attorney says ...Read More
...Read More
Anonymous Contractor
1 answerAdd commentJul 17, 2019
IllinoisMechanics LienNotice of Intent to LienRecovery OptionsRight to Lien
I was working on a project in Illinois as a subcontractor. The GC is based in Missouri. I no longer work for the GC. He will not pay me for my final two weeks of
employment. He is trying to change the agreement we had for the previous 6 weeks. He wants me to rewrite two invoices to show a lesser amou...Read More
...Read More
Anonymous Contractor
1 answerAdd commentJul 11, 2019
IllinoisMechanics LienNotice of Intent to LienPayment DisputesPrompt PaymentRecovery OptionsSlow Payment
30 days behind on 60 hrs of pay and next Friday behind on another paycheck, I am a contractor subbed to a sub-contractor LH piping . I need to know what
information I need to get and what process to go through in order to get paid. The company is in Illinois where the work took place, the sub-contr...Read More
...Read More
Anonymous Contractor
1 answerAdd commentMay 26, 2019
IllinoisMechanics LienNotice of Intent to LienRecovery Options
My husband did Electrical work and owner is not paying general contractor. The owner still owes $3,000 to my husband. Sent an intent to lien...Read More
Anonymous Contractor
1 answerAdd commentApr 23, 2019
IllinoisLien DeadlinesNotice of Intent to Lien
I sent a notice of intent to lien for a public project in Illinois, and the GC I mailed it to is not signing the receipt. What do I need to do at this point?...Read More
Anonymous Contractor
1 answerAdd commentFeb 16, 2019
IllinoisNotice of Intent to Lien
I have a real estate investor customer who will not answer the door for the mailman to accept my certified U.S. Mail letter of Notice To File Mechanic's Lien.
The work was completed about 90 days so I have 30 days left to file. I have proof that the customer viewed my final Quickbooks invoice and als...Read More
...Read More
Anonymous Contractor
1 answerAdd commentJul 24, 2018
IllinoisNotice of Intent to Lien
I'm not an attorney and new at completing the lien paperwork. Since we generally do not work for the property owner, but the tenants. I'm new to
this...Completing the Notice of Intention to File Lien in IL BDA is the GC or Prime Contractor and Claimant. Doing a remodel for a Franchisee in a ...Read More
...Read More
Anonymous Contractor
1 answerAdd commentJun 1, 2018
IllinoisNotice of Intent to Lien