In New Mexico, the deadline for a prime contractor to file a mechanics lien is 120 days after the completion of the project. For those who were not hired directly by the property owner - like a subcontractor or supplier - the deadline is a mere 90 days after the completion of the project.
For more background on New Mexico's mechanics lien rules, here are some great resources:
(1) New Mexico Mechanics Lien Guide and FAQs(2) How to File a New Mexico Mechanics Lien – A Step by Step Guide to Get You Paid
The information presented here is not legal advice and should not be construed as such. Rather, this content is provided for informational purposes. Do not act on this information as if it is advice. Further, this post does not create any attorney-client relationship. If you do need legal advice, seek the helSee More...See More...